Contractor cash flow estimate and critical stage

Short answer

Cash flow management is needed because expenses are paid before client payments, and late certification and retention create a financing gap. A typical cash flow estimate plots contract value, cost, and payments received; margin is value minus cost, deficit is cost minus payments. The most critical stage is early-to-middle work when the cost-payment gap is largest.

Why is cash flow management necessary for a contractor? Draw a typical cash flow estimate of a contractor showing the contract and contractor's margin and the most critical stage, with neat diagram.

Need for cash flow management

Cash flow is the movement of money in (client payments) and out (labour, material, equipment, overhead). A contractor needs to manage it because:

  • Expenses are paid before the client pays, so a shortage of cash can stop work.
  • Payments come late (bill certification, retention, delays), so the gap must be financed.
  • It shows how much working capital or bank overdraft is required, and when.
  • Interest on borrowing reduces profit; proper planning lowers it.
  • It allows timely payment of workers, suppliers and subcontractors, so the contractor keeps its credit.
  • It helps to plan the best time for bidding, purchases and mobilisation.

Typical cash flow estimate

The contractor plots three cumulative curves against time: the contract value of work done (V), the contractor's cost or expenditure (C), and the payments received (P), which lag behind V because of certification and payment delays and the retention. The gap between V and C is the contractor's margin (profit and overhead). The gap between C and P is the cash deficit that the contractor must finance.

 Cumulative Rs
  |                                    VVVVVVVVVVVVVVVVVVVVVVVV
  |                                VVVV     PPPPPPPPPPPPPPP    } margin (V - C)
  |                             VVV   CCCCCCCCCCCCCCCCCCCCCCCCC
  |                          VVV  CCCCPP
  |                        VV CCCC PP
  |                      VV CC  PPP
  |                   VVVCCC  PP
  |                 VVCCC   PP
  |               VVCC   PPP
  |            VVVC    PP
  |         VVVCC   PPP
  |     VVVVC   PPPP
  +----------------------------------------------------------> Time
  Start                ^              End of work
            largest gap C - P = most critical stage

 V = contract value of work done   C = contractor's cost
 P = payments received (lagging; P finally reaches V when
     the retention is released after the defects period)

Most critical stage

The most critical stage is the early-to-middle period of the work, when spending is fastest: the contractor has spent heavily on mobilisation, materials and wages, but the bills are not yet paid and retention (5% in PPR practice) is being deducted. The vertical gap between the cost and payment curves is largest here, so peak borrowing is needed. A mobilisation advance and prompt payment of running bills reduce this peak. Later, P rises above C, and at the end the contractor recovers the full margin.