Masonry work, materials for 20 cum brickwork

Short answer

For 20 m³ brickwork using bricks 230×110×55 mm, 10 mm joints, 1:6 mortar: 10684 bricks needed. Wet mortar = 5.133 m³, dry = 6.519 m³. Cement = 0.931 m³ (≈26.8 bags), sand = 5.588 m³.

What do you mean by Masonry work? Calculate the quantity of materials for the construction of 20 cum. Brick masonry in 1:6 C/S mortar using Brick Size 230 mm × 110 mm × 55 mm.

Masonry work

Masonry is the construction of a structure by building up units such as bricks, stones or concrete blocks, bonded together with mortar. When the units are bricks it is called brick masonry; when they are stones it is called stone masonry. Good masonry has a strong bond, plumb and level courses, fully filled joints and proper curing.

Materials for 20 cum brickwork in 1:6 mortar

Given: brickwork volume =20 m3= 20\ \text{m}^3; brick size 230 mm x 110 mm x 55 mm (actual size, without mortar); mortar joint =10= 10 mm; mortar 1:6 (cement : sand).

Step 1: Volume of one brick with mortar (240 mm x 120 mm x 65 mm)

0.24×0.12×0.065=0.001872 m30.24 \times 0.12 \times 0.065 = 0.001872\ \text{m}^3

Step 2: Number of bricks

N=200.001872=10683.8≈10684 bricksN = \frac{20}{0.001872} = 10683.8 \approx 10684\ \text{bricks}

Step 3: Volume of bricks without mortar

10684×0.23×0.11×0.055=14.867 m310684 \times 0.23 \times 0.11 \times 0.055 = 14.867\ \text{m}^3

Step 4: Wet volume of mortar

20−14.867=5.133 m320 - 14.867 = 5.133\ \text{m}^3

Step 5: Dry volume of mortar (add 27% for dry bulk, voids in sand, wastage and shrinkage)

5.133×1.27=6.519 m35.133 \times 1.27 = 6.519\ \text{m}^3

Step 6: Cement and sand for 1:6 (sum of ratio =7= 7)

Cement=17×6.519=0.931 m3=1341 kg≈26.8 bags (50 kg, 0.0347 m3 each)\text{Cement} = \frac{1}{7} \times 6.519 = 0.931\ \text{m}^3 = 1341\ \text{kg} \approx 26.8\ \text{bags (50 kg, 0.0347 m}^3\text{ each)} Sand=67×6.519=5.588 m3\text{Sand} = \frac{6}{7} \times 6.519 = 5.588\ \text{m}^3

Answer: Bricks = 10684 nos.; cement = 0.931 m³ (about 26.8 bags); sand = 5.59 m³.