- 2081 Bhadra · 4 marks
Well foundation of pier: PCC and steel
Short answer
M20 concrete in steining is 612.61 m3 (upper 1 m thick 188.50 m3, lower 2 m thick 424.12 m3); adding two 1 m plugs gives 689.58 m3. Steel at 1.5% by volume is 72.13 tonnes.
A well foundation for pier of a bridge is to be constructed. It has 7 meters internal diameter and 15 metres depth from river bed level to top of well curb. Well steining of 1 meter thickness is to be constructed up to 7.5 metres depth and remaining of 2 m thickness with M20 RCC. There are two plugs of M20 concrete at top and middle of 1 m thickness. Find out i) Quantity of PCC for M20 RCC works ii) Steel reinforcement for M20 RCC work well steining (1.5% of PCC by volume)
Meaning of the data. The well steining is 1.0 m thick for the top 7.5 m of the 15 m depth and 2.0 m thick for the remaining 7.5 m (M20 RCC). Two 1.0 m thick M20 plugs are placed at the top and middle of the well.
i) Quantity of concrete in the steining
Annular volume = , with m.
- Upper steining ( m, m): m³
- Lower steining ( m, m): m³
Total M20 concrete in steining = 188.496 + 424.115 = 612.61 m³.
Plugs (2 nos., 1.0 m thick, 7 m dia): m³ of M20 plain concrete.
Total M20 concrete including the plugs = 612.61 + 76.97 = 689.58 m³.
ii) Steel reinforcement in steining (1.5 % by volume)
Volume of steel = 0.015 × 612.611 = 9.189 m³.
Weight = 9.189 × 7850 kg/m³ = 72,135 kg = 72.13 tonnes.
Answer: Steining concrete = 612.61 m³ (plus 76.97 m³ in plugs, 689.58 m³ in all); steel = 72.13 t.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Well foundation, 4.5 m internal diameter · Estimating and Costing, chapter 6 · asked 2×
- Well foundation, 5 m internal diameter · Estimating and Costing, chapter 6 · asked 2×
- Well foundation: sinking, brick, sand filling, PCC · Estimating and Costing, chapter 6 · asked 2×
- Units: excavation, well steining, conductor, cornice · Estimating and Costing, chapter 1
- Bheri river suspension bridge collapse · Engineering Professional Practice, chapter 7
- Circular well 4 m, light and heavy well · Foundation Engineering, chapter 9
- River discharge with current meter constants a and b · Engineering Hydrology, chapter 4
- Economic diameter factors; penstock wall thickness (3 m) · Hydropower Engineering, chapter 6