Building: excavation, brick, plaster (18 marks)

Short answer

Centre-line outer walls 21.00 m, partition shortened at junctions; deductions for openings made. Quantities: excavation 14.62 m³, foundation and plinth brickwork 9.67 m³, inside wall and ceiling plaster 73.13 m², superstructure brickwork 11.34 m³.

Estimate the quantities of the following items of work from the accompanying drawing: a) Earth work in excavation in foundation b) Brick work in foundation and plinth c) Inside wall and ceiling cement plaster d) Brick work in superstructure [Drawing: plan 7230 mm × 3730 mm; 230 mm walls; two rooms with 3270 mm clear spans, 3500 mm bays; doors D 1200 × 2100, D1 1000 × 2100; windows W 1200 × 1200, W1 1200 × 1200; section X-X: roof slab with 18 screed over two layers of tarfelt, 600 mm projection, window 3270 wide, heights 2100/2400/1200/900, DPC, floor: 3 cement sand (1:1) pointing over 36 cement concrete (1:2:4), 75 thick brick bats soling, 150 sand filling; foundation 770 mm wide PCC (1:3:6) with footings, layers 150/250/150/150/80 mm.]

Reading of the drawing

Plan: two rooms 3.27 × 3.27 m clear with 230 mm walls (overall 7.23 × 3.73 m, matching the given 7230 × 3730). Centre-line of the outer walls = 2[(7.23 − 0.23) + (3.73 − 0.23)] = 21.00 m. The central partition is 3.27 + 0.23 = 3.50 m between the outer-wall centre lines; at its two T-junctions it is shortened by half the width of the outer-wall item at each end: trench 3.50 − 0.77 = 2.73 m, step 1 3.50 − 0.69 = 2.81 m, step 2 3.50 − 0.46 = 3.04 m, wall 3.50 − 0.23 = 3.27 m.

Foundation section as marked: PCC 1:3:6 0.77 m wide × 0.15 m, brick step 0.69 × 0.25 m, brick step 0.46 × 0.15 m, 230 mm wall; assumed trench depth 0.80 m; plinth 0.45 m above GL (floor 150 mm sand, 75 mm brick soling, concrete, 1:1 pointing). Wall height 2.4 m above plinth, with door D 1.2 × 2.1 (1), D1 1.0 × 2.1 (1, between rooms), W 1.2 × 1.2 (2), W1 1.2 × 1.2 (1). Plaster 12 mm.

a) Earthwork in excavation in foundation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, outer walls121.0000.7700.80012.936
Trench, partition (3.50 − 0.77)12.7300.7700.8001.682
Total14.618

b) Brickwork in foundation and plinth

Wall height above step 2 = 0.80 − 0.15 − 0.25 − 0.15 + 0.45 = 0.70 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick step 0.69 × 0.25 (21.00 + 2.81)123.8100.6900.2504.107
Brick step 0.46 × 0.15 (21.00 + 3.04)124.0400.4600.1501.659
Wall 0.23 × 0.70 to plinth (21.00 + 3.27)124.2700.2300.7003.907
Total9.673

c) Inside wall and ceiling cement plaster

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls 2 rooms × 2(3.27+3.27) × 2.4126.1602.400–62.784
Deduct D (one face)-11.2002.100–-2.520
Deduct D1 (both faces)-21.0002.100–-4.200
Deduct windows W 1.2×1.2 (2) and W1 (1)-31.2001.200–-4.320
Ceiling 2 rooms × 3.27 × 3.2723.2703.270–21.386
Total73.130

d) Brickwork in superstructure

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall 0.23 × 2.4 above plinth124.2700.2302.40013.397
Deduct D 1.2×2.1-11.2000.2302.100-0.580
Deduct D1 1.0×2.1-11.0000.2302.100-0.483
Deduct W 1.2×1.2-21.2000.2301.200-0.662
Deduct W1 1.2×1.2-11.2000.2301.200-0.331
Total11.341

Answer: Excavation 14.62 m³; foundation and plinth brickwork 9.67 m³; plaster (walls and ceiling) 73.13 m²; superstructure brickwork 11.34 m³.