Cement and sand for 100 m² plastering numerical

Short answer

For 100 m² plaster 12 mm thick in 1:6 mix: wet volume 1.2 m³, dry volume 1.524 m³. Cement = 0.218 m³ (about 6.3 bags of 50 kg); sand = 1.306 m³.

Find out the quantities of cement and sand for 100 m² plastering area in 1:6 ratio if the thickness of plaster is 12mm.

Given: plastering area =100 m2= 100\ \text{m}^2; thickness =12= 12 mm; mix 1:6 (cement : sand).

Step 1: Wet volume of mortar

100×0.012=1.2 m3100 \times 0.012 = 1.2\ \text{m}^3

Step 2: Dry volume (add 27% for dry bulk, voids in sand and wastage)

1.2×1.27=1.524 m31.2 \times 1.27 = 1.524\ \text{m}^3

Step 3: Cement and sand (sum of ratio =7= 7)

Cement=1.5247=0.218 m3≈6.3 bags (0.0347 m3 per bag)\text{Cement} = \frac{1.524}{7} = 0.218\ \text{m}^3 \approx 6.3\ \text{bags (0.0347 m}^3\text{ per bag)} Sand=67×1.524=1.306 m3\text{Sand} = \frac{6}{7} \times 1.524 = 1.306\ \text{m}^3

Answer: Cement = 0.218 m³ (about 6.3 bags of 50 kg = 314 kg); sand = 1.306 m³.