Short answer

Earthwork excavation for wall trench and pillar pits: 12.82 m3. Brickwork in 1:6 mortar up to plinth including footings: 6.33 m3. Sal wood door shutter 40 mm thick after frame deduction: 1.755 m2. Inside plaster 12 mm thick: 44.20 m2.

Estimate detailed quantities for the following items from attached building drawing: i) Earth work in excavation in foundation ii) Brick work in cement sand (1:6) mortar up to plinth iii) 40 mm thick sal work wood paneled door shutter iv) 12 mm thick inside cement plaster (1:6) [Figure: single room building with front verandah. Room 4.00 m × 4.50 m (as marked), verandah 2.00 m wide, 30 × 30 cm pillars, 30 cm walls with window; door 100 × 200 cm, window 100 × 140 cm, shelf 100 × 170 cm; steps tread 30, rise 15, 1.40 m / 2.00 m wide; wall section: 7.5 cm L.C. over 10 cm R.B. slab, 3.50 m height, 2.80 m and 2.20 m, 2 cm D.P.C., 45 cm plinth, 80 cm foundation with L.C. 10-30 cm layers; verandah pillar foundation 70 × 70 cm L.C. Details approximate.]

Reading of the figure

Room 4.0 × 4.5 m clear, 300 mm walls, 2.0 m verandah in front carried on three 30 × 30 cm pillars (pillar footings 70 × 70 cm); door 1.00 × 2.00 m, window 1.00 × 1.40 m, shelf 1.00 × 1.70 m (a recess, so its plaster surface is not deducted). Foundation taken as 0.80 m wide × 0.80 m deep: lime concrete 0.30 m, one brick step 0.60 m × 0.15 m, 300 mm wall; plinth 0.45 m; clear height 2.80 m.

Centre-line length = 2[(4.0 + 0.3) + (4.5 + 0.3)] = 18.20 m.

i) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Wall trench 0.80 wide × 0.80 deep118.2000.8000.80011.648
Pillar pits 0.70 × 0.70 × 0.80 (3 nos.)30.7000.7000.8001.176
Total12.824

ii) Brickwork in 1:6 up to plinth

Wall height above the step = 0.80 − 0.30 − 0.15 + 0.45 = 0.80 m.

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing 0.60 × 0.15118.2000.6000.1501.638
Wall 0.30 × 0.80 to plinth118.2000.3000.8004.368
Pillar brick step 0.50 × 0.50 × 0.1530.5000.5000.1500.112
Pillar 0.30 × 0.30 × (0.80−0.30−0.15+0.45)30.3000.3000.8000.216
Total6.335

iii) 40 mm thick sal wood panelled door shutter

Allowing 50 mm for the frame at each side and at the head: shutter = (1.00 − 2 × 0.05) × (2.00 − 0.05) = 0.90 × 1.95 = 1.755 m² (1 no.).

iv) 12 mm inside cement plaster (1:6)

ItemNo.L (m)B (m)H/D (m)Qty (m²)
Inside walls 2(4.0+4.5) × 2.80117.0002.800–47.600
Deduct door 1.0×2.0-11.0002.000–-2.000
Deduct window 1.0×1.4-11.0001.400–-1.400
Total44.200

Answer: Excavation 12.82 m³; brickwork to plinth 6.33 m³; door shutter 1.755 m²; inside plaster 44.20 m² (assumed details).