- 2074 Asoj · 12 marks
RCC slab culvert 1.5 m span: four items
Short answer
Excavation:5.880 m³. PCC (1:3:6) in foundation:2.940 m³. Brickwork in1:4 mortar:5.978 m³. PCC (1:2:4) for slab:1.470 m³.
Estimate the quantities of the following items of work from the accompanying RCC slab culvert drawings: a) Earthwork in excavation in foundation b) PCC (1:3:6) in foundation c) Brick work in (1:4) cement mortar d) PCC (1:2:4) for RCC slab [Figure: R.C.C. slab culvert 1.50 m span with standard modular bricks. Overall length 4.90 m, 4.00 m roadway, 10 cm c.c. wearing coat, slab with 20 mm dia bars @ 30 cm c/c (alternate bent up), distribution bars 10 mm dia @ 25 cm c/c, 15 cm cover; abutment 1.20 m clear span, 40 cm wall, 70 cm, 30 cm footing, C.C. 1:3:6 foundation 30 cm thick, earth slope 1:1, 60 cm curb/kerb, 1.30 m, 1.00 m height; plan 4.80 m, 1.50 m, 1.20 m. Details hard to read in the scan.]
Reading of the drawing (some dimensions are hard to read; assumed values are stated)
- Roadway m + two kerbs of m: width of culvert m = length of abutment.
- Clear span between abutments m, bearing m each side, so slab span m; slab thickness m (assumed).
- Abutment: brick shaft m thick m high on a brick footing m wide m high; PCC (1:3:6) bed m wide m thick; bottom of PCC m below ground (footing + PCC).
a) Earthwork in excavation
m³
b) PCC (1:3:6) in foundation
m³
c) Brickwork in 1:4 mortar
Area of one abutment section m²
m³
d) PCC (1:2:4) for RCC slab
m³
Answer: excavation = 5.880 m³; PCC (1:3:6) = 2.940 m³; brickwork = 5.978 m³; slab concrete (1:2:4) = 1.470 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RCC slab culvert: excavation, PCC foundation, slab · Estimating and Costing, chapter 6
- RCC slab culvert (u): four items · Estimating and Costing, chapter 6
- Building: PCC, brick, sal wood frame, RCC slab · Estimating and Costing, chapter 6
- Well foundation: excavation, sinking, brick, PCC curb · Estimating and Costing, chapter 6 · asked 2×
- Building: excavation, PCC, brick, wood work · Estimating and Costing, chapter 6
- Building: excavation, PCC foundation, brick · Estimating and Costing, chapter 6