- 2080 Baisakh · 3+2+4+3 marks
Building: excavation, PCC, brick, wood work
Short answer
Centre-line method gives excavation 14.62 m³, PCC (1:3:6) 2.741 m³, superstructure brickwork 11.18 m³, and door/window frame timber 0.197 m³.
Prepare detailed estimate of the following items of works from the given building drawing attached fig 3. a) Earth work in excavation in foundation b) Plain cement concrete (1:3:6) in foundation. c) Brickwork in 1:6 C.S. in super structure wall. d) Wood work for door and window frame. [Fig 3: plan, overall length 7250 mm (1265 + 1200 + 2300 + 1200 + 1265), width 3730 mm with internal 3500 mm, 230 mm walls, internal clear 3270 mm each room, partition with door P1, door D 1200 × 2100, D1 1000 × 2100, window W 1500 × 1200, W1 1200 × 1200 (as printed '15400×1200'). Section X-X: 600 mm roof projection, 18 mm screed over 2 layers of tarfelt, roof slab, window 3270 wide, sill/lintel levels 2100 and 2400, DPC, plinth with 3 cm cement sand (1:1) pointing over 36 cement concrete (1:2:4), 75 thick brick bats soling, 150 sand filling, foundation PCC (1:3:6) 770 mm wide with 150/250/150 mm layers.]
Reading of the drawing
Two rooms of 3.27 m × 3.27 m clear side by side, 230 mm walls (3 × 0.23 + 2 × 3.27 = 7.23 m; 3.27 + 2 × 0.23 = 3.73 m). Centre-line length of outer walls = 2[(7.23 − 0.23) + (3.73 − 0.23)] = 21.00 m. The central partition is 3.27 + 0.23 = 3.50 m between the outer-wall centre lines; at its two T-junctions it is shortened by half the width of the outer-wall item at each end, so it is 3.50 − 0.77 = 2.73 m for the trench and PCC, and 3.50 − 0.23 = 3.27 m for the wall.
Foundation profile assumed from the section: PCC 1:3:6, 0.77 m wide × 0.15 m; brick step 0.69 m × 0.25 m; step 0.46 m × 0.15 m; 230 mm wall, trench depth 0.80 m; plinth 0.45 m above GL. Wall height above plinth (floor to slab soffit) = 2.4 m. Openings assumed: D 1.2 × 2.1 (1 no.), D1 1.0 × 2.1 (1 no., partition), W 1.5 × 1.2 (2 nos.), W1 1.2 × 1.2 (1 no.).
a) Earthwork in excavation in foundation
| Item | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| Trench, outer walls | 1 | 21.000 | 0.770 | 0.800 | 12.936 |
| Trench, partition (3.50 − 0.77) | 1 | 2.730 | 0.770 | 0.800 | 1.682 |
| Total | 14.618 |
b) PCC (1:3:6) in foundation
| Item | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| PCC 1:3:6, outer walls | 1 | 21.000 | 0.770 | 0.150 | 2.426 |
| PCC 1:3:6, partition | 1 | 2.730 | 0.770 | 0.150 | 0.315 |
| Total | 2.741 |
c) Brickwork in 1:6 c.s. in superstructure wall
| Item | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| Wall 0.23 × 2.4 above plinth (21.00 + 3.27) | 1 | 24.270 | 0.230 | 2.400 | 13.397 |
| Deduct D 1.2×2.1 | -1 | 1.200 | 0.230 | 2.100 | -0.580 |
| Deduct D1 1.0×2.1 | -1 | 1.000 | 0.230 | 2.100 | -0.483 |
| Deduct W 1.5×1.2 | -2 | 1.500 | 0.230 | 1.200 | -0.828 |
| Deduct W1 1.2×1.2 | -1 | 1.200 | 0.230 | 1.200 | -0.331 |
| Total | 11.175 |
d) Wood work for door and window frames
Frame section assumed 100 × 75 mm (doors have no sill member).
| Frame | No. | L (m) | B (m) | H/D (m) | Qty (m³) |
|---|---|---|---|---|---|
| Frame D (2×2.1 + 1×1.2) | 1 | 5.400 | 0.100 | 0.075 | 0.0405 |
| Frame D1 (2×2.1 + 1×1.0) | 1 | 5.200 | 0.100 | 0.075 | 0.0390 |
| Frame W (2×1.2 + 2×1.5) | 2 | 5.400 | 0.100 | 0.075 | 0.0810 |
| Frame W1 (2×1.2 + 2×1.2) | 1 | 4.800 | 0.100 | 0.075 | 0.0360 |
| Total | 0.1965 |
Answer: Excavation 14.62 m³; PCC 2.741 m³; superstructure brickwork 11.18 m³; frame timber 0.197 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Building: excavation, PCC foundation, brick · Estimating and Costing, chapter 6
- Building: excavation, brick 1:4, wood work · Estimating and Costing, chapter 6
- Two-room building: excavation, PCC, brick, plaster · Estimating and Costing, chapter 6
- Building: excavation, brick, paneled door, plaster · Estimating and Costing, chapter 6
- Building: excavation, soling, PCC, brick to plinth · Estimating and Costing, chapter 6
- RCC frame building: excavation, brick, plaster · Estimating and Costing, chapter 6