- 2082 Bhadra
Underground RCC tank: brickwork, steel (fig a)
Short answer
Brickwork in 1:4 mortar = 2.780 m³. Steel in top RCC cover slab: 10 mm bars at 15 cm c/c both ways, with hooks and alternatte cranked bars, total weight = 33.3 kg.
Calculate quantities for the following items of works for an underground RCC water tank given below: a) First class brickwork in 1:4 c/s mortar b) Steel reinforcement in top RCC cover slab [Figure a: Underground RCC water tank. Plan: outer 300 cm wide, brick wall 23 cm thick with 12 cm and 35 cm offsets/projections, inner opening 200 cm × 100 cm, 200 cm. Section A-A: overall 276 cm wide, top RCC cover slab 20 cm thick with 10 mm dia all-bent-up bars and 10 mm dia main bars @ 15 cm c/c, 10 mm dia distribution bars @ 15 cm c/c, internal height 60 cm + 137 cm + 60 cm as marked, brickwork (1:4) 23 cm at top and 35 cm at base, M20 RCC floor, PCC (1:3:6) and flat brick soling below. Figure dimensions are hard to read in the scan.]
Assumptions (figure dimensions are hard to read)
- Clear internal size of tank m; internal clear height m.
- Brick wall (1:4): bottom part m thick and m high (12 cm offset on the outer face), top part m thick and m high; total m.
- Top cover slab: cm thick RCC, resting on the 23 cm wall at both ends, so its size is m. Clear cover mm.
- 10 mm bars at 15 cm c/c in both directions; main bars in the short direction, alternate bars cranked up; distribution bars in the long direction; hooks m at each end of main and distribution bars; crank extra m at each of the two cranks.
(a) Brickwork in 1:4 mortar (centre-line method)
| Part | Centre-line length (m) | Thickness (m) | Height (m) | Volume (m³) |
|---|---|---|---|---|
| Lower wall | 0.35 | 0.60 | 1.554 | |
| Upper wall | 0.23 | 0.77 | 1.226 | |
| Total | 2.780 |
(b) Steel in the top cover slab
- Number of main bars ; of these 8 are cranked and 9 are straight.
- Straight main bar length m; cranked bar m.
- Number of distribution bars , each m.
- Weight per metre of 10 mm bar kg/m.
| Bars | Number | Length each (m) | Total length (m) | Weight (kg) |
|---|---|---|---|---|
| Main, straight | 9 | 1.590 | 14.31 | 8.83 |
| Main, cranked | 8 | 1.708 | 13.66 | 8.43 |
| Distribution | 10 | 2.590 | 25.90 | 15.99 |
| Total | 33.25 |
Answer: brickwork = 2.780 m³; steel in top slab = 33.3 kg.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Underground RCC tank: brickwork 1:4, M20 PCC, steel · Estimating and Costing, chapter 6
- Underground RCC tank: brick, PCC, steel (1% steel) · Estimating and Costing, chapter 6
- RCC slab culvert: brick, wearing coat, GI pipe, steel · Estimating and Costing, chapter 6
- Underground water tank: excavation, brick, plaster · Estimating and Costing, chapter 6
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- RCC slab culvert (u): four items · Estimating and Costing, chapter 6
- First class brickwork in 1:6 mortar numerical · Building Technology, chapter 3
- Horizontal crack below RCC slab · Building Technology, chapter 10