Brick masonry pier: brickwork and pointing

Short answer

Assuming a stepped pier with two footing steps, shaft, and cap, brickwork volumes are summed: total 3.216 m³. Pointing area is computed for exposed faces above ground: shaft faces, cap vertical faces, overhang underside, and top surface, totaling 10.67 m².

From the drawing attached of the brick masonry pier (Fig. 2), calculate the total quantity of brick work and also the pointing work. [Figure 2 not included in the scanned paper]

The pier drawing is not available, so the method is shown for an assumed stepped brick pier: two footing steps, a square shaft and a projecting cap. Brickwork is the sum of the volumes of each prism; pointing is the exposed surface area only.

Assumed data

  • Footing step 1: 1.50 m × 1.50 m × 0.30 m; step 2: 1.20 m × 1.20 m × 0.30 m (both below ground, so not pointed).
  • Shaft: 0.90 m × 0.90 m × 2.40 m high; cap: 1.05 m × 1.05 m × 0.15 m. Brick in 1:6 cement mortar.

Brickwork

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Footing step 1: 1.50 × 1.50 × 0.3011.5001.5000.3000.675
Footing step 2: 1.20 × 1.20 × 0.3011.2001.2000.3000.432
Pier shaft 0.90 × 0.90 × 2.4010.9000.9002.4001.944
Cap course 1.05 × 1.05 × 0.1511.0501.0500.1500.165
Total3.216

Pointing (exposed faces above ground)

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Shaft, 4 faces40.9002.400–8.640
Cap, 4 vertical faces41.0500.150–0.630
Cap overhang underside (1.05² − 0.90²)10.292––0.292
Cap top surface11.0501.050–1.103
Total10.665

Answer: Brickwork = 3.216 m³; pointing = 10.67 m² (assumed dimensions; for the actual figure take each step as length × breadth × height and each exposed face once).