Mortar for 1.5 m³ brickwork numerical

Short answer

Brick faces: stretcher (240×57 mm), header (115×57 mm), bed (240×115 mm), frog, arris. For 1.5 m³ brickwork with 1:4 mortar: wet mortar 0.372 m³, dry 0.472 m³; cement 0.094 m³ (2.7 bags) and sand 0.378 m³; bricks 717 nos.

Define with sketch and labelling the various faces of a brick. Calculate the quantity of mortar required for the construction of 1.5 m³ first class brick work using 1:4 cement mortar.

Faces of a brick

A brick (standard 240 x 115 x 57 mm) has the following faces and parts:

  • Stretcher (side) face: the longest vertical face, 240 x 57 mm; it shows in a stretcher course.
  • Header (end) face: the small end face, 115 x 57 mm; it shows in a header course.
  • Bed (top / bottom) face: the horizontal face, 240 x 115 mm, on which mortar is spread.
  • Frog: a depression (about 10 mm deep) in the top bed face which holds mortar.
  • Arris: the edge where two faces meet.
           240 (length)
      +----------------+
     /|               /|
    / |  top (bed)    / |  57
   +----------------+  |  (height)
   |  | header face |  |
   |  +-------------|--+
   | /  stretcher   | /  115 (width)
   +----------------+

Mortar for 1.5 m³ brickwork in 1:4

Given: brickwork volume =1.5 m3= 1.5\ \text{m}^3; brick size 57 mm x 115 mm x 240 mm (actual size, without mortar); mortar joint =10= 10 mm; mortar 1:4 (cement : sand).

Step 1: Size of brick with mortar

(0.25×0.125×0.067)=0.002094 m3(0.25 \times 0.125 \times 0.067) = 0.002094\ \text{m}^3

Step 2: Number of bricks

N=1.50.002094=716.4≈717 bricksN = \frac{1.5}{0.002094} = 716.4 \approx 717\ \text{bricks}

Step 3: Volume of bricks without mortar

717×0.24×0.115×0.057=1.128 m3717 \times 0.24 \times 0.115 \times 0.057 = 1.128\ \text{m}^3

Step 4: Wet volume of mortar

1.5−1.128=0.372 m31.5 - 1.128 = 0.372\ \text{m}^3

Step 5: Dry volume of mortar (add 27% for dry bulk, voids in sand, wastage and shrinkage)

0.372×1.27=0.472 m30.372 \times 1.27 = 0.472\ \text{m}^3

Step 6: Cement and sand for 1:4 (sum of ratio =5= 5)

Cement=15×0.472=0.094 m3=136 kg≈2.7 bags (50 kg, 0.0347 m3 each)\text{Cement} = \frac{1}{5} \times 0.472 = 0.094\ \text{m}^3 = 136\ \text{kg} \approx 2.7\ \text{bags (50 kg, 0.0347 m}^3\text{ each)} Sand=45×0.472=0.378 m3\text{Sand} = \frac{4}{5} \times 0.472 = 0.378\ \text{m}^3

Answer: Mortar = 0.372 m³ (wet), 0.472 m³ (dry); cement 0.094 m³ and sand 0.378 m³; bricks = 717 nos.