Excavation:7.05×4.05×2.20 =62.82 m³. Brickwork in five stepped sections:17.644 m³. Inner plaster 1.5 cm thick:29.92 m² (3.28 bags cement,0.456 m³ sand).
The plan and section of the under-ground water tank which is fully constructed below the ground level. Find the quantities of a) Earthwork in excavation for construction. b) Brickwork in 1:6 cement sand mortar. c) Plastering work for inner part of tank. [Figure: Underground water tank. Top plan: outer 550 cm × 250 cm plus 30 cm wall all round (30 | 550 | 30 and 30 | 250 | 30). Sectional elevation: wall stepped with offsets of 30, 40, 50, 60 and 70 cm widths in 40 cm high steps, total height 190 cm, base footing 85 cm wide with 30 cm thick lime concrete, 3 cm thick C.C. flooring, outer plaster 1.2 cm thick 1:6 C:S, inner plaster 1.5 cm thick 1:4 C:S.]
Reading of the figure and assumptions
- Clear internal plan m. The wall is stepped on the outside only, inside face vertical. Widths m; heights m for the top step and m for each of the other four (total wall height m).
- Base footing: lime concrete m thick, m wide (0.075 m projection on each face of the 0.70 m base). The tank is fully below ground, so the top of the wall is at ground level and excavation depth is m.
- Floor: 3 cm C.C. flooring on the lime concrete; inner plaster 1.5 cm in 1:4 from floor to top of wall.
a) Earthwork in excavation
Footing outer size: length m; width m.
m³ (no working space or side slope allowed).
b) Brickwork in 1:6 mortar (centre-line method for each step)
| Thickness (m) | Height (m) | Centre-line length (m) | Volume (m³) |
|---|---|---|---|
| 0.30 | 0.30 | 1.548 | |
| 0.40 | 0.40 | 2.816 | |
| 0.50 | 0.40 | 3.600 | |
| 0.60 | 0.40 | 4.416 | |
| 0.70 | 0.40 | 5.264 | |
| Total | 17.644 |
c) Inner plaster 1.5 cm (1:4)
- Inner perimeter m; plastered height m (above the floor).
- Area m²
- Wet mortar m³; dry m³; cement m³ bags; sand m³
Answer: excavation = 62.82 m³; brickwork = 17.644 m³; inner plaster = 29.92 m² (3.28 bags cement, 0.456 m³ sand).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Underground RCC tank: brickwork, steel (fig a) · Estimating and Costing, chapter 6
- Double room: excavation, CRS, brick, plaster · Estimating and Costing, chapter 6
- Two-room building: excavation, PCC, brick, plaster · Estimating and Costing, chapter 6
- Load bearing building: excavation, brick, plaster · Estimating and Costing, chapter 6
- Single room: excavation, brickwork, plaster, shutter · Estimating and Costing, chapter 6
- Building: excavation, brick, paneled door, plaster · Estimating and Costing, chapter 6
- Cement and sand for 100 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Cement and sand for 200 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Mortar properties; cement and sand for 10 cum · Building Technology, chapter 3
- Detailed specification of brick work in 1:4 mortar · Construction Management, chapter 12 · asked 5×