- 2076 Asoj · 10 marks
RCC slab culvert: excavation, PCC foundation, slab
Short answer
Based on assumed dimensions: excavation20.16 m³, PCC (1:3:6)4.032 m³, PCC (1:2:4) slab5.472 m³. Substitute actual drawing dimensions in same expressions.
Estimate the quantities of the following items of work from the accompanying RCC Slab Culvert drawings: a) Earthwork in excavation in foundation b) PCC (1:3:6) in foundation c) PCC (1:2:4) for RCC slab [Drawing not included in the scanned paper]
The drawing is not available, so the method is shown on a stated set of dimensions; the same steps are used for any slab culvert.
Assumed dimensions
- Clear span m, bearing of slab m on each abutment; slab thickness m.
- Width of culvert (measured across the road, i.e. along the stream) m (4.00 m roadway + 2 kerbs of 0.40 m); this is also the length of each abutment.
- Each abutment foundation: PCC (1:3:6) m wide m thick m long, with the bottom of excavation m below the ground.
a) Earthwork in excavation
m³
b) PCC (1:3:6) in foundation
m³
c) PCC (1:2:4) for RCC slab
Slab length m; m³
Answer (for the assumed drawing): excavation = 20.16 m³; PCC 1:3:6 = 4.032 m³; concrete 1:2:4 in slab = 5.472 m³. For the actual drawing, substitute its dimensions in the same expressions.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- RCC slab culvert (u): four items · Estimating and Costing, chapter 6
- Earthwork, concrete, brick, RCC from drawing · Estimating and Costing, chapter 6 · asked 2×
- Building: PCC, brick, sal wood frame, RCC slab · Estimating and Costing, chapter 6
- Aqueduct: excavation, concrete, brick, RCC · Estimating and Costing, chapter 6 · asked 2×
- Building: excavation, PCC foundation, brick · Estimating and Costing, chapter 6