Excavation:5.936 m³. Plain cement concrete foundation:2.544 m³. Brickwork:4.770 m³. RCC work in slab:3.339 m³.
Estimate the quantities of the following items of work from the accompanying drawing. a) Earthwork in excavation b) Cement concrete in foundation c) Brick work d) RCC work [Figure: RCC slab culvert; roadway 4 m, overall length 530 cm, 8 cm C.C. wearing coat, 22 cm thick road metal, slab 30 cm with 10 mm dia @ 22 c/c and 16 mm dia @ 10 c/c bars (alternate bars cranked), wall 50 cm × 90 cm, footing 80 cm × 30 cm, 45 degree earth slope, 150 cm, 140 cm, 120 cm, 500 cm length, 15 cm offsets. All dimensions in centimetres.]
Reading of the drawing (dimensions in the scan are hard to read; assumed values are stated)
- Overall length of culvert across the road m (4.00 m roadway plus kerbs). Clear span m.
- Abutment: wall m thick m high; C.C. foundation (1:3:6 assumed) m wide m thick; excavation to m depth (0.30 m C.C. plus 0.40 m below bed level).
- Slab m thick resting m on each abutment (span m). The wearing coat and road metal are not asked.
a) Earthwork in excavation
m³
b) Cement concrete in foundation
m³
c) Brickwork
m³
d) RCC work (slab)
m³
Answer: excavation = 5.936 m³; C.C. foundation = 2.544 m³; brickwork = 4.770 m³; RCC slab = 3.339 m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- RCC slab culvert: brick, wearing coat, GI pipe, steel · Estimating and Costing, chapter 6
- RCC slab culvert: excavation, PCC foundation, slab · Estimating and Costing, chapter 6
- Earthwork, concrete, brick, RCC from drawing · Estimating and Costing, chapter 6 · asked 2×
- Aqueduct: excavation, concrete, brick, RCC · Estimating and Costing, chapter 6 · asked 2×
- T-beam decking: RCC and wearing coat · Estimating and Costing, chapter 6 · asked 2×