- 2070 Magh · 6 marks
First-order kinematic wave, flood peak at community
Short answer
Apply the first-order implicit scheme Q_{i+1}^{n+1} = (Q_{i+1}^n + C Q_i^{n+1})/(1+C) with c = 1.2 m/s, Δt = 1 h, Δx = 7.2 km, giving C = 0.6. The downstream peak discharge is (100 + 0.6×150)/1.6 = 118.75 m³/s.
A flood of 150 m/s peak discharge passed a gauging station at 12:00 noon on a river. There is a community adjacent to the river 7.2 km downstream. What will be the value of peak discharge at that community at 12:00 noon if the velocity of flow is 1.2 m/s [as printed] and the peak discharge at that community at 9:00 A.M. is 100 m/s? Assume width of river as [?] and use the first order accurate numerical scheme of the kinematic wave equation. Take km and hr.
The first-order accurate (implicit) scheme of the linear kinematic wave equation is
Interpretation of the data
- The gauging station is point ; the community ( km downstream) is .
- m/s (peak at the station at 12:00 noon).
- m/s is the flow already at the community at the earlier level (taken as the 9:00 A.M. value, with h per step).
- The velocity given as 1.2 (m/s) is used as the wave celerity ; the channel width is then not needed, because the equation is written in terms of .
Calculation
Answer: the discharge at the community at 12:00 noon is about 118.75 m/s (the peak is delayed and attenuated numerically). The data are incomplete in the question (width missing, unit of velocity printed as m/s), so this reading is assumed.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Non-linear kinematic wave discharge at 1 km · Computational Techniques in Civil Engineering, chapter 5
- Non-linear kinematic wave, trapezoidal river · Computational Techniques in Civil Engineering, chapter 5
- First-order implicit non-linear kinematic wave · Computational Techniques in Civil Engineering, chapter 5
- Second-order scheme, linear kinematic wave · Computational Techniques in Civil Engineering, chapter 5
- Second-order non-linear kinematic wave; FDM principle · Computational Techniques in Civil Engineering, chapter 5
- Linear kinematic wave, 200 ft channel · Computational Techniques in Civil Engineering, chapter 5
- Slope-area flood discharge, 7 km reach · Engineering Hydrology, chapter 4 · asked 2×
- Slope-area flood discharge, Marin River at Kusuntar · Engineering Hydrology, chapter 4
- Slope-area flood discharge, 6 km reach · Engineering Hydrology, chapter 4
- Gumbel 30-year flood, Lothar River 1989-2009 · Engineering Hydrology, chapter 6
All Computational Techniques in Civil Engineering chapter 5 questions →