Skip to main content

Chapter 3 · 6 hours

Power and Energy Potential study

IOE past exam questions

Past questions and answers

24 questions set from this chapter. Most repeated first.

  • 2079 Baishakh · 2+2+2+2+4 marks

A hydropower plant is planned to be designed in a Nepalese river, where mean monthly flows for a typical year are as follows.
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)4.43.93.44.24.216.578.1108.952.822.09.96.4
Other data: design discharge = 18 m³/s; full supply level = 2250 masl; turbine centerline = 1650 masl; diameter of 4 km long tunnel = 3 m, f = 0.014; diameter of 1 km long penstock = 2.2 m, f = 0.012; hydraulic efficiency = 95%, turbine efficiency = 93%, generator efficiency = 99%, transformer efficiency = 99%. Considering only the frictional loss, (i) Compute the installed capacity, primary and secondary energy to be produced from the power plant assuming that 10% of the minimum monthly flow is to be released downstream. What is the plant factor? (ii) The developer is interested in developing a daily peaking reservoir for 4 hours. What will be the capacity of the reservoir to satisfy the daily peaking requirement?

Similar questions: Installed capacity, energy and daily peaking reservoir (2072) (2072 Chaitra)

Answer

Data and approach

Gross head =2250−1650=600= 2250-1650 = 600 m. Only friction loss is considered. Overall efficiency η=0.95×0.93×0.99×0.99=0.8659\eta = 0.95\times0.93\times0.99\times0.99 = 0.8659 (hydraulic × turbine × generator × transformer). Energy is computed month by month (730 h per month), with the friction loss recalculated for the flow used.

Head loss at design flow Qd=18Q_d = 18 m³/s (Darcy-Weisbach)

Tunnel: A=π4(3)2=7.069A=\frac{\pi}{4}(3)^2 = 7.069 m², V=2.546V = 2.546 m/s

hf,t=fLDV22g=0.014×40003×2.54622×9.81=6.17 mh_{f,t} = f\frac{L}{D}\frac{V^2}{2g} = 0.014\times\frac{4000}{3}\times\frac{2.546^2}{2\times9.81} = 6.17\ \text{m}

Penstock: A=π4(2.2)2=3.801A=\frac{\pi}{4}(2.2)^2 = 3.801 m², V=4.735V = 4.735 m/s

hf,p=0.012×10002.2×4.73522×9.81=6.23 mh_{f,p} = 0.012\times\frac{1000}{2.2}\times\frac{4.735^2}{2\times9.81} = 6.23\ \text{m}

Net head at QdQ_d: Hn=600−6.17−6.23=587.60H_n = 600-6.17-6.23 = 587.60 m. (Loss varies as Q2Q^2 for smaller flows.)

(i) Installed capacity, energy and plant factor

Environmental release =10%×=10\%\times minimum monthly flow =0.1×3.4=0.34=0.1\times3.4=0.34 m³/s, so the flow available for power is Q−0.34Q-0.34.

P=9.81 η Hn Qd=9.81×0.8659×587.60×18=89,846 kW=89.85 MWP = 9.81\,\eta\,H_n\,Q_d = 9.81\times0.8659\times587.60\times18 = 89,846\ \text{kW} = 89.85\ \text{MW}
MonthQ (m³/s)Q − 0.1QminQ usedNet head (m)Power (MW)Energy (GWh)
Jan4.44.064.06599.420.6715.09
Feb3.93.563.56599.518.1313.23
Mar3.43.063.06599.615.5911.38
Apr4.23.863.86599.419.6514.35
May4.23.863.86599.419.6514.35
Jun16.516.1616.16590.080.9959.12
Jul78.177.7618.00587.689.8565.59
Aug108.9108.5618.00587.689.8565.59
Sep52.852.4618.00587.689.8565.59
Oct2221.6618.00587.689.8565.59
Nov9.99.569.56596.548.4435.36
Dec6.46.066.06598.630.8122.49
  • Total annual energy =447.73= 447.73 GWh
  • Primary (firm) energy, from the minimum available flow 3.063.06 m³/s (available in every month): 136.54136.54 GWh
  • Secondary energy =447.73−136.54=311.19=447.73-136.54 = 311.19 GWh
  • Plant factor =447.73×10689.85×103×8760=0.569=\dfrac{447.73\times10^6}{89.85\times10^3\times8760} = 0.569 (56.9%)

(ii) Reservoir for 4-hour daily peaking

In the driest month the available inflow is Qin=3.06Q_{in} = 3.06 m³/s. The plant is to run for 4 hours a day at the design flow of 18 m³/s and store water in the other 20 hours. The daily inflow is 264,384 m³ and the peak use is 18×4×3600=259,20018\times4\times3600 = 259,200 m³, which is slightly smaller, so 4-hour peaking at 18 m³/s is possible.

During the 4 peak hours the draw-down from the reservoir is

V=(Qd−Qin)×t=(18−3.06)×4×3600=215,136 m3≈2.15×105 m3V = (Q_d - Q_{in})\times t = (18-3.06)\times4\times3600 = 215,136\ \text{m}^3 \approx 2.15\times10^5\ \text{m}^3

The same volume must be stored in the 20 off-peak hours (3.06×20×3600=220,3203.06\times20\times3600 = 220,320 m³ available), so it fills in time.

Answer: P = 89.8 MW; total energy = 447.7 GWh; primary energy = 136.5 GWh; secondary energy = 311.2 GWh; plant factor = 0.57; pondage volume ≈ 215,136 m³ (≈ 2.15 × 10⁵ m³).

  • 2072 Chaitra · 5+2+3 marks

A hydropower plant is to be planned in a Nepalese river, where the mean monthly flows for a typical year are as follows:
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)4.43.93.44.25.616.578.1108.952.822.09.96.4
Other data pertaining to the plant: design discharge = 18 m³/s; full supply level = 2250 masl; turbine center line = 1650 masl; diameter of 4.0 km long tunnel = 3.0 m, f = 0.014; diameter of 1.0 km long penstock = 2.2 m, f = 0.012; hydraulic efficiency = 95%; turbine efficiency = 93%; generator efficiency; transformer efficiency = 99%. Considering only frictional loss, a) Compute the installed capacity, primary and secondary energy to be produced from the power plant assuming that 10% of the minimum flow is to be released downstream. What is the plant factor? b) The developer is interested in developing a daily peaking reservoir for 4 hours. What will be the capacity of the reservoir to satisfy the daily peaking requirement?

Similar questions: Installed capacity, energy and daily peaking reservoir (2079) (2079 Baishakh)

Answer

The generator efficiency is missing in the question; it is assumed to be 99%, the same as the transformer (all other data as given).

Data and approach

Gross head =2250−1650=600= 2250-1650 = 600 m. Only friction loss is considered. Overall efficiency η=0.95×0.93×0.99×0.99=0.8659\eta = 0.95\times0.93\times0.99\times0.99 = 0.8659 (hydraulic × turbine × generator × transformer). Energy is computed month by month (730 h per month), with the friction loss recalculated for the flow used.

Head loss at design flow Qd=18Q_d = 18 m³/s (Darcy-Weisbach)

Tunnel: A=π4(3)2=7.069A=\frac{\pi}{4}(3)^2 = 7.069 m², V=2.546V = 2.546 m/s

hf,t=fLDV22g=0.014×40003×2.54622×9.81=6.17 mh_{f,t} = f\frac{L}{D}\frac{V^2}{2g} = 0.014\times\frac{4000}{3}\times\frac{2.546^2}{2\times9.81} = 6.17\ \text{m}

Penstock: A=π4(2.2)2=3.801A=\frac{\pi}{4}(2.2)^2 = 3.801 m², V=4.735V = 4.735 m/s

hf,p=0.012×10002.2×4.73522×9.81=6.23 mh_{f,p} = 0.012\times\frac{1000}{2.2}\times\frac{4.735^2}{2\times9.81} = 6.23\ \text{m}

Net head at QdQ_d: Hn=600−6.17−6.23=587.60H_n = 600-6.17-6.23 = 587.60 m. (Loss varies as Q2Q^2 for smaller flows.)

(i) Installed capacity, energy and plant factor

Environmental release =10%×=10\%\times minimum monthly flow =0.1×3.4=0.34=0.1\times3.4=0.34 m³/s, so the flow available for power is Q−0.34Q-0.34.

P=9.81 η Hn Qd=9.81×0.8659×587.60×18=89,846 kW=89.85 MWP = 9.81\,\eta\,H_n\,Q_d = 9.81\times0.8659\times587.60\times18 = 89,846\ \text{kW} = 89.85\ \text{MW}
MonthQ (m³/s)Q − 0.1QminQ usedNet head (m)Power (MW)Energy (GWh)
Jan4.44.064.06599.420.6715.09
Feb3.93.563.56599.518.1313.23
Mar3.43.063.06599.615.5911.38
Apr4.23.863.86599.419.6514.35
May5.65.265.26598.926.7619.54
Jun16.516.1616.16590.080.9959.12
Jul78.177.7618.00587.689.8565.59
Aug108.9108.5618.00587.689.8565.59
Sep52.852.4618.00587.689.8565.59
Oct2221.6618.00587.689.8565.59
Nov9.99.569.56596.548.4435.36
Dec6.46.066.06598.630.8122.49
  • Total annual energy =452.92= 452.92 GWh
  • Primary (firm) energy, from the minimum available flow 3.063.06 m³/s (available in every month): 136.54136.54 GWh
  • Secondary energy =452.92−136.54=316.38=452.92-136.54 = 316.38 GWh
  • Plant factor =452.92×10689.85×103×8760=0.575=\dfrac{452.92\times10^6}{89.85\times10^3\times8760} = 0.575 (57.5%)

(ii) Reservoir for 4-hour daily peaking

In the driest month the available inflow is Qin=3.06Q_{in} = 3.06 m³/s. The plant is to run for 4 hours a day at the design flow of 18 m³/s and store water in the other 20 hours. The daily inflow is 264,384 m³ and the peak use is 18×4×3600=259,20018\times4\times3600 = 259,200 m³, which is slightly smaller, so 4-hour peaking at 18 m³/s is possible.

