System implementation and conversion
Short answer
System implementation is the phase where the designed system is built, tested, and put into operation. Steps include planning, acquisition, coding, testing, data conversion, training, and conversion. Conversion approaches: direct cutover, parallel, pilot, and phased.
What do you understand by system implementation? Discuss steps in system implementation along with different approaches in system conversion.
System implementation
System implementation is the phase of the system development life cycle in which the designed system is built or installed, tested, and put into operation so that the users start using it in place of the old system. It turns the design into a working system.
Steps in system implementation
- Planning the implementation: schedule, resources, responsibilities.
- Acquiring and installing hardware, software and network.
- Coding / customising and integrating the software.
- Testing: unit, integration, system and user acceptance testing.
- Data conversion and file preparation: old data are cleaned and loaded into the new system.
- Training of users and operators, and preparing documentation.
- Conversion / changeover to the new system.
- Post-implementation review and support.
Approaches to system conversion
| Approach | Description | Pros / cons |
|---|---|---|
| Direct (cold turkey) | The old system is stopped and the new one starts at once | Cheap and fast, but risky |
| Parallel | Both systems run together for a period and outputs are compared | Safe, but costly and double work |
| Pilot | The new system is tried in one branch/department first | Limits risk; takes longer |
| Phased (staged) | Modules or locations are converted step by step | Easier control; needs interfaces between old and new |
Direct: Old ------| New ------>
Parallel: Old ----------|
New ---------->
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- CSFs of IS implementation · Information System, chapter 6
- Strategic information system and benefits · Information System, chapter 1 · asked 2×
- DSM concept; planning and implementation steps · Utilization of Electrical Energy, chapter 6
- Short note: Distributed system implementation · Object Oriented Analysis and Design, chapter 4
- File system layout; interface vs implementation · Operating System, chapter 5
- Design steps and criteria of distribution system · Water Supply Engineering, chapter 7 · asked 3×