Short answer

Wall volume 27.60 m³ yields 14,012 bricks (nominal size 235×110×57 mm with 10 mm joint). Mortar dry volume 8.832 m³ for 1:6 mix: cement 36.3 bags, sand 7.57 m³.

Calculate the quantities of materials required for a 100 m long, 23 cm thick and 1.20 m high wall in (1:6) cement mortar. (Assume size of brick is 235 × 110 × 57 mm and thickness of mortar 10 mm.)

Assumptions: dry volume = 1.54 × wet volume for concrete and 1.27 × wet volume for mortar; 1 m³ of cement = 28.8 bags of 50 kg; no wastage is added.

Volume of wall

V=100×0.23×1.20=27.60V = 100 \times 0.23 \times 1.20 = 27.60 m³ (23 cm = two bricks of 110 mm plus one 10 mm joint).

Quantities (brick 235 × 110 × 57 mm, joint 10 mm, mortar 1:6)

Brickwork 1:6

  • Brick with mortar =0.245×0.120×0.067=1969.8×10−6= 0.245 \times 0.120 \times 0.067 = 1969.8\times 10^{-6} m³; bricks per m³ =1/1969.8×106=507.67= 1/1969.8\times10^6 = 507.67
  • Bricks for 27.60 m³ =507.67×27.60=14,012= 507.67 \times 27.60 = 14,012 nos (say 14,012)
  • Volume of bricks only =0.235×0.110×0.057=1473.4×10−6= 0.235\times0.110\times0.057 = 1473.4\times10^{-6} m³ each; wet mortar per m³ =1−507.67×1473.4×10−6=0.2520= 1 - 507.67\times1473.4\times10^{-6} = 0.2520 m³
  • Wet mortar for 27.60 m³ =6.955= 6.955 m³; dry =1.27×6.955=8.832= 1.27\times6.955 = 8.832 m³
  • Cement =1/7×8.832=1.262= 1/7\times8.832 = 1.262 m³ =36.3= 36.3 bags
  • Sand =6/7×8.832=7.571= 6/7\times8.832 = 7.571 m³

Answer: bricks = 14,012 nos; cement = 36.3 bags; sand = 7.57 m³.