RoR capacity, peaking capacity and benefit

Short answer

(i) 123.4 MW. (ii) 277.7 MW. (iii) Extra benefit ≈ Rs 3.70 million per day (≈ Rs 111 million per month).

The mean monthly flow of a typical Nepalese river is as follows:

MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)807483100130222600800590240120100

i) Calculate the installed capacity of a plant based on the minimum flow of the river without pondage (if the plant is designed for a pure run-of-river plant) with net head of 200 m and overall efficiency of the plant 85%. ii) The plant has three sets of units (turbine and generator) such that one unit with full capacity is operated during off-peak hours. If the plant is designed as a peaking plant with 4 hour peaking (morning 2 hour and evening 2 hour), what will be the installed capacity of the plant? iii) What will be the increase in benefit from peaking if the peak hour energy rate is Rs 12/kWh and the off-peak energy rate is Rs 6/kWh during the minimum flow month?

i) Pure run-of-river plant

Minimum flow is 74 m³/s (February).

P1=9.81×0.85×74×200=123,410 kW=123.41 MWP_1 = 9.81\times0.85\times74\times200 = 123,410\ \text{kW} = 123.41\ \text{MW}

ii) Peaking plant with three units, 4 h peaking

One unit (discharge QuQ_u) runs at full load for the 20 off-peak hours; all three units (3Qu3Q_u) run for the 4 peak hours. Daily water balance on the minimum flow of 74 m³/s:

20 Qu+4 (3Qu)=24×74⇒32 Qu=1776⇒Qu=55.50 m3/s20\,Q_u + 4\,(3Q_u) = 24\times74 \Rightarrow 32\,Q_u = 1776 \Rightarrow Q_u = 55.50\ \text{m}^3/\text{s}

Peak discharge =3Qu=166.50=3Q_u=166.50 m³/s.

P2=9.81×0.85×166.50×200=277,672 kW=277.67 MWP_2 = 9.81\times0.85\times166.50\times200 = 277,672\ \text{kW} = 277.67\ \text{MW}

(Each unit is 92.56 MW. Check storage: off-peak stored =(74−55.5)×20=370=(74-55.5)\times20 = 370 m³/s·h; peak draw =(166.5−74)×4=370=(166.5-74)\times4=370 m³/s·h, equal.)

iii) Increase in benefit during the minimum flow month

Daily energy is the same in both cases (24×123.41=2,96224\times123.41 = 2,962 MWh).

  • RoR (constant output): 4 peak hours at Rs 12 and 20 off-peak hours at Rs 6 per kWh:
B1=123,410×(4×12+20×6)=Rs 20,732,846 per dayB_1 = 123,410\times(4\times12+20\times6) = \text{Rs }20,732,846\text{ per day}
  • Peaking plant: B2=92,557×20×6+277,672×4×12=Rs 24,435,140B_2 = 92,557\times20\times6 + 277,672\times4\times12 = \text{Rs }24,435,140 per day

Increase =3,702,294=3,702,294 Rs/day ≈\approx Rs 3.70 million per day, or about Rs 111.1 million for a 30-day month.

Answer: (i) 123.4 MW; (ii) 277.7 MW; (iii) extra benefit ≈ Rs 3.70 million per day (≈ Rs 111 million per month).