Short answer

Risk management is necessary because projects are uncertain, costly, and lenders require it; it prevents overruns and improves decisions. Risk natures include pure/speculative, internal/external, known/unknown, threat/opportunity. Hydropower risks include hydrological, geological, construction delay, cost overrun, financial, political, environmental, market/PPA, and natural hazards.

Why is project risk management necessary? What are the different natures of risk? Discuss the major types of risks that might occur in planning and implementing a hydropower project.

Why project risk management is necessary

  1. Projects are one-time and uncertain; many things can go wrong.
  2. Hydropower and other large projects need a big investment, so any loss is very costly.
  3. It prevents or reduces cost and time overruns.
  4. It helps to make better decisions and to use resources properly.
  5. Lenders and investors require it before approving a loan.
  6. It improves safety, quality and the chance of success.
  7. It converts problems into planned actions with reserves.

Different natures of risk

  • Pure (insurable) risk: only loss is possible (fire, flood, accident).
  • Speculative (business) risk: gain or loss is possible (market price, demand).
  • Internal / external, known / unknown, negative (threat) / positive (opportunity).

Major risks in planning and implementing a hydropower project

PhaseMajor risks
Planning / feasibilityWrong hydrology (flow) data, poor geological investigation, wrong demand and tariff forecast
FinancingDelay in loan, high interest, currency change, PPA (power purchase agreement) delay
Licensing / pre-constructionDelay in survey and generation licences, land acquisition and compensation, environmental (EIA) approval, local opposition
DesignDesign error, change in capacity, wrong tunnel/penstock design
ConstructionPoor rock condition in the tunnel, landslide, flood in river works, access road problems, contractor failure, accidents, price rise
Commissioning / operationSediment (silt) damage to turbines, low river flow, transmission line not ready, equipment failure, glacial lake outburst flood (GLOF), earthquake

Other main risks are geological and hydrological risk, construction delay, cost overrun, financial and exchange rate risk, political and regulatory risk, environmental and social risk, market and PPA risk (the Nepal Electricity Authority is the main buyer), and natural hazards. These are managed with detailed investigation, insurance, careful contracts, community engagement and a contingency reserve.