- 2062 Poush · 8 marks
True horizontal distance from slope distances
The following slope distances were measured along a chain line with a 30 m tape.
Slope distance (m) = 25.50, 24.60, 28.70, 29.50 and 18.50.
Difference of elevation between ends (m) = 2.50, 5.30, 3.35, 2.50 and 1.50.
It was noted afterwards that the tape was 2 cm too long. Find the true horizontal distance.
Method. The tape is 30.02 m, 2 cm too long, so every reading is too small. First each slope distance is corrected for tape length, then reduced to horizontal using the height difference :
| Slope (m) | (m) | Corrected slope (m) | Horizontal (m) |
|---|---|---|---|
| 25.50 | 2.50 | 25.5170 | 25.3942 |
| 24.60 | 5.30 | 24.6164 | 24.0391 |
| 28.70 | 3.35 | 28.7191 | 28.5231 |
| 29.50 | 2.50 | 29.5197 | 29.4136 |
| 18.50 | 1.50 | 18.5123 | 18.4515 |
| Total | 125.8215 |
(The total measured slope length is 126.80 m.)
Answer: true horizontal distance m.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Correct horizontal distance, 28.00 m measured · Surveying I, chapter 2
- Horizontal length of 16 m, 29.8850 m tape · Surveying I, chapter 2
- Horizontal length of 30 m span, 50 m tape · Surveying I, chapter 2
- True length of 1020 m line, 20 m tape · Surveying I, chapter 2 · asked 2×
- Correct horizontal distance 630 m, tape 8.9 N · Surveying I, chapter 2
- Tape correction for 24.726 m distance · Surveying I, chapter 2 · asked 2×
- Subnet 202.70.91.0/24 for 25, 16, 29, 11 · Computer Networks and Security, chapter 4 · asked 2×
- AVL tree for 10, 20, 30, 35, 50, ... · Data Structure and Algorithm, chapter 6
- Conductor selection, 100 MW 70 km 132 kV · Transmission and Distribution System Design, chapter 4
- Subnet 202.77.19.0/24 for 30, 24, 25, 20 · Computer Networks and Security, chapter 4