Short answer

Surface excavation up to 30 cm deep is measured in m², deeper bulk excavation in m³; brickwork in well steining in m³ by ring volume; lightning conductor as a set or number; cornice in running metre.

Write the units of measurement and payment for the following items of work: (i) Surface excavation (ii) Brick work in well steining (iii) Lightning conductor (iv) Cornice.

ItemUnit of measurementUnit of paymentNotes
(i) Surface excavationm² (excavation not more than 30 cm deep, over 1.5 m wide and over 10 m² on plan; depth stated). Deeper bulk excavation is measured in m³m²Length x width of the area, in the soil type and depth stated
(ii) Brick work in well steiningm³m³Mean circumference x thickness x height, or the ring volume pi x (D² - d²)/4 x height
(iii) Lightning conductorset (number) for the complete installation; extra length of conductor strip in mno. / setIncludes the air terminal, down conductor and earth pit
(iv) Cornicem (running metre), profile and girth givenmMeasured along the centre line of the cornice