Strategies for threats and opportunities

Short answer

For negative risks: avoid (remove threat), transfer (shift impact to third party), mitigate (reduce probability/impact), and accept (with or without contingency). For positive risks: exploit (ensure it happens), enhance (increase probability/impact), share (partner), and accept.

What are strategies for negative risks or threats as well as strategies for positive risks or opportunities?

Risk response strategies are the options for dealing with risks. PMBOK separates strategies for negative risks (threats) and for positive risks (opportunities); one strategy, accept, is common to both.

Strategies for negative risks (threats)

  1. Avoid: change the plan or scope to eliminate the threat or protect objectives from its impact. Example: drop a high-risk feature, use proven technology, clarify requirements.
  2. Transfer: shift the negative impact and ownership of response to a third party; the risk is not eliminated. Example: insurance, performance bonds, warranties, fixed-price contract for outsourcing.
  3. Mitigate: reduce the probability or impact to an acceptable threshold. Example: more testing, prototypes, simpler design, backup systems, training.
  4. Accept: acknowledge the risk and take no action unless it occurs. Passive: do nothing; active: establish a contingency reserve or plan.

Strategies for positive risks (opportunities)

  1. Exploit: make sure the opportunity definitely happens. Example: assign the best people to finish early and gain a bonus.
  2. Enhance: increase the probability or positive impact by influencing its causes. Example: add resources to finish earlier.
  3. Share: allocate ownership to a third party best able to capture the opportunity. Example: joint venture, partnership.
  4. Accept: be willing to take the benefit if it occurs but do not actively pursue it.
Threat strategyOpportunity strategy
AvoidExploit
TransferShare
MitigateEnhance
AcceptAccept

Other strategies

  • Contingency response strategies: plan used only if a trigger occurs.
  • Fallback plan if contingency fails.
Risk -> Threat?  Avoid/Transfer/Mitigate/Accept
     -> Opportunity? Exploit/Share/Enhance/Accept

Example: A supplier delay threat is mitigated by using two suppliers; an opportunity of early completion with a bonus is enhanced by adding two developers.