- 2071 Magh · 3 marks
Rock classes needing steel rib and shotcrete
Short answer
Steel ribs and thick shotcrete are required for Class IV (Poor) and Class V (Very poor). Class IV uses light to medium ribs at1.5 m spacing where necessary and 100–150 mm shotcrete; Class V demands medium to heavy ribs at0.75 m and150–200 mm shotcrete applied immediately.
According to the RMR system, which rock mass classes require steel rib and thick shotcrete for support of underground excavation?
According to the RMR system (Bieniawski, 1989) the classes needing steel ribs together with shotcrete are the two weakest:
| Class | RMR | Steel ribs | Shotcrete |
|---|---|---|---|
| IV (Poor) | 21 to 40 | Light to medium ribs at 1.5 m spacing, where required | 100 to 150 mm crown, 100 mm sides |
| V (Very poor) | below 20 | Medium to heavy ribs at 0.75 m with steel lagging and forepoling if required; close the invert | 150 to 200 mm crown, 150 mm sides, 50 mm on the face |
Class V definitely needs steel ribs and thick shotcrete, applied immediately after blasting. For Class IV ribs are used where required (weak zones, high water or squeezing), with thick shotcrete. Classes I to III do not need steel sets.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RMR fair rock support and excavation · Engineering Geology II, chapter 6 · asked 6×
- RMR poor rock support and excavation · Engineering Geology II, chapter 6 · asked 2×
- RMR class II support and excavation · Engineering Geology II, chapter 6 · asked 7×
- RMR class IV support and excavation · Engineering Geology II, chapter 6 · asked 6×
- RMR rock mass classification · Engineering Geology II, chapter 6 · asked 8×
- Role of RMR in underground design · Engineering Geology II, chapter 6 · asked 2×
- Two-hinged arch: thrust with rib shortening, support yield · Theory of Structures II, chapter 2
- Underground water tank: excavation, brick, plaster · Estimating and Costing, chapter 6
- RMR system and its parameters · Engineering Geology I, chapter 5 · asked 2×
- Underground RCC tank: brickwork, steel (fig a) · Estimating and Costing, chapter 6