- 2081 Bhadra · 10 marks
RoR best installed capacity (USD 1200 million)
Short answer
With 10 m³/s left in the river, the optimum design flow is 2004 m³/s, yielding installed capacity 3652 MW. Firm energy is 1261 GWh, secondary energy 10197 GWh, total energy 11458 GWh, and plant factor 0.36.
The mean monthly flows of a river in a typical year are as follows:
| Month | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sept | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Flow (m³/s) | 93 | 89 | 115 | 209 | 593 | 1011 | 2014 | 2542 | 1450 | 830 | 196 | 118 |
The gross available head is 229 m, and the average head loss in transition is 12 m. The efficiencies of the turbines, gearboxes and generators are 94%, 92% and 99% respectively. 10 m³/s of water must be left in the river for downstream users. The other data are as follows: fixed cost = US$ 1200 × 10⁶; variable cost (present worth value) = US$ 500/kW; energy price = US$ 48/MWh for primary and secondary energy; interest rate = 12%; economic life of the project = 50 years. Determine the best installed capacity, firm energy, secondary energy, total energy and plant factor of a run-of-river plant.
The optimum capacity of a RoR plant is where the marginal benefit of the last unit of capacity equals its marginal cost (equivalently, where the net benefit is maximum). The fixed cost does not change with capacity, so it does not affect the optimum.
Data and constants
- Net head m (gross head minus the average transition loss)
- Overall efficiency (turbine × gearbox × generator)
- Fixed cost US$ 1200 × 10⁶; variable cost US$ 500/kW (present worth, annualised with the CRF); price US$ 48/MWh = US$ 0.048/kWh
- 10 m³/s is left in the river, so the available flow
- Capital recovery factor for , years
- Energy per month: (8760/12 h per month)
- Annual cost ; annual benefit = energy × price
Flow available for power
After deducting the 10 m³/s release, the available flows (m³/s) in descending order are: 2532, 2004, 1440, 1001, 820, 583, 199, 186, 108, 105, 83, 79.
Marginal check
Each extra 1 kW of capacity above a flow level is used only in the months in which the flow is greater than that level. A kW used for months produces MWh per year. The benefit per kW per month of use USD 35.04 per year; the annual cost of 1 kW USD 60.21, so a kW must be used for at least 1.72 months, i.e. at least 2 months. The 2nd highest flow is 2014 m³/s (2004 m³/s after the 10 m³/s release); capacity beyond that would be used for only 1 month.
Trial design discharges
| (m³/s) | P (MW) | Energy (GWh) | Benefit (USD M) | Cost (USD M) | Net (USD M) |
|---|---|---|---|---|---|
| 79 | 143.98 | 1,261.28 | 60.5 | 153.2 | -92.6 |
| 83 | 151.27 | 1,319.82 | 63.4 | 153.6 | -90.3 |
| 105 | 191.37 | 1,612.52 | 77.4 | 156.0 | -78.6 |
| 108 | 196.84 | 1,648.44 | 79.1 | 156.4 | -77.2 |
| 186 | 338.99 | 2,478.65 | 119.0 | 164.9 | -45.9 |
| 199 | 362.69 | 2,599.72 | 124.8 | 166.3 | -41.6 |
| 583 | 1,062.55 | 5,665.11 | 271.9 | 208.5 | 63.5 |
| 820 | 1,494.49 | 7,241.70 | 347.6 | 234.5 | 113.1 |
| 1001 | 1,824.37 | 8,204.96 | 393.8 | 254.3 | 139.5 |
| 1440 | 2,624.47 | 9,957.18 | 477.9 | 302.5 | 175.4 |
| 2004 | 3,652.39 | 11,457.94 | 550.0 | 364.4 | 185.6 |
| 2532 | 4,614.70 | 12,160.42 | 583.7 | 422.3 | 161.4 |
The net benefit is greatest at m³/s (available flow after the release; river flow 2014 m³/s).
Results
- Installed capacity: MW
- Firm (primary) energy, from the minimum available flow of 79 m³/s all year: GWh
- Total energy: GWh
- Secondary energy GWh
- Plant factor (35.8%)
Answer: best installed capacity = 3,652.4 MW (design flow 2004 m³/s); firm energy = 1,261.3 GWh; secondary energy = 10,196.7 GWh; total energy = 11,457.9 GWh; plant factor = 0.36.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RoR best installed capacity (USD 2795 million) · Hydropower Engineering, chapter 3
- RoR best installed capacity (NRs, 45 years) · Hydropower Engineering, chapter 3
- Installed capacity, energy and daily peaking reservoir (2079) · Hydropower Engineering, chapter 3 · asked 2×
- Installed capacity, energy and daily peaking reservoir (2072) · Hydropower Engineering, chapter 3 · asked 2×
- RoR capacity, peaking capacity and benefit · Hydropower Engineering, chapter 3
- Peaking RoR: max power and wet/dry energy ratio · Hydropower Engineering, chapter 3
- Best installed capacity at 10% interest · Hydro Power, chapter 3
- Best installed capacity at 12% interest · Hydro Power, chapter 3
- Firm and secondary energy from average monthly flows · Hydro Power, chapter 3