During the 4 peak hours the draw-down from the reservoir is

V=(Qd−Qin)×t=(18−3.06)×4×3600=215,136 m3≈2.15×105 m3V = (Q_d - Q_{in})\times t = (18-3.06)\times4\times3600 = 215,136\ \text{m}^3 \approx 2.15\times10^5\ \text{m}^3

The same volume must be stored in the 20 off-peak hours (3.06×20×3600=220,3203.06\times20\times3600 = 220,320 m³ available), so it fills in time.

Answer: P = 89.8 MW; total energy = 452.9 GWh; primary energy = 136.5 GWh; secondary energy = 316.4 GWh; plant factor = 0.58; pondage volume ≈ 215,136 m³ (≈ 2.15 × 10⁵ m³).

  • 2080 Baishakh · 4 marks

How do you estimate the gross and net hydropower potential between two sections of a river?

Answer

Gross potential is the theoretical power of the river between two sections, using all the flow and the full head difference with 100% efficiency. Net potential is the power that can actually be developed after deducting head loss, efficiency and the part of the flow that cannot be used.

Gross potential

Divide the reach into small sub-reaches where the flow is nearly constant (the flow increases downstream with tributaries and catchment area). For each sub-reach:

Pgross=∑ρgQiΔHi=∑9.81 Qi ΔHi  (kW)P_{gross} = \sum \rho g Q_i \Delta H_i = \sum 9.81\, Q_i\, \Delta H_i \ \ (\text{kW})

where QiQ_i is the mean flow (m³/s) and ΔHi\Delta H_i is the drop in elevation (m) of the sub-reach. Annual energy = P×8760P \times 8760 kWh. Flow comes from the flow series at the two sections (area-ratio method for ungauged sites), and elevations from topographic maps or survey.

Net (technical/economic) potential

  • Choose the design discharge QdQ_d from the flow duration curve (e.g. Q40Q_{40} for RoR), after leaving the environmental flow.
  • Net head Hn=Hgross−hfH_n = H_{gross} - h_f, where hfh_f includes the intake, desander, waterway and penstock losses (about 5-10% of gross head).
  • Overall efficiency η\eta of the turbine, generator and transformer (about 80-90%).
Pnet=9.81 η Qd Hn  (kW)P_{net} = 9.81\, \eta\, Q_d\, H_n \ \ (\text{kW})
  • Annual energy is found from the monthly flows up to QdQ_d. Economic potential is the part for which benefit-cost ratio is greater than one.
  • 2080 Bhadra · 4 marks

How do you optimize the plant capacity of a RoR project? Discuss.

Answer

The installed capacity of a RoR plant is optimised by comparing the extra cost and the extra benefit of each increase in capacity. Since flow varies throughout the year, a bigger plant uses the large flow only for a short time, so there is an optimum point.

Procedure

  1. Prepare the flow duration curve (FDC) from the long-term flow series (after the environmental release).
  2. Select a number of trial design discharges QdQ_d (e.g. Q30Q_{30}, Q40Q_{40}, Q50Q_{50} ...). For each, compute the power P=9.81 η Hn QdP = 9.81\,\eta\,H_n\,Q_d and the energy:
E=∑9.81 η Hn min⁡(Qi,Qd) tiE = \sum 9.81\,\eta\,H_n\,\min(Q_i,Q_d)\,t_i
  1. Compute annual benefit = energy × price (firm and secondary energy may have different prices).
  2. Compute annual cost = (fixed cost + variable cost × P) × capital recovery factor + O&M. Fixed cost includes the headworks, civil structures, access and so on; variable cost is proportional to the capacity (turbine, generator, penstock).
  3. Plot the net benefit (benefit − cost), the benefit/cost ratio and the marginal values against the capacity.

Criterion

  • Maximum net benefit (NPV), or
  • Marginal benefit = marginal cost: increase capacity until the extra benefit from the last kW (= price × energy produced by it during the time it is used) equals its extra annual cost. Beyond this point the machines run only a few weeks per year and do not pay back.

Other considerations: the cost per kW, the plant factor (usually 50-70% for RoR), the grid demand, the risk and the possibility of staged development.

  • 2082 Bhadra · 10 marks

The mean monthly flow of a river at the headworks site of a ROR hydropower project is as follows:
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)908580952005001,0001,200800450150100
The other data are as follows: net available head = 150 m; efficiency of turbine = 95%; efficiency of generator = 97%; fixed cost = NRs. 10,00,00,00,000; variable cost (present worth value) = NRs. 1,50,000/kW; energy price = NRs. 10 per unit; interest rate = 10%; economic life of the project = 45 years. Estimate the best installed capacity, firm energy, secondary energy, total energy, and power factor of the project.

Answer

Optimum capacity of a RoR plant is where the marginal benefit of the last unit of capacity equals its marginal cost (equivalently the net benefit is maximum). The fixed cost does not change with capacity, so it does not affect the optimum.

Data and constants

  • Fixed cost = NRs 10,00,00,00,000 (= NRs 10,000 million); variable cost = NRs 1,50,000/kW (present worth); price = NRs 10/kWh
  • Turbine 95%, generator 97%, so η=0.95×0.97=0.9215\eta = 0.95\times0.97 = 0.9215; no O&M cost is given
  • "Power factor" in the question is read as the plant factor.
  • Net head H=150H = 150 m; overall efficiency η=0.9215\eta = 0.9215
  • Capital recovery factor CRF=i(1+i)n(1+i)n−1=0.10139CRF = \dfrac{i(1+i)^n}{(1+i)^n-1} = 0.10139 for i=10%i=10\%, n=45n=45 years
  • Energy per month: Em=9.81 η H Q (730 h)E_m = 9.81\,\eta\,H\,Q\,(730\ \text{h}) (8760/12 h per month)
  • Annual cost =(fixed+variable×P) CRF=(\text{fixed}+\text{variable}\times P)\,CRF; annual benefit = energy × price

Flow available for power

available flows (m³/s) in descending order: 1200, 1000, 800, 500, 450, 200, 150, 100, 95, 90, 85, 80.

Marginal check

Each extra 1 kW of capacity above the flow level is used only in the months in which the flow is greater than the capacity flow. Benefit of 1 kW used for kk months =0.73 k= 0.73\,k MWh × price. Benefit per kW for each month it is used = 730 kWh × NRs 10 = NRs 7,300; so a kW must be used for at least 2.08 months, i.e. at least 3 months in a year, to pay for itself. The 3rd highest flow is 800 m³/s, so capacity beyond 800 m³/s (used only 2 months) is not justified.

Trial design discharges

QdQ_d (m³/s)P (MW)Energy (GWh)Benefit (NRs M)Cost (NRs M)Net (NRs M)
80108.48950.289,502.82,663.76,839.0
85115.261,004.7210,047.22,766.87,280.3
90122.041,054.2110,542.12,870.07,672.2
95128.821,098.7610,987.62,973.18,014.5
100135.601,138.3511,383.53,076.28,307.3
150203.401,484.8114,848.14,107.310,740.7
200271.201,781.7717,817.75,138.512,679.2
450610.193,019.1130,191.110,294.119,896.9
500677.993,217.0832,170.811,325.320,845.5
8001,084.794,107.9641,079.617,512.123,567.5
10001,355.994,503.9145,039.121,636.623,402.5
12001,627.184,701.8947,018.925,761.221,257.7

The net benefit is greatest at Qd=800Q_d = 800 m³/s.

Results

  • Installed capacity: P=9.81×0.9215×150×800=1,084,790 kW=1,084.79P = 9.81\times0.9215\times150\times800 = 1,084,790\ \text{kW} = 1,084.79 MW
  • Firm (primary) energy, from the minimum flow 80 m³/s all year: 9.81×0.9215×150×80×8760=950,275,865 kWh=950.289.81\times0.9215\times150\times80\times8760 = 950,275,865\ \text{kWh} = 950.28 GWh
  • Total energy: 4,107.964,107.96 GWh
  • Secondary energy =4,107.96−950.28=3,157.69= 4,107.96-950.28 = 3,157.69 GWh
  • Plant factor =EP×8760=4,107.96×1061,084,790×8760=0.432= \dfrac{E}{P\times8760} = \dfrac{4,107.96\times10^6}{1,084,790\times8760} = 0.432 (43.2%)

Answer: best installed capacity = 1,084.8 MW (design flow 800 m³/s); firm energy = 950.3 GWh; secondary energy = 3,157.7 GWh; total energy = 4,108.0 GWh; plant factor = 0.43.

  • 2082 Baishakh · 9 marks

The mean monthly flow of a river in a typical year is as follows:
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Flow (m³/s)383328231836739368534843
The effective head of the ROR plant is 48 m and can be assumed constant. The other data are as follows: fixed cost = USD 2795 × 10⁶; variable cost = US$ 645/kW; annual O&M cost = 2.5% of variable cost; energy price = US$ 38/MWh for primary and secondary energy; interest rate = 11%; economic life of the project = 45 years; overall efficiency = 89%. Determine the best installed capacity, firm energy, secondary energy, total energy, and plant factor.

