Explanatory note: interface treatment

Short answer

Interface treatment provides a bond between pavement layers by sweeping clean and spraying a prime coat on granular bases (0.6-1.0 kg/m²) or a tack coat on bituminous surfaces (0.20-0.30 kg/m²), followed by curing. It prevents slippage, delamination, and water entry, and is done just before laying.

Write down an explanatory note on bituminous construction type: interface treatment.

Interface treatment is the preparation of the surface between two pavement layers (for example, between a granular base and a bituminous layer, or between an old and a new bituminous layer) to give a good bond. The surface is first swept clean and then sprayed with a prime coat on granular bases or a tack coat on bituminous or concrete surfaces. A good interface bond prevents slippage and delamination, helps the layers act together as one structure (reducing tensile strain at the bottom of the bituminous layer), and stops water entering between layers. Interface treatment is done just before laying, with the correct rate of spray (prime coat 0.6-1.0 kg/m2, tack coat 0.20-0.30 kg/m2) and sufficient curing/breaking time.

✓ Answer checked by Claude Opus 5.5 (high effort)

All Transportation Engineering II chapter 3 questions →