Mortar for 10 m³ brickwork (1:4) numerical

Short answer

For 10 m³ brickwork, compute brick count (4777 nos.) and subtract dry brick volume (7.515 m³) to get wet mortar 2.485 m³; dry volume is 3.156 m³ (×1.27). For 1:4 mortar, cement = 1/5 × 3.156 = 0.631 m³ (18.2 bags) and sand = 2.525 m³.

Calculate mortar required for construction of 10 m³ first class brickwork using 1:4 cement sand mortar. (Size of brick = 57 mm × 115 mm × 240 mm and thickness of mortar = 10 mm)

Given: brickwork volume =10 m3= 10\ \text{m}^3; brick size 57 mm x 115 mm x 240 mm (actual size, without mortar); mortar joint =10= 10 mm; mortar 1:4 (cement : sand).

Step 1: Size of brick with mortar

(0.25×0.125×0.067)=0.002094 m3(0.25 \times 0.125 \times 0.067) = 0.002094\ \text{m}^3

Step 2: Number of bricks

N=100.002094=4776.1≈4777 bricksN = \frac{10}{0.002094} = 4776.1 \approx 4777\ \text{bricks}

Step 3: Volume of bricks without mortar

4777×0.24×0.115×0.057=7.515 m34777 \times 0.24 \times 0.115 \times 0.057 = 7.515\ \text{m}^3

Step 4: Wet volume of mortar

10−7.515=2.485 m310 - 7.515 = 2.485\ \text{m}^3

Step 5: Dry volume of mortar (add 27% for dry bulk, voids in sand, wastage and shrinkage)

2.485×1.27=3.156 m32.485 \times 1.27 = 3.156\ \text{m}^3

Step 6: Cement and sand for 1:4 (sum of ratio =5= 5)

Cement=15×3.156=0.631 m3=909 kg≈18.2 bags (50 kg, 0.0347 m3 each)\text{Cement} = \frac{1}{5} \times 3.156 = 0.631\ \text{m}^3 = 909\ \text{kg} \approx 18.2\ \text{bags (50 kg, 0.0347 m}^3\text{ each)} Sand=45×3.156=2.525 m3\text{Sand} = \frac{4}{5} \times 3.156 = 2.525\ \text{m}^3

Answer: Mortar required for 10 m³ brickwork = 2.49 m³ (wet) or 3.16 m³ (dry); this needs about 0.631 m³ cement (18.2 bags) and 2.53 m³ sand; bricks = 4777 nos.