Answer

Optimum capacity of a RoR plant is where the marginal benefit of the last unit of capacity equals its marginal cost (equivalently the net benefit is maximum). The fixed cost does not change with capacity, so it does not affect the optimum.

Data and constants

  • Fixed cost = USD 2795 × 10⁶; variable cost = USD 645/kW; O&M = 2.5% of the variable cost per year; price = USD 38/MWh = USD 0.038/kWh for primary and secondary energy
  • Overall efficiency η=0.89\eta = 0.89 and head = 48 m (constant)
  • Net head H=48H = 48 m; overall efficiency η=0.8900\eta = 0.8900
  • Capital recovery factor CRF=i(1+i)n(1+i)n−1=0.11101CRF = \dfrac{i(1+i)^n}{(1+i)^n-1} = 0.11101 for i=11%i=11\%, n=45n=45 years
  • Energy per month: Em=9.81 η H Q (730 h)E_m = 9.81\,\eta\,H\,Q\,(730\ \text{h}) (8760/12 h per month)
  • Annual cost =(fixed+variable×P) CRF+O&M=(\text{fixed}+\text{variable}\times P)\,CRF + \text{O\&M}; annual benefit = energy × price

Flow available for power

available flows (m³/s) in descending order: 93, 73, 68, 53, 48, 43, 38, 36, 33, 28, 23, 18.

Marginal check

Each extra 1 kW of capacity above the flow level is used only in the months in which the flow is greater than the capacity flow. Benefit of 1 kW used for kk months =0.73 k= 0.73\,k MWh × price. Benefit per kW for each month it is used =0.73×38=27.74=0.73\times38 = 27.74 USD/yr; the annual cost of 1 kW is USD 87.73, so a kW must be used for at least 3.16 months, i.e. at least 4 months. The 4th highest flow is 53 m³/s, so the optimum design flow is 53 m³/s.

Trial design discharges

QdQ_d (m³/s)P (MW)Energy (GWh)Benefit (USD M)Cost (USD M)Net (USD M)
187.5466.082.5310.9-308.4
239.6482.913.2311.1-308.0
2811.7398.203.7311.3-307.6
3313.83111.974.3311.5-307.2
3615.09119.314.5311.6-307.1
3815.93123.604.7311.7-307.0
4318.02132.775.0311.9-306.8
4820.12140.425.3312.0-306.7
5322.21146.545.6312.2-306.7
6828.50160.316.1312.8-306.7
7330.59163.376.2313.0-306.8
9338.97169.496.4313.7-307.3

The net benefit is greatest at Qd=53Q_d = 53 m³/s.

Results

  • Installed capacity: P=9.81×0.8900×48×53=22,211 kW=22.21P = 9.81\times0.8900\times48\times53 = 22,211\ \text{kW} = 22.21 MW
  • Firm (primary) energy, from the minimum flow 18 m³/s all year: 9.81×0.8900×48×18×8760=66,081,039 kWh=66.089.81\times0.8900\times48\times18\times8760 = 66,081,039\ \text{kWh} = 66.08 GWh
  • Total energy: 146.54146.54 GWh
  • Secondary energy =146.54−66.08=80.46= 146.54-66.08 = 80.46 GWh
  • Plant factor =EP×8760=146.54×10622,211×8760=0.753= \dfrac{E}{P\times8760} = \dfrac{146.54\times10^6}{22,211\times8760} = 0.753 (75.3%)

Note: with the fixed cost taken exactly as stated (USD 2795 million), the net benefit is negative for every capacity (the project does not pay for itself). The optimum capacity is the same because the fixed cost is independent of capacity; the fixed cost is possibly a misprint in the question.

Answer: best installed capacity = 22.2 MW (design flow 53 m³/s); firm energy = 66.1 GWh; secondary energy = 80.5 GWh; total energy = 146.5 GWh; plant factor = 0.75.

  • 2081 Bhadra · 10 marks

The mean monthly flows of a river in a typical year are as follows:
MonthJanFebMarAprMayJunJulAugSeptOctNovDec
Flow (m³/s)93891152095931011201425421450830196118
The gross available head is 229 m, and the average head loss in transition is 12 m. The efficiencies of the turbines, gearboxes and generators are 94%, 92% and 99% respectively. 10 m³/s of water must be left in the river for downstream users. The other data are as follows: fixed cost = US$ 1200 × 10⁶; variable cost (present worth value) = US$ 500/kW; energy price = US$ 48/MWh for primary and secondary energy; interest rate = 12%; economic life of the project = 50 years. Determine the best installed capacity, firm energy, secondary energy, total energy and plant factor of a run-of-river plant.

Answer

Optimum capacity of a RoR plant is where the marginal benefit of the last unit of capacity equals its marginal cost (equivalently the net benefit is maximum). The fixed cost does not change with capacity, so it does not affect the optimum.

Data and constants

  • Net head =229−12=217= 229-12 = 217 m (gross head minus average transition loss)
  • Efficiency η=0.94×0.92×0.99=0.8562\eta = 0.94\times0.92\times0.99 = 0.8562 (turbine × gearbox × generator)
  • Fixed cost US$ 1200 × 10⁶; variable cost US$ 500/kW (present worth, annualised with CRF); price US$ 48/MWh = 0.048 US$/kWh
  • 10 m³/s is left in the river, so available flow =Q−10=Q-10
  • Net head H=217H = 217 m; overall efficiency η=0.8562\eta = 0.8562
  • Capital recovery factor CRF=i(1+i)n(1+i)n−1=0.12042CRF = \dfrac{i(1+i)^n}{(1+i)^n-1} = 0.12042 for i=12%i=12\%, n=50n=50 years
  • Energy per month: Em=9.81 η H Q (730 h)E_m = 9.81\,\eta\,H\,Q\,(730\ \text{h}) (8760/12 h per month)
  • Annual cost =(fixed+variable×P) CRF=(\text{fixed}+\text{variable}\times P)\,CRF; annual benefit = energy × price

Flow available for power

Environmental release of 10 m³/s is deducted: available flows (m³/s) in descending order: 2532, 2004, 1440, 1001, 820, 583, 199, 186, 108, 105, 83, 79.

Marginal check

Each extra 1 kW of capacity above the flow level is used only in the months in which the flow is greater than the capacity flow. Benefit of 1 kW used for kk months =0.73 k= 0.73\,k MWh × price. Benefit per kW per month of use =0.73×48=35.04=0.73\times48 = 35.04 USD/yr; annual cost of 1 kW =500×0.12042=60.21= 500\times0.12042 = 60.21 USD, so a kW must be used at least 1.72 months, i.e. at least 2 months. The 2nd highest flow is 2014 m³/s (2004 m³/s after the 10 m³/s release); beyond that the capacity is used for only 1 month.

Trial design discharges

QdQ_d (m³/s)P (MW)Energy (GWh)Benefit (USD M)Cost (USD M)Net (USD M)
79143.981,261.2860.5153.2-92.6
83151.271,319.8263.4153.6-90.3
105191.371,612.5277.4156.0-78.6
108196.841,648.4479.1156.4-77.2
186338.992,478.65119.0164.9-45.9
199362.692,599.72124.8166.3-41.6
5831,062.555,665.11271.9208.563.5
8201,494.497,241.70347.6234.5113.1
10011,824.378,204.96393.8254.3139.5
14402,624.479,957.18477.9302.5175.4
20043,652.3911,457.94550.0364.4185.6
25324,614.7012,160.42583.7422.3161.4

The net benefit is greatest at Qd=2004Q_d = 2004 m³/s (available flow after release; river flow 2014 m³/s).

Results

  • Installed capacity: P=9.81×0.8562×217×2004=3,652,392 kW=3,652.39P = 9.81\times0.8562\times217\times2004 = 3,652,392\ \text{kW} = 3,652.39 MW
  • Firm (primary) energy, from the minimum flow 79 m³/s all year: 9.81×0.8562×217×79×8760=1,261,277,982 kWh=1,261.289.81\times0.8562\times217\times79\times8760 = 1,261,277,982\ \text{kWh} = 1,261.28 GWh
  • Total energy: 11,457.9411,457.94 GWh
  • Secondary energy =11,457.94−1,261.28=10,196.66= 11,457.94-1,261.28 = 10,196.66 GWh
  • Plant factor =EP×8760=11,457.94×1063,652,392×8760=0.358= \dfrac{E}{P\times8760} = \dfrac{11,457.94\times10^6}{3,652,392\times8760} = 0.358 (35.8%)

Answer: best installed capacity = 3,652.4 MW (design flow 2004 m³/s); firm energy = 1,261.3 GWh; secondary energy = 10,196.7 GWh; total energy = 11,457.9 GWh; plant factor = 0.36.

  • 2080 Baishakh · 8 marks

A RoR hydropower plant is proposed in a river. Using the marginal cost and benefit method, optimize the installed capacity with the following data: interest rate = 12%; energy price = $0.08/kWh; fixed cost = $60 × 10⁶; variable cost (electro-mechanical) = $650/kW; annual O&M = 3% of variable cost; project life = 35 years.
% Time8.3316.6725.033.3341.6750.058.3366.6775.083.3391.67100
Power (kW)80560456440730016713011596897465

Answer

Capacity should be increased as long as the marginal benefit (MB) of the added capacity is at least its marginal cost (MC). The fixed cost ($60 × 10⁶) does not depend on the capacity, so it does not enter the marginal comparison.

