- 2071 Magh · 8 marks
Mortar properties; cement and sand for 10 cum
Short answer
For 10 m³ brickwork with standard bricks (240x115x57 mm) and 10 mm joints using 1:4 mortar: 4777 bricks, wet mortar 2.485 m³, dry volume 3.156 m³. Cement required 0.631 m³ (≈18.2 bags of 50 kg), sand 2.53 m³.
What are the properties of mortar? Find out the quantities of cement and sand from the mortar used in 10 cum brick work.
Properties of mortar
- Workability: easy to mix, spread and lay without segregation.
- Water retentivity: holds enough water, so bricks do not absorb it quickly.
- Adhesion and bond strength with brick or stone.
- Strength: adequate compressive strength (1:4 cement mortar 7.5 N/mm² at 28 days).
- Durability: resists weather, frost and chemicals.
- Proper setting time and low shrinkage.
- Impermeable and economical.
Cement and sand for 10 cum brickwork
The question gives no data, so assume: brick 240 x 115 x 57 mm (actual size, without mortar), 10 mm joints, mortar 1:4 (cement : sand), and dry volume = 1.27 x wet volume.
Given: brickwork volume .
Step 1: Size of brick with mortar
Step 2: Number of bricks
Step 3: Volume of bricks without mortar
Step 4: Wet volume of mortar
Step 5: Dry volume of mortar (add 27% for dry bulk, voids in sand, wastage and shrinkage)
Step 6: Cement and sand for 1:4 (sum of ratio )
Answer: Cement = 0.631 m³ (about 18.2 bags); sand = 2.53 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Masonry work, materials for 20 cum brickwork · Building Technology, chapter 3
- Cement and sand for 100 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Cement and sand for 200 m² plastering numerical · Building Technology, chapter 3 · asked 2×
- Mortar for 10 m³ brickwork (1:4) numerical · Building Technology, chapter 3
- First class brickwork in 1:6 mortar numerical · Building Technology, chapter 3
- Preparing cement mortar by manual process · Building Technology, chapter 3 · asked 2×
- Detailed specification of brick work in 1:4 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of brick work in 1:6 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of cement sand mortar 1:4 · Construction Management, chapter 12 · asked 2×
- Detailed specification of cement sand mortar 1:6 · Construction Management, chapter 12 · asked 2×