Cash flow management: importance and preparation

Short answer

Cash flow management plans and monitors money inflows and outflows so funds are available when needed. Prepare by spreading activity costs monthly, adding markup, applying payment lag, retention, and advances, then plotting cumulative flows; the peak negative cumulative value is the peak financing requirement. It prevents cash shortages, helps arrange finance, and supports decisions.

What is cash flow management in a construction project? How is a cash flow prepared, and explain its importance for smooth running of the project.

Cash flow management

Cash flow is the movement of money into (receipts) and out of (payments) a project over time. Cash flow management is the planning, monitoring and control of these flows, so that enough money is available when payments fall due. A project may be profitable on paper but fail if there is no cash at the right time.

Preparation of a cash flow forecast

  1. Prepare the work programme (bar chart) and the cost of each activity (from the BOQ and rate analysis).
  2. Spread the cost of each activity over its duration, month by month, to obtain the monthly expenditure (outflow), including site overheads.
  3. Add the contractor's markup (head-office overhead and profit) to get the billing value for each month.
  4. Apply the payment terms: certification and payment lag (for example, one month), mobilisation advance and its recovery, retention (for example, 5%) and its release.
  5. Get the monthly inflow and the net cash flow = inflow - outflow; find the cumulative net cash flow.
  6. Plot the cumulative outflow and inflow (S-curves); the maximum negative cumulative value is the peak financing requirement.

Example

Cost of work Rs 10 million over 5 months; the contractor adds 10% for profit and overhead, so the contract value is Rs 11 million. The client pays 95% of each bill one month later; the 5% retention is released in month 7.

MonthOutflow (Rs m)Inflow (Rs m)NetCumulative
11.000.00-1.00-1.00
22.001.045-0.955-1.955
33.002.09-0.91-2.865
42.503.1350.635-2.23
51.502.61251.1125-1.1175
60.001.56751.56750.45
70.000.550.551.00

The contractor must arrange about Rs 2.87 million (the peak deficit, at the end of month 3) from its own funds or an overdraft. The final profit is Rs 1.0 million.

Importance

  • Shows when and how much money is needed, so finance and bank loans are arranged in time.
  • Prevents shortage of cash for labour, materials and subcontractors, so work is not delayed.
  • Helps to find the cost of financing (interest) and to include it in the bid.
  • Helps to negotiate the payment terms, advance and retention.
  • Lets management compare actual and planned cash and take early action.
  • Supports decisions on when to purchase materials, whether to hire or buy equipment, and on the expected profit.
  • For the client, it shows the budget needs over the project period.