Data

  • Interest i=12%i=12\%, life n=35n=35 years: CRF=i(1+i)n(1+i)n−1=0.12232CRF=\dfrac{i(1+i)^n}{(1+i)^n-1}=0.12232
  • Annual cost of 1 kW of electro-mechanical equipment =650 (CRF+0.03)=650×(0.12232+0.03)=99.01= 650\,(CRF+0.03) = 650\times(0.12232+0.03) = 99.01 USD per kW per year
  • Energy price = $0.08/kWh

Method

The power duration table gives the percentage of time each power level is equalled or exceeded. Raising the capacity from the next lower power level to the level PkP_k adds ΔP\Delta P kW, which can be used for only the percentage of time tkt_k for which that power is available:

ΔE=ΔP×tk100×8760,MB=0.08 ΔE,MC=c ΔP\Delta E = \Delta P \times \frac{t_k}{100} \times 8760,\quad MB = 0.08\,\Delta E,\quad MC = c\,\Delta P
Capacity step (kW)ΔP (kW)Time used (%)ΔE (kWh)MB ($)MC ($)MB/MC
604 → 8052018.33146,67111,73419,9000.59
564 → 6044016.6758,4124,6733,9601.18
407 → 56415725.0343,83027,50615,5441.77
300 → 40710733.33312,40924,99310,5942.36
167 → 30013341.67485,48938,83913,1682.95
130 → 1673750.0162,06012,9653,6633.54
115 → 1301558.3376,6466,1321,4854.13
96 → 1151966.67110,9668,8771,8814.72
89 → 96775.045,9903,6796935.31
74 → 891583.33109,4968,7601,4855.90
65 → 74991.6772,2735,7828916.49
0 → 6565100569,40045,5526,4357.08

Decision

The ratio MB/MC is below 1 for the step 604 → 805 kW (MB = $11,734 < MC = $19,900), so this extra capacity is not worth building. The step 564 → 604 kW has MB/MC = 1.18 (more than 1), so it is justified, and all lower steps are also justified.

Answer: the optimum installed capacity is 604 kW (the capacity exceeded 16.67% of the time).

(If the curve is interpolated linearly between the 8.33% and 16.67% points, the break-even occurs at about 14.3% of the time, which is roughly 660 kW; with the tabulated power levels, 604 kW is the answer.)

  • 2079 Bhadra · 4+4 marks

In a Nepali river the mean monthly flow in the year 2021 is given below.
MonthDischarge (m³/s)MonthDischarge (m³/s)
Jan50July125
Feb40Aug150
March30Sept120
April25Oct100
May10Nov75
June75Dec70
a) Draw the flow duration curve. b) Find the power available at the mean flow of water if the available head is 100 m at the site and the overall efficiency of the plant is 85%.

Answer

a) Flow duration curve

Arrange the 12 monthly flows in descending order and assign the exceedance probability by the Weibull formula p=mN+1×100p = \dfrac{m}{N+1}\times100 with N=12N = 12.

RankQ (m³/s)Exceedance (%)
11507.7
212515.4
312023.1
410030.8
57538.5
67546.2
77053.8
85061.5
94069.2
103076.9
112584.6
121092.3

Plot Q (vertical) against percentage of time (horizontal) and join the points with a smooth curve:

 Q (m³/s)
 150 |*
 125 | *
 100 |   *
  75 |      * *
  50 |           *
  25 |               * *
  10 |                    *
     +--------------------------
      0  20  40  60  80  100 %
         time flow is exceeded

b) Power at the mean flow

Mean flow Qˉ=∑Q12=87012=72.5\bar Q = \dfrac{\sum Q}{12} = \dfrac{870}{12} = 72.5 m³/s

P=γQHη=9.81×72.5×100×0.85=60,454.12 kW=60.45 MWP = \gamma Q H \eta = 9.81\times72.5\times100\times0.85 = 60,454.12\ \text{kW} = 60.45\ \text{MW}

The mean flow of 72.5 m³/s is exceeded about 46% of the time (six of the twelve months have flows above it).

Answer: mean flow = 72.5 m³/s; power at mean flow ≈ 60.45 MW (the FDC is tabulated above).

  • 2069 Chaitra · 8 marks

The stream flow record for a hydropower development site is given below. Draw a flow duration curve and determine firm and secondary energy if the available head is 60 m, design discharge capacity is 45 m³/s and overall efficiency is 82%.
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)303828221632567254463836

Answer

Flow duration curve

Rank the monthly flows in descending order and take p=mN+1×100p=\dfrac{m}{N+1}\times100 with N=12N=12.

RankQ (m³/s)Exceedance (%)Q used = min(Q, 45)
1727.745
25615.445
35423.145
44630.845
53838.538
63846.238
73653.836
83261.532
93069.230
102876.928
112284.622
121692.316
 Q (m³/s)
  72 |*
  56 | *
  45 |-+--*-*-----  design flow
  38 |        * *
  30 |           * *
  22 |               *
  16 |                  *
     +----------------------
      0  20  40  60  80 100 %

The FDC is flat at 45 m³/s for about 31% of the time (months with flow above the design flow).

Energy

Constants: H=60H=60 m, η=0.82\eta=0.82, Qd=45Q_d=45 m³/s, 730 h per month.

  • Installed capacity P=9.81×0.82×60×45=21,719P=9.81\times0.82\times60\times45 = 21,719 kW =21.72=21.72 MW
  • Firm energy is based on the flow available all the time (minimum flow 16 m³/s):
Pfirm=9.81×0.82×60×16=7,722 kW,Efirm=7,722×8760=67.65 GWhP_{firm} = 9.81\times0.82\times60\times16 = 7,722\ \text{kW},\quad E_{firm} = 7,722\times8760 = 67.65\ \text{GWh}
  • Total energy with Qused=min⁡(Q,45)Q_{used}=\min(Q,45): sum of used flows = 420 m³/s-months, so mean used flow = 35 m³/s
Etotal=9.81×0.82×60×35×8760=147.98 GWhE_{total} = 9.81\times0.82\times60\times35\times8760 = 147.98\ \text{GWh}
  • Secondary energy =Etotal−Efirm=147.98−67.65=80.33=E_{total}-E_{firm} = 147.98-67.65 = 80.33 GWh

Answer: firm energy ≈ 67.6 GWh; secondary energy ≈ 80.3 GWh; total ≈ 148.0 GWh per year.

  • 2078 Bhadra · 12 marks

A peaking ROR project in western Nepal with net head of 250 m has the following river flow data:
MonthJanFebMarAprMayJunJulAugSepOctNovDec
River flow (m³/s)100808010520050011001200800350200120
The storage capacity available for this project is 1100 million m³. This storage capacity is utilized for dry months (Nov-May) during which the plant is used as a peak load plant operating 4 hours a day. Considering design flow as Q₂₅, calculate the maximum power generation (in MW) and the ratio of wet season energy to dry season energy.

Answer

Data and assumptions

Net head H=250H=250 m. Dry months (Nov-May, 7 months) use stored water for 4 h/day of peaking. Wet months (Jun-Oct, 5 months) the plant runs as RoR for 24 h. One month =730=730 h =2.628×106=2.628\times10^6 s. Overall efficiency is not given, so power is first found for η=1\eta=1 and then for a typical η=0.85\eta=0.85; the energy ratio does not depend on η\eta.

Design flow Q25Q_{25}

Arrange the 12 monthly flows in descending order: 1200, 1100, 800, 500, 350, 200, 200, 120, 105, 100, 80, 80. The flow equalled or exceeded 25% of the time (3 months out of 12) is the 3rd value:

Q25=800 m3/sQ_{25} = 800\ \text{m}^3/\text{s}

Is the stored water enough for peaking at Q25Q_{25}?

  • Dry-season inflow volume =∑Q×2.628×106=885×2.628×106=2,326×106=\sum Q\times 2.628\times10^6 = 885\times2.628\times10^6 = 2,326\times10^6 m³
  • Plus live storage =1100×106=1100\times10^6 m³, so water available =3,426×106=3,426\times10^6 m³
  • Peaking hours in 7 months =7×730×424=851.7=7\times730\times\frac{4}{24} = 851.7 h
  • Water needed to run at Q25Q_{25} for these hours =800×851.7×3600=2,453×106=800\times851.7\times3600 = 2,453\times10^6 m³ (less than available)

So the turbines can run at Q25=800Q_{25}=800 m³/s during the 4 peak hours every day, and the plant capacity is controlled by the design flow (the water available would allow up to 1,117 m³/s).

Maximum power

Pmax=9.81 η Q H=9.81×η×800×250=1,962 η MWP_{max} = 9.81\,\eta\,Q\,H = 9.81\times\eta\times800\times250 = 1,962\,\eta\ \text{MW}
  • With η=1\eta = 1: Pmax=1,962P_{max} = 1,962 MW
  • With η=0.85\eta = 0.85: Pmax=1,668P_{max} = 1,668 MW

Wet-season to dry-season energy ratio

Wet season flows used: min⁡(Q,800)\min(Q,800) = 500, 800, 800, 800, 350, total =3250=3250 m³/s-months.

Ewet∝3250×730=2,372,500,Edry∝800×851.7=681,333E_{wet} \propto 3250\times730 = 2,372,500,\qquad E_{dry} \propto 800\times851.7 = 681,333 EwetEdry=2,372,500681,333=3.48\frac{E_{wet}}{E_{dry}} = \frac{2,372,500}{681,333} = 3.48

Answer: maximum power = 1,962 MW for η=1\eta=1 (1,668 MW for η=0.85\eta=0.85); wet season energy / dry season energy = 3.48.

