Aggregate reserve: sandstone N42W/34, 80 m
Short answer
True thickness t = 80 cos34° ≈ 66.3 m. Area on bed = 2.5 km × 0.5 km = 1.25×10⁶ m². Volume = 1.25×10⁶ m² × 66.3 m = 8.29×10⁷ m³.
The attitude of sandstone is N42°W/34°. The difference of top and bottom of bed rock is 80 m. Calculate the reserve of aggregate in 2.5 km strike length and 0.5 km dip length of rock quarry site.
Principle: the area of the quarry on the bed surface = strike length dip length; reserve = area true thickness, with .
Given
Attitude N42°W/34° (dip ), vertical thickness (top to bottom) m, strike length 2.5 km, dip length 0.5 km (taken along the dip of the bed).
Calculation
Answer: reserve of aggregate = 8.29 × 10⁷ m³ (about 82.9 million m³ = 0.083 km³).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Aggregate reserve: sandstone N44W/36, 82 m · Engineering Geology II, chapter 7 · asked 2×
- Aggregate reserve: sandstone 300 m, 227 km2 · Engineering Geology II, chapter 7 · asked 2×
- Sandstone attitude: A N45W 900 m, C S20E 700 m · Engineering Geology II, chapter 6
- Reserve: quartzite apparent dips 1:9 and 1:12, 2.7 x 3.1 km · Engineering Geology II, chapter 7 · asked 2×
- Reserve: quartzite apparent dips 1:9 and 1:12, 4.6 km2 · Engineering Geology II, chapter 7 · asked 2×
- Sandstone attitude in oil field (feet) · Engineering Geology II, chapter 6
- Reserve: limestone dip 30, apparent 20 m · Engineering Geology II, chapter 7
- Strike of quartzite bed, dip 80° towards N10°E · Engineering Geology I, chapter 5
- Strike of quartzite bed, dip 70° towards S20°E · Engineering Geology I, chapter 5
- Strike of limestone bed directed N20°E, dip 45° · Engineering Geology I, chapter 5
- Strike of limestone bed, dip N40°W, 64° · Engineering Geology I, chapter 5