Risk in construction projects and its management

Short answer

Risk is an uncertain event affecting project objectives, measured by probability × impact. More chance arises from uniqueness, long duration, outdoor work, many parties, and large resources. Manage by planning, identifying, analyzing, and responding (avoid, transfer, reduce, accept) while monitoring with a risk register.

Define the risk that may occur in a project. Why is there more chance of occurrence of risk in a construction project? Explain in detail how you effectively manage the different types of risk that may occur in a construction project.

Risk

Risk is an uncertain event or condition which, if it occurs, has a positive or negative effect on the project objectives (scope, time, cost, quality). It is measured by the probability of the event and the size of its impact: Risk = Probability x Impact.

Why construction projects have more chance of risk

  1. Every project is unique, with new site, design and conditions.
  2. Long duration, so more time for change in price, law and weather.
  3. Outdoor work exposed to rain, flood, earthquake and ground conditions that are not fully known.
  4. Many parties (owner, designer, contractor, subcontractors, suppliers) with different interests.
  5. Large amount of money, labour and equipment at one time.
  6. Dependence on approvals, land and utilities.
  7. Frequent design change and variations.
  8. Hazardous activities, so higher accident risk.
  9. Difficult access and logistics in Nepal.
  10. Use of the lowest-bid system and thin profit margins.

Managing the different types of risk

TypeManagement
Technical / designComplete investigation, design review, peer check, standard codes (reduce)
CostRealistic estimate, price adjustment clause, early purchase of material, contingency (reduce, transfer)
ScheduleDetailed CPM schedule, buffers, resource planning, liquidated damages (reduce)
FinancialFunds plan, assured payment, advance guarantee (transfer, reduce)
Contractual / legalClear contract, dispute board, legal review (avoid)
NaturalInsurance (CAR), seasonal planning, flood-resistant design (transfer, reduce)
SafetySafety plan, PPE, training, inspection (reduce)
Political and socialStakeholder consultation, community benefit, early land (avoid, reduce)
QualityQuality plan, testing, supervision (reduce)

Process followed: plan -> identify -> analyse (qualitative and quantitative) -> respond (avoid, transfer, reduce, accept) -> monitor and control. A risk register with owner, trigger and contingency is kept, and the process is repeated through the project.