  • 2075 Chaitra · 4+4 marks

A run-of-river hydroelectric power station is proposed across a river at a site where a net head of 30 m is available on the turbine. The river carries a sustained minimum flow of 25 m³/s in dry weather and behind the power station sufficient pondage is provided to supply the daily peak load demand with a load factor of 65%. Assuming the plant efficiency of 60%, determine the maximum generating capacity of the generator to be installed at the power house. If the daily load pattern indicates 20 hours average load and 4 hours of peak load, determine the volume of pondage to be provided to supply the daily demand.

Answer

Maximum generating capacity

The minimum flow gives the average power available throughout the day:

Pavg=γQHη=9.81×25×30×0.60=4,414.5 kWP_{avg} = \gamma Q H \eta = 9.81\times25\times30\times0.60 = 4,414.5\ \text{kW}

With pondage the plant can follow the daily load, and the load factor is

Load factor=PavgPmax=0.65⇒Pmax=4,414.50.65=6,791.5 kW≈6.79 MW\text{Load factor} = \frac{P_{avg}}{P_{max}} = 0.65 \Rightarrow P_{max} = \frac{4,414.5}{0.65} = 6,791.5\ \text{kW} \approx 6.79\ \text{MW}

Volume of pondage (20 h average load + 4 h peak load)

Peak load: Pmax=6,791.5P_{max}=6,791.5 kW for 4 h. The average over the day must equal PavgP_{avg}, so the off-peak load for 20 h is

Poff=24×4,414.5−4×6,791.520=3,939.1 kWP_{off} = \frac{24\times4,414.5 - 4\times6,791.5}{20} = 3,939.1\ \text{kW}

Flow needed at peak:

Qpeak=Pmax9.81×30×0.6=6,791.5176.58=38.46 m3/sQ_{peak} = \frac{P_{max}}{9.81\times30\times0.6} = \frac{6,791.5}{176.58} = 38.46\ \text{m}^3/\text{s}

The river supplies 25 m³/s, so the deficit of (38.46−25)(38.46-25) m³/s for 4 hours must come from the pond:

V=(38.46−25)×4×3600=193,846 m3≈1.94×105 m3V = (38.46-25)\times4\times3600 = 193,846\ \text{m}^3 \approx 1.94\times10^5\ \text{m}^3

(The pond fills during the 20 off-peak hours by (25−22.31)×20×3600=193,846(25-22.31)\times20\times3600 = 193,846 m³, the same volume.)

Answer: generator capacity = 6.79 MW; pondage volume ≈ 193,846 m³ (≈ 1.94 × 10⁵ m³).

  • 2076 Ashwin · 5+5 marks

During a low water week a river has an average daily flow of 40 m³/s. Fluctuation during the day required a pondage capacity of approximately 30% of the daily discharge. A hydroelectric plant is to be located on the river which will operate 6 days a week, 24 hours a day, but will supply power at a varying rate such that the daily load factor is 50%, corresponding to which the pondage required is equal to 0.2 times the mean flow to the turbine. On Saturday all the flow is ponded for use on the rest of the days. If the effective head on the turbines when the pond is full is to be 25 m and the maximum allowable fluctuation in pond level is 1 m, find (i) the surface area of the pond to satisfy all the operating conditions, (ii) the weekly output at the switch board in kWh. Assume turbine efficiency 80% and generator efficiency 90%.

Answer

Data

Inflow Q=40Q=40 m³/s; daily inflow volume =40×86400=3,456,000=40\times86400 = 3,456,000 m³. The plant works 6 days (Sunday-Friday) and on Saturday the whole flow is stored. Hfull=25H_{full}=25 m, maximum fluctuation =1=1 m, ηt=0.80\eta_t=0.80, ηg=0.90\eta_g=0.90.

(i) Surface area of the pond

1. Weekly pondage (Saturday flow): all of Saturday's inflow is stored for use on the other days.

V1=40×86400=3,456,000 m3V_1 = 40\times86400 = 3,456,000\ \text{m}^3

2. Daily pondage: two requirements are given.

  • To take care of the daily flow fluctuation: 0.30×3,456,000=1,036,8000.30\times3,456,000 = 1,036,800 m³
  • For the 50% daily load factor: mean flow to the turbines on working days =40×76=46.67=40\times\frac{7}{6}=46.67 m³/s, so the pondage =0.2×46.67×86400=806,400=0.2\times46.67\times86400 = 806,400 m³

The pond must satisfy both, so the larger value is taken: V2=1,036,800V_2=1,036,800 m³.

3. Total live storage:

V=V1+V2=3,456,000+1,036,800=4,492,800 m3V = V_1+V_2 = 3,456,000+1,036,800 = 4,492,800\ \text{m}^3

The allowed draw-down is 1 m, so

A=VΔh=4,492,8001=4,492,800 m2≈4.49 km2A = \frac{V}{\Delta h} = \frac{4,492,800}{1} = 4,492,800\ \text{m}^2 \approx 4.49\ \text{km}^2

(ii) Weekly output at the switchboard

The whole weekly inflow is used: 40×7×24=6,72040\times7\times24 = 6,720 m³/s·h. The pond level goes down by 1 m, so the average head is 25−0.5=24.525-0.5 = 24.5 m.

E=9.81 ηtηg H ∑Q t=9.81×0.80×0.90×24.5×6,720=1,162,885 kWhE = 9.81\,\eta_t\eta_g\,H\,\sum Q\,t = 9.81\times0.80\times0.90\times24.5\times6,720 = 1,162,885\ \text{kWh}

(With the full-pond head of 25 m, the figure would be 1,186,618 kWh.)

Answer: pond surface area ≈ 4.49 km² (4,492,800 m²); weekly output ≈ 1.16 GWh (1,162,885 kWh).

  • 2075 Ashwin · 6 marks

A RoR plant has a minimum flow of 30 m³/s and net head of 70 m. The overall efficiency of the plant is 85%. Calculate the installed capacity of the plant (i) without pondage (designed for pure RoR plant) and (ii) if the plant is designed for a peaking plant with 6 hours peaking. The plant has two sets of units such that one unit at full capacity is operating during off-peak hours. Total evaporation and other losses is 5% of the stored water.

Answer

(i) Pure RoR plant (no pondage)

Only the minimum flow can be used continuously:

P1=9.81 η Q H=9.81×0.85×30×70=17,511 kW=17.51 MWP_1 = 9.81\,\eta\,Q\,H = 9.81\times0.85\times30\times70 = 17,511\ \text{kW} = 17.51\ \text{MW}

(ii) Peaking plant, 6 h peak, two units

Let QuQ_u be the discharge of one unit at full load. Off-peak (18 h) only one unit runs, using QuQ_u. In peak hours (6 h) both units run, using 2Qu2Q_u.

Water stored in the 18 off-peak hours (inflow 30 m³/s) after 5% loss:

Vs=0.95 (30−Qu)×18×3600V_s = 0.95\,(30-Q_u)\times18\times3600

During the 6 peak hours the extra flow required is (2Qu−30)(2Q_u-30), supplied from storage:

(2Qu−30)×6×3600=0.95 (30−Qu)×18×3600(2Q_u-30)\times6\times3600 = 0.95\,(30-Q_u)\times18\times3600 12Qu−180=513−17.1 Qu⇒Qu=69329.1=23.814 m3/s12Q_u - 180 = 513 - 17.1\,Q_u \Rightarrow Q_u = \frac{693}{29.1} = 23.814\ \text{m}^3/\text{s}

Peak discharge =2Qu=47.629=2Q_u=47.629 m³/s.

P2=9.81×0.85×47.629×70=27,801 kW=27.80 MWP_2 = 9.81\times0.85\times47.629\times70 = 27,801\ \text{kW} = 27.80\ \text{MW}

Check: pondage volume =400,825=400,825 m³ (about 4.01 × 10⁵ m³). Off-peak one unit uses 23.81 m³/s (less than 30), so the surplus goes to the pond.

Answer: (i) installed capacity = 17.51 MW (pure RoR); (ii) installed capacity = 27.80 MW with 6-hour peaking (2 units of 13.90 MW each), a gain of 1.59 times.

  • 2070 Ashad · 2+4+2 marks

The mean monthly flow of a typical Nepalese river is as follows:
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (m³/s)807483100130222600800590240120100
i) Calculate the installed capacity of a plant based on the minimum flow of the river without pondage (if the plant is designed for a pure run-of-river plant) with net head of 200 m and overall efficiency of the plant 85%. ii) The plant has three sets of units (turbine and generator) such that one unit with full capacity is operated during off-peak hours. If the plant is designed as a peaking plant with 4 hour peaking (morning 2 hour and evening 2 hour), what will be the installed capacity of the plant? iii) What will be the increase in benefit from peaking if the peak hour energy rate is Rs 12/kWh and the off-peak energy rate is Rs 6/kWh during the minimum flow month?

Answer

i) Pure run-of-river plant

Minimum flow is 74 m³/s (February).

P1=9.81×0.85×74×200=123,410 kW=123.41 MWP_1 = 9.81\times0.85\times74\times200 = 123,410\ \text{kW} = 123.41\ \text{MW}

ii) Peaking plant with three units, 4 h peaking

One unit (discharge QuQ_u) runs at full load for the 20 off-peak hours; all three units (3Qu3Q_u) run for the 4 peak hours. Daily water balance on the minimum flow of 74 m³/s:

20 Qu+4 (3Qu)=24×74⇒32 Qu=1776⇒Qu=55.50 m3/s20\,Q_u + 4\,(3Q_u) = 24\times74 \Rightarrow 32\,Q_u = 1776 \Rightarrow Q_u = 55.50\ \text{m}^3/\text{s}

Peak discharge =3Qu=166.50=3Q_u=166.50 m³/s.

