- 2066 Magh (old course) · 16 marks
Road construction equipment, paver and bitumen sprayer
Short answer
Road equipment includes bulldozers, excavators, graders, rollers, water tankers, crushers, hot-mix plant, bitumen sprayer, chip spreader and paver. A paver receives hot mix, conveys it to augers, and the vibrating screed levels and compacts; sprayer heats bitumen and sprays uniformly at controlled rate. Both operate in a steady sequence followed by rolling.
Describe the different equipments used for road-construction. Explain the functions and sequence of operation of paver and bitumen sprayer.
Equipment for road construction
| Stage | Equipment |
|---|---|
| Clearing, earthwork | Bulldozer, excavator, scraper, dump truck |
| Shaping | Motor grader |
| Compaction | Smooth, pneumatic, vibratory, sheepsfoot rollers |
| Water | Water tanker |
| Aggregate | Crusher, screen, stone spreader |
| Bituminous mix | Hot-mix plant, bitumen heater/boiler, pugmill |
| Surfacing | Bitumen sprayer (distributor), chip spreader, paver |
| Concrete road | Batching plant, slip-form paver, finishers, joint cutters |
Paver (finisher)
tipper -> [hopper] -conveyor-> [auger] -> [screed]
(receives hot mix) spreads levels, compacts
Functions: receives hot mix from trucks, spreads it evenly across the width, and gives the specified thickness, camber and level, with initial compaction by the vibrating screed. Sequence of operation:
- Clean the base and apply a tack coat.
- Set the screed height (thickness) and the guide wire or sensors; pre-heat the screed.
- The tipper backs to the paver, which pushes it forward as hot mix is discharged to the hopper.
- The conveyor feeds the mix to the augers, which spread it in front of the screed.
- The screed levels and compacts the mat as the paver moves forward at a steady speed.
- Rollers (breakdown, intermediate, finish) follow immediately to compact.
Bitumen sprayer (distributor)
[Insulated tank + burner] pump spray bar
=========truck========== |||||||||||
(nozzles spray hot bitumen)
Functions: sprays bitumen (tack coat, prime coat, surface dressing binder) uniformly over the road surface at a controlled rate (kg/m) and temperature. Sequence:
- Heat the bitumen in the tank to the spraying temperature.
- Clean the base; set the spray bar height and the nozzles.
- Pump the bitumen through the spray bar as the truck moves at a uniform speed.
- Check the rate of application; avoid overlap or gaps at joints.
- Spread chippings immediately (for surface dressing) and roll.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Equipment used in hydropower construction · Construction Management, chapter 4
- Equipment for concrete construction and functions · Construction Management, chapter 4
- Equipment for highway and pavement construction · Construction Management, chapter 4 · asked 3×
- Advantages and disadvantages of construction equipment · Construction Management, chapter 4 · asked 6×
- Factors in selecting construction equipment · Construction Management, chapter 4 · asked 6×
- Tunnelling and rock drilling equipment · Construction Management, chapter 4 · asked 3×
- Road construction equipment and mass haul characteristics · Transportation Engineering II, chapter 3 · asked 3×
- Road construction equipment and DBSD procedure · Transportation Engineering II, chapter 3
- Construction equipment; prime, tack and seal coats · Transportation Engineering II, chapter 3
- Road construction activities; plants for bituminous and CC · Transportation Engineering II, chapter 3