- Asked 2/22
- 2079 Bhadra · 4×2 marks
Well foundation: sinking, brick, sand filling, PCC
Short answer
Outer area 5.309 m², inner 3.142 m², ring 2.168 m². Sinking: outer area × 14 m = 74.33 m³. Brickwork: ring area × 14.20 m = 30.78 m³. Sand filling: inner area × 13.75 m = 43.20 m³. PCC cover: inner area × 0.45 m = 1.414 m³.
Work out quantity of well foundation for bridge. The well is to be circular of 2 m internal diameter with 300 mm thick masonry wall in 1:6 cement sand mortar. The well is founded in strata 14.00 m thick. Water table remains at 3.80 m depth. Well curb at bottom is RCC with M25 grade concrete mix and is 400 mm deep. The well rises 60 cm above ground level. Top of well is to be sealed with 0.45 m thick (1:4:8) cement concrete as well cover. Estimate quantities for the following works. a) Sinking of well. b) Brick masonry work in (1:6) cement sand mortar. c) Sand filling. d) PCC for RCC in well cover.
Data. Internal dia 2.0 m; wall 0.30 m, so outer dia = 2.60 m. Depth of well below GL = 14.0 m (curb included); well rises 0.6 m above GL; curb 0.4 m; cover 0.45 m thick placed inside the top of the bore.
- Outer area m²; inner area m²; ring area m².
a) Sinking of well
74.33 m³ (of this, 3.8 m is above the water table: 20.18 m³ and 54.15 m³ below it, which is priced separately if required).
b) Brick masonry (1:6)
Height = 14.0 − 0.4 + 0.6 = 14.20 m; volume = 2.168 × 14.20 = 30.78 m³.
c) Sand filling
Filling goes from the top of the curb to the underside of the cover: height = 14.0 + 0.6 − 0.4 − 0.45 = 13.75 m; volume = 3.142 × 13.75 = 43.20 m³.
d) PCC (1:4:8) in well cover
Volume = 1.414 m³.
Answer: Sinking 74.33 m³; brickwork 30.78 m³; sand filling 43.20 m³; well cover concrete 1.414 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Well foundation, 5 m internal diameter · Estimating and Costing, chapter 6 · asked 2×
- Well foundation, 4.5 m internal diameter · Estimating and Costing, chapter 6 · asked 2×
- Building: excavation, PCC, brick, wood work · Estimating and Costing, chapter 6
- Well foundation of pier: PCC and steel · Estimating and Costing, chapter 6
- Two-room building: excavation, PCC, brick, plaster · Estimating and Costing, chapter 6
- Building: brick 1:6, ceiling plaster, PCC · Estimating and Costing, chapter 6
- Brick and mortar for 230 mm wall (100 kN/m) · Concrete Technology and Masonry Structure, chapter 8 · asked 7×
- Brick and mortar for 250 mm wall (350 kN/m) · Concrete Technology and Masonry Structure, chapter 8 · asked 7×