Short answer

Using centre-line method for an assumed one-room building with RCC roof: excavation 15.23 m3, cement concrete 4.62 m3, first class brickwork 16.99 m3, RCC 2.61 m3. Deduct openings and lintels from brickwork; roof slab and lintels are measured under RCC.

Estimate the quantities of the following items of work from the accompanying drawing. a) Earthwork in excavation b) Cement concrete c) 1st class brick work d) RCC work [Drawing not included in the scanned paper]

No drawing is given. The method is therefore shown on an assumed one-room building with an RCC flat roof, using the centre-line method.

Assumed data

  • Room 4.5 m × 3.5 m clear; walls 0.23 m (first class brick in 1:6 cement mortar); centre-line length = 2(4.5 + 3.5 + 2 × 0.23) = 16.92 m.
  • Trench 0.90 m wide, 1.00 m deep; PCC 1:3:6, 0.20 m thick; two brick footing steps (0.69 m and 0.46 m wide, 0.15 m each); plinth 0.45 m above GL; ceiling height 3.0 m.
  • One door 1.0 × 2.1 m and two windows 1.2 × 1.2 m; RCC lintels 0.23 × 0.15 m with 0.2 m bearing on each side; roof slab 125 mm; floor PCC 100 mm.
  • Wall height from the last footing to the plinth top = 1.00 − 0.20 − 0.30 + 0.45 = 0.95 m.

a) Earthwork in excavation

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Trench, all walls (centre-line)116.9200.9001.00015.228
Total15.228

b) Cement concrete

ItemNo.L (m)B (m)H/D (m)Qty (m³)
PCC bed under walls116.9200.9000.2003.046
Floor PCC 1:4:8, 100 mm (room)14.5003.5000.1001.575
Total4.621

c) First class brick work (foundation, plinth and superstructure)

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Brick footing step 1 (0.69 m wide)116.9200.6900.1501.751
Brick footing step 2 (0.46 m wide)116.9200.4600.1501.167
Wall up to plinth116.9200.2300.9503.697
Wall above plinth, full length116.9200.2303.00011.675
Deduct door 1.00×2.10-11.0000.2302.100-0.483
Deduct window 1.20×1.20-21.2000.2301.200-0.662
Deduct lintel over door (1.00 m opening + 2 × 0.20 m bearing)-11.4000.2300.150-0.048
Deduct lintels over windows (1.20 m opening + 2 × 0.20 m bearing)-21.6000.2300.150-0.110
Total16.986

(The full lintels are deducted from the brickwork because they are measured under RCC work.)

d) RCC work

ItemNo.L (m)B (m)H/D (m)Qty (m³)
Roof slab, 125 mm (outer size of walls)14.9603.9600.1252.455
Lintel over door11.4000.2300.1500.048
Lintels over windows21.6000.2300.1500.110
Total2.614

Answer: Excavation = 15.23 m³; cement concrete = 4.62 m³; brickwork = 16.99 m³; RCC = 2.61 m³ (assumed dimensions; follow the same sequence for the actual drawing).