Materials for brickwork 1:4 (230×110×55)

Short answer

Brick 230x110x55 mm, mortar 10 mm gives 534 bricks per m³ with mortar. Per m³: 535 bricks, 1.88 bags cement, 0.261 m³ sand. Per 10 m³: 5,342 bricks, 18.8 bags cement, 2.61 m³ sand.

Prepare materials required for an item of brickwork in cement mortar (1:4). Size of brick is 230 mm × 110 mm × 55 mm, with mortar joint 10 mm.

Assumptions: dry volume = 1.54 × wet volume for concrete and 1.27 × wet volume for mortar; 1 m³ of cement = 28.8 bags of 50 kg; no wastage is added. The volume of brickwork is not stated, so quantities are found per 1 m³ and per 10 m³.

Per 1 m³ brickwork

  • Brick with mortar =0.240×0.120×0.065=1872.0×10−6= 0.240 \times 0.120 \times 0.065 = 1872.0\times 10^{-6} m³; bricks per m³ =1/1872.0×106=534.19= 1/1872.0\times10^6 = 534.19
  • Bricks for 1.00 m³ =534.19×1.00=534= 534.19 \times 1.00 = 534 nos (say 535)
  • Volume of bricks only =0.230×0.110×0.055=1391.5×10−6= 0.230\times0.110\times0.055 = 1391.5\times10^{-6} m³ each; wet mortar per m³ =1−534.19×1391.5×10−6=0.2567= 1 - 534.19\times1391.5\times10^{-6} = 0.2567 m³
  • Wet mortar for 1.00 m³ =0.257= 0.257 m³; dry =1.27×0.257=0.326= 1.27\times0.257 = 0.326 m³
  • Cement =1/5×0.326=0.065= 1/5\times0.326 = 0.065 m³ =1.9= 1.9 bags
  • Sand =4/5×0.326=0.261= 4/5\times0.326 = 0.261 m³

Per 10 m³ brickwork

  • Brick with mortar =0.240×0.120×0.065=1872.0×10−6= 0.240 \times 0.120 \times 0.065 = 1872.0\times 10^{-6} m³; bricks per m³ =1/1872.0×106=534.19= 1/1872.0\times10^6 = 534.19
  • Bricks for 10.00 m³ =534.19×10.00=5,342= 534.19 \times 10.00 = 5,342 nos (say 5,342)
  • Volume of bricks only =0.230×0.110×0.055=1391.5×10−6= 0.230\times0.110\times0.055 = 1391.5\times10^{-6} m³ each; wet mortar per m³ =1−534.19×1391.5×10−6=0.2567= 1 - 534.19\times1391.5\times10^{-6} = 0.2567 m³
  • Wet mortar for 10.00 m³ =2.567= 2.567 m³; dry =1.27×2.567=3.260= 1.27\times2.567 = 3.260 m³
  • Cement =1/5×3.260=0.652= 1/5\times3.260 = 0.652 m³ =18.8= 18.8 bags
  • Sand =4/5×3.260=2.608= 4/5\times3.260 = 2.608 m³

Answer: per m³ about 535 bricks, 1.88 bags cement, 0.261 m³ sand; per 10 m³: 5,342 bricks, 18.8 bags cement, 2.61 m³ sand.