P2=9.81×0.85×166.50×200=277,672 kW=277.67 MWP_2 = 9.81\times0.85\times166.50\times200 = 277,672\ \text{kW} = 277.67\ \text{MW}

(Each unit is 92.56 MW. Check storage: off-peak stored =(74−55.5)×20=370=(74-55.5)\times20 = 370 m³/s·h; peak draw =(166.5−74)×4=370=(166.5-74)\times4=370 m³/s·h, equal.)

iii) Increase in benefit during the minimum flow month

Daily energy is the same in both cases (24×123.41=2,96224\times123.41 = 2,962 MWh).

  • RoR (constant output): 4 peak hours at Rs 12 and 20 off-peak hours at Rs 6 per kWh:
B1=123,410×(4×12+20×6)=Rs 20,732,846 per dayB_1 = 123,410\times(4\times12+20\times6) = \text{Rs }20,732,846\text{ per day}
  • Peaking plant: B2=92,557×20×6+277,672×4×12=Rs 24,435,140B_2 = 92,557\times20\times6 + 277,672\times4\times12 = \text{Rs }24,435,140 per day

Increase =3,702,294=3,702,294 Rs/day ≈\approx Rs 3.70 million per day, or about Rs 111.1 million for a 30-day month.

Answer: (i) 123.4 MW; (ii) 277.7 MW; (iii) extra benefit ≈ Rs 3.70 million per day (≈ Rs 111 million per month).

  • 2070 Chaitra · 2+2+2+2+2+2 marks

A hydropower project is planned to develop in a river having net head of 100 m and overall efficiency of 85% with the monthly hydrograph as shown below.
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Discharge (m³/s)1001201403003201800200025002100900500300
i) Calculate the installed capacity, annual spill energy and firm energy if the RoR project is designed based on the 40% probability of exceedence flow. ii) If the storage project is developed with full regulation of the annual hydrograph (design discharge is equal to the average monthly flow), calculate the storage requirements. iii) Calculate the installed capacity and annual energy generation from the storage project as mentioned in the above case.

Answer

Data

H=100H=100 m, η=0.85\eta=0.85, so 9.81 η H=833.859.81\,\eta\,H = 833.85 kW per m³/s. One month =730=730 h =2.628×106=2.628\times10^6 s.

i) RoR designed for Q40Q_{40}

Flows in descending order: 2500, 2100, 2000, 1800, 900, 500, 320, 300, 300, 140, 120, 100. By the Weibull formula p=mN+1×100p=\frac{m}{N+1}\times100 with N=12N=12, p=40%p=40\% gives m=0.4×13=5.2m=0.4\times13=5.2, which lies between 900 (m = 5) and 500 (m = 6):

Q40=900−0.2 (900−500)=820 m3/sQ_{40} = 900 - 0.2\,(900-500) = 820\ \text{m}^3/\text{s} P=833.85×820=683,757 kW=683.8 MWP = 833.85\times820 = 683,757\ \text{kW} = 683.8\ \text{MW}
  • Spill (flow above Q40Q_{40}) by month (m³/s): Jun 980, Jul 1180, Aug 1680, Sep 1280, Oct 80, total =5,200=5,200 m³/s-months.
Espill=833.85×5,200×730=3,165 GWhE_{spill} = 833.85\times5,200\times730 = 3,165\ \text{GWh}
  • Firm energy (minimum flow 100 m³/s available all year):
Efirm=833.85×100×8760=730.5 GWhE_{firm} = 833.85\times100\times8760 = 730.5\ \text{GWh}
  • (Total energy of the RoR plant =833.85×5,880×730=3,579= 833.85\times5,880\times730 = 3,579 GWh, so the non-firm energy is 2,849 GWh.)

ii) Storage with full regulation

The design discharge equals the mean flow:

Qˉ=11,08012=923.33 m3/s\bar Q = \frac{11,080}{12} = 923.33\ \text{m}^3/\text{s}

Deficits (Qˉ−Q\bar Q-Q) in the months with flow below the mean, from Oct to May (m³/s-months): Oct 23.33, Nov 423.33, Dec 623.33, Jan 823.33, Feb 803.33, Mar 783.33, Apr 623.33, May 603.33. Sum =4,706.67=4,706.67 (this equals the surplus of Jun-Sep, which refills the reservoir).

Vs=4,706.67×2.628×106=12,369×106 m3≈12.37 billion m3V_s = 4,706.67\times2.628\times10^6 = 12,369\times10^6\ \text{m}^3 \approx 12.37\ \text{billion m}^3

iii) Installed capacity and energy of the storage project

P=833.85×923.33=769,922 kW=769.9 MWP = 833.85\times923.33 = 769,922\ \text{kW} = 769.9\ \text{MW} E=P×8760=6,745 GWh/yearE = P\times8760 = 6,745\ \text{GWh/year}

(The head is taken as constant at 100 m.)

Answer: (i) P = 683.8 MW at Q40=820Q_{40}=820 m³/s; spill energy ≈ 3,165 GWh; firm energy = 730.5 GWh. (ii) storage = 12,369 Mm³. (iii) P = 769.9 MW; E = 6,745 GWh.

  • 2074 Ashwin · 3+3+4 marks

The hydrograph of a typical river of Nepal follows the equation Qt=5.589t2−51.275t+139.94Q_t = 5.589t^2 - 51.275t + 139.94, where QtQ_t is the mean monthly discharge in m³/s and tt is time in months counted with October as the 1st month and so on. A hydropower plant has to be developed in this river with net head of 150 m and overall efficiency of 85%; the environmental flow is not considered. a) Calculate the installed capacity and firm energy for the RoR project that will be developed for design discharge Q40Q_{40}. b) If the project has to be designed as a Peaking Run of the River (PRoR) project for 6 hrs daily peaking (3 hrs in morning and 3 hrs in evening) and with design discharge Q40Q_{40}, what is the installed capacity of the PRoR project? Assume that the project is designed in such a way that 50% of the available flow is used during the off-peak hours and the remaining 50% of the available flow is stored for peak hour generation. Neglect all the losses.

Answer

Monthly flows from Qt=5.589t2−51.275t+139.94Q_t = 5.589t^2 - 51.275t + 139.94

tMonthQ (m³/s)
1Oct94.25
2Nov59.75
3Dec36.42
4Jan24.26
5Feb23.29
6Mar33.49
7Apr54.88
8May87.44
9Jun131.17
10Jul186.09
11Aug252.18
12Sep329.46

H=150H=150 m, η=0.85\eta=0.85: 9.81 η H=1250.779.81\,\eta\,H = 1250.77 kW per m³/s.

Design discharge Q40Q_{40}

Descending flows: 329.46, 252.18, 186.09, 131.17, 94.25, 87.44, 59.75, 54.88, 36.42, 33.49, 24.26, 23.29. Weibull position for 40%: m=0.4×13=5.2m=0.4\times13=5.2 (between the 5th flow 94.25 and the 6th flow 87.44):

Q40=94.25−0.2 (94.25−87.44)=92.89 m3/sQ_{40} = 94.25 - 0.2\,(94.25-87.44) = 92.89\ \text{m}^3/\text{s}

a) RoR project

P=1250.77×92.89=116,185 kW=116.18 MWP = 1250.77\times92.89 = 116,185\ \text{kW} = 116.18\ \text{MW}

The minimum monthly flow is 23.29 m³/s (February), the flow available in all months, so

Efirm=1250.77×23.29×8760=255,183,616 kWh=255.2 GWhE_{firm} = 1250.77\times23.29\times8760 = 255,183,616\ \text{kWh} = 255.2\ \text{GWh}

(Total energy with flows limited to Q40Q_{40} is 715.8 GWh; the part above firm energy is secondary energy.)

b) Peaking run-of-river (6 h daily peaking)

Daily water volume at Q40Q_{40}: Q40×24×3600Q_{40}\times24\times3600. Half of it (50%) is used during the 18 off-peak hours and the other half is stored (pond volume =0.5×92.89×86400=4,012,865=0.5\times92.89\times86400=4,012,865 m³) and used in the 6 peak hours:

Qpeak=0.5 Q40×246=2 Q40=185.78 m3/sQ_{peak} = \frac{0.5\,Q_{40}\times24}{6} = 2\,Q_{40} = 185.78\ \text{m}^3/\text{s} PPRoR=1250.77×185.78=232,370 kW=232.37 MWP_{PRoR} = 1250.77\times185.78 = 232,370\ \text{kW} = 232.37\ \text{MW}

Off-peak the plant uses 0.5 Q40×24/18=61.930.5\,Q_{40}\times24/18 = 61.93 m³/s. The installed capacity is therefore twice that of the RoR plant.

Answer: (a) RoR: installed capacity = 116.2 MW, firm energy = 255.2 GWh; (b) PRoR: installed capacity = 232.4 MW.

  • 2071 Chaitra · 3+2+3 marks

A hydropower project is planned to develop in a Nepalese river having net head of 150 m, turbine efficiency of 90% and generator efficiency of 95% with the monthly hydrograph as shown below:
MonthsOctNovDecJanFebMarAprMayJunJulAugSep
Q (m³/sec)1008060504030405070110150120
As an environmental flow, a minimum flow of 10% of each month is mandatory. If the storage project is designed with full regulation of the annual hydrograph, find out the capacity of the reservoir, installed capacity of the power plant, and annual energy generation.

