- 2066 Bhadra (old course) · 10 marks
Materials: 100 m² plaster 1:6, 100 m³ PCC 1:2:4
Short answer
For 100 m2 12 mm plaster (1:6), wet mortar 1.2 m3, dry 1.524 m3: cement 6.27 bags, sand 1.31 m3. For 100 m3 PCC (1:2:4), dry volume 154 m3: cement 633.6 bags, sand 44 m3, aggregate 88 m3.
Calculate the quantities of material required for following works. i) 100 m² cement sand plaster 12 mm thick in (1:6) ii) 100 m³ P.C.C. (1:2:4).
Assumptions: dry volume 1.27 × wet for mortar and 1.54 × wet for concrete; 1 m³ cement = 28.8 bags; no wastage.
(i) 100 m² of 12 mm plaster (1:6)
- Wet mortar m³; dry volume m³
- Cement m³ bags
- Sand m³
(ii) 100 m³ of PCC (1:2:4)
- Wet volume m³; dry volume m³ (sum of ratio )
- Cement m³ bags (50 kg)
- Sand m³
- Coarse aggregate m³
Answer: (i) cement 6.3 bags, sand 1.31 m³. (ii) cement 633.6 bags, sand 44.00 m³, aggregate 88.00 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Materials: 115 m² PCC floor, 110 m² plaster · Estimating and Costing, chapter 4 · asked 2×
- Materials: 105 m³ PCC 1:4:8, 725 m² plaster · Estimating and Costing, chapter 4 · asked 2×
- Materials: 12 mm plaster 1:6 per 10 m² · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Materials: 150 m³ brick 1:4, 120 m² plaster · Estimating and Costing, chapter 4
- Materials: 10 m³ brick 1:4, 100 m³ PCC 1:3:6 · Estimating and Costing, chapter 4 · asked 2×
- Cement and sand for 100 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Cement and sand for 200 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Mortar properties; cement and sand for 10 cum · Building Technology, chapter 3
- Detailed specification of cement plaster 1:4 · Construction Management, chapter 12