Building: excavation, soling, PCC, brick to plinth

Short answer

Earthwork excavation for six column pits and wall trenches: 9.12 m3. Stone soling in foundation: 1.79 m3; sand filling in floor: 7.35 m3. PCC for RCC up to plinth beam (footings, columns, plinth beams): 4.15 m3. Brick infill walls up to plinth: 3.67 m3.

Calculate the following items of work from the attached building drawing. i) Earthwork in excavation ii) Stone soling in foundation and sand filling in floor. iii) PCC for RCC up to plinth beam iv) Brick work up to plinth [Figure: plan 7.90 m × 4.10 m with two rooms 3.5 × 3.5 m, columns 0.30 × 0.30 m, door D 1.0 × 2.1 m, window 1.8 × 1.5 m; wall section 0.35, 0.30, 0.30 m with 0.45 m plinth, 10 cm PCC, 15 cm stone soling, 30 cm sand filling; column footing 0.90 × 0.90 m, footing depth 1.00 m, plinth beam 0.30 × 0.30 m, 10 cm PCC and 15 cm stone soling below footing. Dimensions in metre, not to scale.]

Reading of the figure

Plan 7.90 × 4.10 m = columns 0.30 m + room 3.5 m + column 0.30 m + room 3.5 m + column 0.30 m (and 3.5 + 0.3 + 0.3 across). Six columns 0.30 × 0.30 m on a 3.8 m grid; beams and infill walls form 7 panels of 3.5 m clear (4 along the long sides, 3 across). The sketch is approximate, so these assumptions are made: column footing 0.90 × 0.90 m, 0.30 m thick RCC on 10 cm PCC and 15 cm stone soling, bottom at 1.00 m below GL; 0.30 m thick brick wall panels in a 0.35 m wide trench 0.60 m deep (10 cm PCC + 15 cm soling at the bottom) up to the underside of the 0.30 × 0.30 m plinth beam; plinth top 0.45 m above GL.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Column footing pits 0.90 × 0.90 × 1.0060.9000.9001.0004.860
Wall trenches 0.35 wide × 0.60 deep (7 panels, 3.8 − 0.9 each)72.9000.3500.6004.263
Total9.123

ii) Stone soling in foundation and sand filling in floor

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Soling 15 cm under footings60.9000.9000.1500.729
Soling 15 cm under wall trenches72.9000.3500.1501.066
Total1.795
ItemNo.L (m)B (m)H/D (m)Qty (m³)
Sand filling 30 cm in two rooms 3.5 × 3.523.5003.5000.3007.350
Total7.350

Soling = 1.795 m³; sand filling = 7.35 m³.

iii) PCC (for RCC) up to plinth beam

Column height from footing top to plinth = 1.00 − 0.10 − 0.15 − 0.30 + 0.45 = 0.90 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Footings 0.90 × 0.90 × 0.3060.9000.9000.3001.458
Columns 0.30 × 0.30 × 0.90 (footing top to plinth)60.3000.3000.9000.486
Plinth beams 0.30 × 0.30, 3.5 m clear (7 panels)73.5000.3000.3002.205
Total4.149

iv) Brickwork up to plinth

Height below the beam = 0.60 − 0.10 − 0.15 + 0.45 − 0.30 = 0.50 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.30 thick × 0.50 m high, 7 panels of 3.5 m73.5000.3000.5003.675
Total3.675

Answer: Excavation 9.12 m³; soling 1.79 m³ and sand filling 7.35 m³; concrete for RCC 4.15 m³ (footings, columns, plinth beams); brickwork to plinth 3.67 m³.