Building: excavation, PCC, brick, wood work

Short answer

Centre-line method gives excavation 14.62 m³, PCC (1:3:6) 2.741 m³, superstructure brickwork 11.18 m³, and door/window frame timber 0.197 m³.

Prepare detailed estimate of the following items of works from the given building drawing attached fig 3. a) Earth work in excavation in foundation b) Plain cement concrete (1:3:6) in foundation. c) Brickwork in 1:6 C.S. in super structure wall. d) Wood work for door and window frame. [Fig 3: plan, overall length 7250 mm (1265 + 1200 + 2300 + 1200 + 1265), width 3730 mm with internal 3500 mm, 230 mm walls, internal clear 3270 mm each room, partition with door P1, door D 1200 × 2100, D1 1000 × 2100, window W 1500 × 1200, W1 1200 × 1200 (as printed '15400×1200'). Section X-X: 600 mm roof projection, 18 mm screed over 2 layers of tarfelt, roof slab, window 3270 wide, sill/lintel levels 2100 and 2400, DPC, plinth with 3 cm cement sand (1:1) pointing over 36 cement concrete (1:2:4), 75 thick brick bats soling, 150 sand filling, foundation PCC (1:3:6) 770 mm wide with 150/250/150 mm layers.]

Reading of the drawing

Two rooms of 3.27 m × 3.27 m clear side by side, 230 mm walls (3 × 0.23 + 2 × 3.27 = 7.23 m; 3.27 + 2 × 0.23 = 3.73 m). Centre-line length of outer walls = 2[(7.23 − 0.23) + (3.73 − 0.23)] = 21.00 m. The central partition is 3.27 + 0.23 = 3.50 m between the outer-wall centre lines; at its two T-junctions it is shortened by half the width of the outer-wall item at each end, so it is 3.50 − 0.77 = 2.73 m for the trench and PCC, and 3.50 − 0.23 = 3.27 m for the wall.

Foundation profile assumed from the section: PCC 1:3:6, 0.77 m wide × 0.15 m; brick step 0.69 m × 0.25 m; step 0.46 m × 0.15 m; 230 mm wall, trench depth 0.80 m; plinth 0.45 m above GL. Wall height above plinth (floor to slab soffit) = 2.4 m. Openings assumed: D 1.2 × 2.1 (1 no.), D1 1.0 × 2.1 (1 no., partition), W 1.5 × 1.2 (2 nos.), W1 1.2 × 1.2 (1 no.).

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, outer walls121.0000.7700.80012.936
Trench, partition (3.50 − 0.77)12.7300.7700.8001.682
Total14.618

b) PCC (1:3:6) in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC 1:3:6, outer walls121.0000.7700.1502.426
PCC 1:3:6, partition12.7300.7700.1500.315
Total2.741

c) Brickwork in 1:6 c.s. in superstructure wall

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.23 × 2.4 above plinth (21.00 + 3.27)124.2700.2302.40013.397
Deduct D 1.2×2.1-11.2000.2302.100-0.580
Deduct D1 1.0×2.1-11.0000.2302.100-0.483
Deduct W 1.5×1.2-21.5000.2301.200-0.828
Deduct W1 1.2×1.2-11.2000.2301.200-0.331
Total11.175

d) Wood work for door and window frames

Frame section assumed 100 × 75 mm (doors have no sill member).

FrameNo.L (m)B (m)H/D (m)Qty (m³)
Frame D (2×2.1 + 1×1.2)15.4000.1000.0750.0405
Frame D1 (2×2.1 + 1×1.0)15.2000.1000.0750.0390
Frame W (2×1.2 + 2×1.5)25.4000.1000.0750.0810
Frame W1 (2×1.2 + 2×1.2)14.8000.1000.0750.0360
Total0.1965

Answer: Excavation 14.62 m³; PCC 2.741 m³; superstructure brickwork 11.18 m³; frame timber 0.197 m³.