Answer

Data

H=150H=150 m, η=ηtηg=0.90×0.95=0.855\eta=\eta_t\eta_g = 0.90\times0.95=0.855. Environmental flow = 10% of each month's flow, so the flow available for power is 0.9 Q0.9\,Q. One month =2.628×106=2.628\times10^6 s.

Sum of flows =900=900 m³/s, mean =75=75 m³/s. Mean available flow =0.9×75=67.5=0.9\times75 = 67.5 m³/s. With full regulation the design discharge is this mean flow, so the plant runs at constant Qd=67.5Q_d=67.5 m³/s.

Reservoir capacity (mass-curve method)

The reservoir is full at the start of December, when inflow drops below the draft. Cumulative of (0.9Q − 67.5):

MonthQ (m³/s)0.9Q0.9Q − meanCumulative (m³/s-month)
Dec6054.0-13.5-13.5
Jan5045.0-22.5-36.0
Feb4036.0-31.5-67.5
Mar3027.0-40.5-108.0
Apr4036.0-31.5-139.5
May5045.0-22.5-162.0
Jun7063.0-4.5-166.5
Jul11099.0+31.5-135.0
Aug150135.0+67.5-67.5
Sep120108.0+40.5-27.0
Oct10090.0+22.5-4.5
Nov8072.0+4.5+0.0

The cumulative reaches its lowest value of −166.5-166.5 m³/s-months in June; from July the surplus refills the reservoir.

V=166.5×2.628×106=0.0×106 m3≈0 Mm3V = 166.5\times2.628\times10^6 = 0.0\times10^6\ \text{m}^3 \approx 0\ \text{Mm}^3

Installed capacity

P=9.81 η H Qd=9.81×0.855×150×67.5=84,924 kW=84.92 MWP = 9.81\,\eta\,H\,Q_d = 9.81\times0.855\times150\times67.5 = 84,924\ \text{kW} = 84.92\ \text{MW}

Annual energy

E=P×8760=743.9 GWhE = P\times8760 = 743.9\ \text{GWh}

(The head is taken as constant at 150 m; in practice the head varies with the reservoir level.)

Answer: reservoir capacity ≈ 0 Mm³; installed capacity ≈ 84.9 MW; annual energy ≈ 744 GWh.

  • 2080 Bhadra · 4+4 marks

The water turbine at a hydel storage plant produces 1000 HP when working under a net head of 30 m and with an overall efficiency of 80%. The inflow in the reservoir during a year is given below.
MonthJanFebMarAprMayJunJulAugSepOctNovDec
Q (Mm³)908073807098120809610510075
Find (i) the minimum capacity required, (ii) the total quantity of water wasted. (Assume the reservoir is full at the beginning of the year.)

Answer

Water needed by the turbine

Take 1 HP = 0.7457 kW. Output =1000×0.7457=745.7=1000\times0.7457 = 745.7 kW, net head 30 m, overall efficiency 0.80:

Q=P9.81 η H=745.79.81×0.80×30=3.167 m3/sQ = \frac{P}{9.81\,\eta\,H} = \frac{745.7}{9.81\times0.80\times30} = 3.167\ \text{m}^3/\text{s}

Monthly demand volume D=3.167×2.628×106=8.32×106D = 3.167\times2.628\times10^6 = 8.32\times10^6 m³ =8.32=8.32 Mm³ (constant draft).

As the data are given (1000 HP)

The demand (8.32 Mm³/month) is far below the smallest monthly inflow (70 Mm³), so the inflow is greater than the demand in every month and the reservoir never goes short.

  • (i) Minimum capacity required =0=0 Mm³ (no storage is needed for this load).
  • (ii) Water wasted =∑(inflow)−12D=1067−99.88=967.1=\sum(\text{inflow}) - 12D = 1067 - 99.88 = 967.1 Mm³ per year.

If the turbine is 10,000 HP (probable intended load)

The inflow data (mean 88.9 Mm³/month) match a turbine about ten times larger, so the working for 10,000 HP is also shown. P=7,457P=7,457 kW, Q=31.67Q=31.67 m³/s, monthly demand D=83.24D=83.24 Mm³.

MonthInflowDemandOpeningClosingWasted
Jan9083.2429.9429.946.76
Feb8083.2429.9426.710.00
Mar7383.2426.7116.470.00
Apr8083.2416.4713.240.00
May7083.2413.240.000.00
Jun9883.240.0014.760.00
Jul12083.2414.7629.9421.59
Aug8083.2429.9426.710.00
Sep9683.2426.7129.949.53
Oct10583.2429.9429.9421.76
Nov10083.2429.9429.9416.76
Dec7583.2429.9421.710.00

The reservoir (full at the start of the year) falls to empty in May, so the minimum capacity is the deficit accumulated from February to May: 29.9 Mm³. The inflow after June refills it, and the water that cannot be stored (spill) adds to 76.4 Mm³ per year.

Answer: for the 1000 HP load stated, minimum capacity = 0 and wasted water = 967 Mm³. For a 10,000 HP turbine, minimum capacity ≈ 29.9 Mm³ and wasted water ≈ 76.4 Mm³.

  • 2081 Baishakh · 12 marks

The table below shows the inflow for one reservoir.
MonthOctNovDecJanFebMarAprMayJunJulAugSep
Inflow (m³/s)383227261510876433
i) By assuming the mean inflow as the draft, develop the mass curve of the reservoir. ii) Determine the storage capacity and length of the critical period. iii) Determine the storage capacity if the draft is only 80% of the mean inflow and compare it with the storage capacity of (ii).

Answer

Units are m³/s-months; one m³/s-month =2.628×106=2.628\times10^6 m³.

i) Mass curve

Mean inflow =∑Q12=17912=14.917=\dfrac{\sum Q}{12} = \dfrac{179}{12} = 14.917 m³/s, taken as the uniform draft.

MonthInflowCum. inflowCum. draft (mean)Cum. inflow − draft
Oct383814.92+23.08
Nov327029.83+40.17
Dec279744.75+52.25
Jan2612359.67+63.33
Feb1513874.58+63.42
Mar1014889.50+58.50
Apr8156104.42+51.58
May7163119.33+43.67
Jun6169134.25+34.75
Jul4173149.17+23.83
Aug3176164.08+11.92
Sep3179179.00+0.00
 Cum.
 volume
  179 |                          ____*   inflow mass curve
      |                   ___---
      |              _--*      draft line (slope = mean)
      |        __.-*      .-'
      |   _.-*      _.--'
      | *     _.--'
      +---------------------------
       Oct                    Sep

The mass curve of inflow lies above the draft line from October to February (surplus) and below it from March to September (deficit, the reservoir is drawn down).

ii) Storage capacity and critical period

The largest vertical gap between the draft line (tangent to the mass curve at the end of February) and the mass curve is at the end of September. This is the sum of the deficits from March to September:

S=∑(Qˉ−Q)Mar−Sep=(4.917+6.917+7.917+8.917+10.917+11.917+11.917)=63.42 m3/s-monthsS = \sum(\bar Q - Q)_{Mar-Sep} = (4.917+6.917+7.917+8.917+10.917+11.917+11.917) = 63.42\ \text{m}^3/\text{s-months} S=63.42×2.628×106=166.7×106 m3S = 63.42\times2.628\times10^6 = 166.7\times10^6\ \text{m}^3

Critical period =7=7 months (March to September), when the reservoir goes from full to empty. It refills by about February of the next year.

iii) Draft = 80% of mean inflow

0.8×14.917=11.9330.8\times14.917 = 11.933 m³/s. Deficit months are those with inflow below this value (Mar to Sep: 10, 8, 7, 6, 4, 3, 3):

S80=(1.933+3.933+4.933+5.933+7.933+8.933+8.933)=42.53 m3/s-months=111.8×106 m3S_{80} = (1.933+3.933+4.933+5.933+7.933+8.933+8.933) = 42.53\ \text{m}^3/\text{s-months} = 111.8\times10^6\ \text{m}^3

The critical period is still March to September (7 months). The storage required is reduced from 166.7 Mm³ to 111.8 Mm³, a saving of 33%, but the water supplied also falls by 20%.

Answer: storage for the mean-flow draft = 166.7 Mm³ (63.42 m³/s-months), critical period = 7 months; storage for 80% draft = 111.8 Mm³ (42.53 m³/s-months).

  • 2075 Ashwin · 4 marks

Monthly flow volumes feeding a reservoir are given in the table. Determine the storage capacity required to supply the mean annual flow.
Month123456789101112
Volume (10⁶ m³)29638650471481011547461158348150223182

Answer

The reservoir must supply the mean flow as a constant draft, so the storage is the largest cumulative deficit.

Mean monthly volume =6,67112=555.9×106=\dfrac{6,671}{12} = 555.9\times10^6 m³.

MonthVolumeMean (draft)Excess (+) / Deficit (−)
1296555.9-259.9
2386555.9-169.9
3504555.9-51.9
4714555.9+158.1
5810555.9+254.1
61154555.9+598.1
7746555.9+190.1
81158555.9+602.1
9348555.9-207.9
10150555.9-405.9
11223555.9-332.9
12182555.9-373.9

Months 4 to 8 have a surplus and fill the reservoir. Months 9 to 12 and 1 to 3 (the following year) are deficit months. Cumulative deficit from month 9 (reservoir full at the start of month 9):

After month9101112123
Cumulative deficit207.9613.8946.71320.71580.61750.51802.4

The maximum cumulative deficit is 1802.4 × 10⁶ m³.

