Skip to main content

Non-linear kinematic wave discharge at 1 km

Short answer

With Δt=900 s, Δx=1000 m, γ=Δt/Δx=0.9, upstream Q=14 m³/s, previous downstream Q=11 m³/s, α=3.2113, the implicit nonlinear scheme solved by Newton-Raphson gives Q at 1 km downstream = 12.67 m³/s.

Using the finite difference equation developed in the previous part (first order accurate implicit non-linear kinematic wave), compute the discharge at 1 km downstream of location X at time 14:00 hrs, for the following data: rectangular channel, width = 20 m, bed slope = 0.001, Manning's n=0.03n = 0.03. Discharge at location X at time 14:00 hrs = 14 m3^3/s; discharge at location X at time 13:45 hrs = 12 m3^3/s; discharge at 1 km downstream of location X at time 13:45 hrs = 11 m3^3/s. No lateral flow, wetted perimeter approximately equal to width of channel.

Use the first-order implicit scheme

ΔtΔxQi+1n+1+α(Qi+1n+1)β=ΔtΔxQin+1+α(Qi+1n)β\frac{\Delta t}{\Delta x}Q_{i+1}^{n+1}+\alpha\left(Q_{i+1}^{n+1}\right)^{\beta}=\frac{\Delta t}{\Delta x}Q_i^{n+1}+\alpha\left(Q_{i+1}^n\right)^\beta

with q=0q=0. Here ii is location X and i+1i+1 is the point 1 km downstream; nn is 13:45 and n+1n+1 is 14:00.

Data

Δx=1000\Delta x=1000 m, Δt=15×60=900\Delta t=15\times60=900 s, ΔtΔx=0.90\dfrac{\Delta t}{\Delta x}=0.90, Qin+1=14Q_i^{n+1}=14, Qin=12Q_i^n=12, Qi+1n=11Q_{i+1}^n=11 m3^3/s.

Step 1: Kinematic coefficients (P≈B=20P\approx B=20 m)

α=(nP2/3S01/2)0.6=(0.03×202/30.001)0.6=3.2113,β=0.6\alpha=\left(\frac{nP^{2/3}}{S_0^{1/2}}\right)^{0.6}=\left(\frac{0.03\times20^{2/3}}{\sqrt{0.001}}\right)^{0.6}=3.2113,\qquad \beta=0.6

Step 2: Equation to solve

Right side: 0.90(14)+3.2113(11)0.6=26.13690.90(14)+3.2113(11)^{0.6}=26.1369

f(x)=0.90 x+3.2113 x0.6−26.1369=0,f′(x)=0.90+1.9268 x−0.4f(x)=0.90\,x+3.2113\,x^{0.6}-26.1369=0,\qquad f'(x)=0.90+1.9268\,x^{-0.4}

Step 3: Newton iteration from x0=Qi+1n=11x_0=Q_{i+1}^n=11

Iterationxkx_kf(xk)f(x_k)xk+1x_{k+1}
111.0000-2.700012.6480
212.6480-0.034112.6693
312.6693-0.000012.6693
412.6693-0.000012.6693

Answer: the discharge 1 km downstream of X at 14:00 hrs is Qi+1n+1≈12.67Q_{i+1}^{n+1}\approx12.67 m3^3/s.

✓ Answer checked by Claude Opus 5.5 (high effort)