Mortar properties; cement and sand for 10 cum

Short answer

For 10 m³ brickwork with standard bricks (240x115x57 mm) and 10 mm joints using 1:4 mortar: 4777 bricks, wet mortar 2.485 m³, dry volume 3.156 m³. Cement required 0.631 m³ (≈18.2 bags of 50 kg), sand 2.53 m³.

What are the properties of mortar? Find out the quantities of cement and sand from the mortar used in 10 cum brick work.

Properties of mortar

  1. Workability: easy to mix, spread and lay without segregation.
  2. Water retentivity: holds enough water, so bricks do not absorb it quickly.
  3. Adhesion and bond strength with brick or stone.
  4. Strength: adequate compressive strength (1:4 cement mortar ≈\approx 7.5 N/mm² at 28 days).
  5. Durability: resists weather, frost and chemicals.
  6. Proper setting time and low shrinkage.
  7. Impermeable and economical.

Cement and sand for 10 cum brickwork

The question gives no data, so assume: brick 240 x 115 x 57 mm (actual size, without mortar), 10 mm joints, mortar 1:4 (cement : sand), and dry volume = 1.27 x wet volume.

Given: brickwork volume =10 m3= 10\ \text{m}^3.

Step 1: Size of brick with mortar

(0.25×0.125×0.067)=0.002094 m3(0.25 \times 0.125 \times 0.067) = 0.002094\ \text{m}^3

Step 2: Number of bricks

N=100.002094=4776.1≈4777 bricksN = \frac{10}{0.002094} = 4776.1 \approx 4777\ \text{bricks}

Step 3: Volume of bricks without mortar

4777×0.24×0.115×0.057=7.515 m34777 \times 0.24 \times 0.115 \times 0.057 = 7.515\ \text{m}^3

Step 4: Wet volume of mortar

10−7.515=2.485 m310 - 7.515 = 2.485\ \text{m}^3

Step 5: Dry volume of mortar (add 27% for dry bulk, voids in sand, wastage and shrinkage)

2.485×1.27=3.156 m32.485 \times 1.27 = 3.156\ \text{m}^3

Step 6: Cement and sand for 1:4 (sum of ratio =5= 5)

Cement=15×3.156=0.631 m3=909 kg≈18.2 bags (50 kg, 0.0347 m3 each)\text{Cement} = \frac{1}{5} \times 3.156 = 0.631\ \text{m}^3 = 909\ \text{kg} \approx 18.2\ \text{bags (50 kg, 0.0347 m}^3\text{ each)} Sand=45×3.156=2.525 m3\text{Sand} = \frac{4}{5} \times 3.156 = 2.525\ \text{m}^3

Answer: Cement = 0.631 m³ (about 18.2 bags); sand = 2.53 m³.