Answer: required storage capacity ≈ 1,802 × 10⁶ m³ (about 1,802 million m³).

  • 2076 Chaitra · 7+3+2 marks

The monthly flows of a stream over the period of the driest year on record are as shown below:
MonthJFMAMJJASOND
Flow (×10⁶ m³)4.02.255.01.250.50.750.50.751.251.255.06.25
(i) Estimate the maximum possible uniform draw-off from this stream and determine the reservoir capacity to achieve the uniform draw-off and the minimum initial storage to maintain the demand. (ii) If the reservoir has only a total capacity of 8×10⁶ m³ with an initial storage of 4×10⁶ m³, determine (a) the maximum possible uniform draw-off and (b) the spillage.

Answer

Volumes are in 10⁶ m³ per month.

(i) Maximum uniform draw-off, reservoir capacity, minimum initial storage

Total inflow of the driest year =28.75=28.75. The maximum uniform draw-off possible in the year is the mean monthly inflow:

x=28.7512=2.396×106 m3/monthx = \frac{28.75}{12} = 2.396\times10^6\ \text{m}^3/\text{month}

Mass-curve table (cumulative of inflow − draw-off, starting from January):

MonthInflowDraw-offNetCumulative
J4.02.396+1.604+1.604
F2.252.396-0.146+1.458
M5.02.396+2.604+4.062
A1.252.396-1.146+2.917
M0.52.396-1.896+1.021
J0.752.396-1.646-0.625
J0.52.396-1.896-2.521
A0.752.396-1.646-4.167
S1.252.396-1.146-5.313
O1.252.396-1.146-6.458
N5.02.396+2.604-3.854
D6.252.396+3.854-0.000
  • The cumulative reaches its highest value (+4.062) at the end of March and its lowest (-6.458) at the end of October.
  • Minimum initial storage (January 1st) needed so that the demand is never short: 6.458×1066.458\times10^6 m³.
  • Reservoir capacity = peak − trough =4.062−(−6.458)=10.521×106=4.062-(-6.458) = 10.521\times10^6 m³.

(ii) Capacity 8 × 10⁶ m³, initial storage 4 × 10⁶ m³

The reservoir is smaller than 10.52, so some water is spilled when it is full and the draw-off must be reduced so that the storage never becomes negative. Trial routing gives the largest draw-off for which the reservoir just reaches zero (in October):

MonthInflowDraw-offStorage before spillSpillStorage end
J4.02.0365.9640.0005.964
F2.252.0366.1790.0006.179
M5.02.0369.1431.1438.000
A1.252.0367.2140.0007.214
M0.52.0365.6790.0005.679
J0.752.0364.3930.0004.393
J0.52.0362.8570.0002.857
A0.752.0361.5710.0001.571
S1.252.0360.7860.0000.786
O1.252.036-0.0000.000-0.000
N5.02.0362.9640.0002.964
D6.252.0367.1790.0007.179

(a) Maximum uniform draw-off =2.036×106=2.036\times10^6 m³/month (≈0.77\approx0.77 m³/s).

(b) Spillage =1.143×106=1.143\times10^6 m³ in the year (in March, when the reservoir is full).

Answer: (i) draw-off = 2.396 Mm³/month, capacity = 10.52 Mm³, minimum initial storage = 6.46 Mm³. (ii) (a) draw-off = 2.036 Mm³/month; (b) spillage = 1.14 Mm³.

  • 2073 Shrawan · 5+5 marks

The power supplied by the state electricity authority throughout the year by a steam power plant is as shown in the table below.
MonthPower supplied (MW)
Jestha550
Asar500
Shrawan450
Bhadra380
Asoj330
Kartik280
Mangsir250
Poush220
Magh200
Falgun150
Chaitra145
Baisakh100
But the current demand forced them to have load shedding. To minimize the load shedding by providing at least power equivalent to the Magh month throughout the year, the Authority has decided to import power from a neighbouring country for only 3 months, i.e. Falgun, Chaitra and Baisakh, as 50 MW, 55 MW and 100 MW respectively. a) Despite importing power, the authority felt that they cannot provide uniform power of Magh throughout. So they decide to have a diesel plant for the deficit. Estimate the minimum capacity of the diesel plant. (Use load duration curve for analysis.) b) If instead of the above system (steam plant + import + diesel plant), the Authority has planned to provide the power in the near future by constructing a ROR hydropower plant by its own to substitute the current model, derive the flow duration curve for such a new hydro project to supply the power demand given in the table. Assume power demand is constant in future.

Answer

Each month is taken as 1/12 of the year (8.33% of the time). The months are already in descending order of power, so the table is the load duration curve (LDC).

a) Load duration curve and diesel plant

RankMonthPower (MW)% of time exceeded
1Jestha5508.3
2Asar50016.7
3Shrawan45025.0
4Bhadra38033.3
5Asoj33041.7
6Kartik28050.0
7Mangsir25058.3
8Poush22066.7
9Magh20075.0
10Falgun15083.3
11Chaitra14591.7
12Baisakh100100.0
 MW
 550 |*
 500 | *
 450 |  *
 380 |   *
 330 |    *
 280 |     *
 250 |      *
 220 |       *
 200 |--------*---- Magh level (target)
 150 |         *
 145 |          *
 100 |           *
     +------------------------
      0   25   50   75   100 %

Target: at least the Magh power, 200 MW, in every month. Months below 200 MW and their deficits:

MonthSteam supply (MW)Deficit to 200 MWImport (MW)Remaining deficit
Falgun15050500
Chaitra14555550
Baisakh1001001000

The import in these three months is exactly equal to the deficits, so on the LDC the supply is at or above 200 MW for 100% of the time and no further deficit is left to be covered by the diesel plant. The minimum diesel capacity needed is therefore 0 MW for the stated imports. If the imports were not available, or fell short by xx MW in a month, the minimum diesel plant would be the largest remaining deficit: with no import at all it would be the largest gap, 100 MW (in Baisakh), and it would run only for about 25% of the time (energy ≈ (50+55+100) MW × 730 h = 149,650 MWh/year).

b) Flow duration curve for a RoR hydro plant

A constant (future) demand equal to the table has to be met by the hydropower plant, so the required flow follows from

Q=P9.81 η HQ = \frac{P}{9.81\,\eta\,H}

Head and efficiency are not given, so assume H=100H=100 m and η=0.85\eta=0.85: 9.81×0.85×100=833.859.81\times0.85\times100 = 833.85 kW per m³/s, i.e. Q=P/833.85Q=P/833.85 with PP in kW. The FDC has the same shape as the LDC.

RankPower (MW)Flow Q (m³/s)% of time exceeded
1550659.68.3
2500599.616.7
3450539.725.0
4380455.733.3
5330395.841.7
6280335.850.0
7250299.858.3
8220263.866.7
9200239.975.0
10150179.983.3
11145173.991.7
12100119.9100.0

So the flow required is 659.6 m³/s for 8.3% of the time, 263.8 m³/s for about 67% of the time and at least 119.9 m³/s all the year (flow scales as 1/(ηH)1/(\eta H) for other values). The plant must be able to deliver 550 MW; for the minimum months the river must provide at least the flow of the Baisakh row.

Answer: (a) diesel capacity = 0 MW with the stated imports (deficits 50, 55, 100 MW are fully covered); (b) FDC as tabulated, with Q = P/(9.81ηH).

  • 2072 Kartik · 2+2+2 marks

A hydropower plant receives design discharge of 25 m³/s from 150 m height. The annual output of the plant is 220 GWh. If the peak load demand is 30 MW, determine (i) annual load factor, (ii) capacity factor and (iii) utilization factor. Assume the overall efficiency of the plant equals 85% and neglect head loss in the penstock.

Answer

Installed capacity

Pinst=9.81 η Q H=9.81×0.85×25×150=31,269 kW=31.27 MWP_{inst} = 9.81\,\eta\,Q\,H = 9.81\times0.85\times25\times150 = 31,269\ \text{kW} = 31.27\ \text{MW}

Average load

Annual energy =220 GWh=220×106=220\ \text{GWh} = 220\times10^6 kWh.

Pavg=220×1068760=25,114 kW=25.114 MWP_{avg} = \frac{220\times10^6}{8760} = 25,114\ \text{kW} = 25.114\ \text{MW}

(i) Annual load factor

LF=PavgPpeak=25.11430=0.837 (≈83.7%)\text{LF} = \frac{P_{avg}}{P_{peak}} = \frac{25.114}{30} = 0.837\ (\approx 83.7\%)

(ii) Capacity (plant) factor

CF=EPinst×8760=220×10631,269×8760=0.803 (≈80.3%)\text{CF} = \frac{E}{P_{inst}\times8760} = \frac{220\times10^6}{31,269\times8760} = 0.803\ (\approx 80.3\%)

(iii) Utilization factor

UF=PpeakPinst=3031.27=0.959 (≈95.9%)\text{UF} = \frac{P_{peak}}{P_{inst}} = \frac{30}{31.27} = 0.959\ (\approx 95.9\%)

Check: CF = LF × UF = 0.837 × 0.959 = 0.803.

Answer: load factor = 0.837; capacity factor = 0.803; utilization factor = 0.959.

Questions from Old Question Collection (CE 704) (IOE exam papers from 2069 Chaitra to 2082 Bhadra). Answers are written for this site; check them against your class notes.

Chapter titles and hours from the IOE syllabus ↗