Underground RCC tank: brick, PCC, steel (1% steel)

Short answer

On assumed dimensions, brickwork by centre-line method: 3.767 m³. PCC for floor and top slab (deducting manhole) is 2.255 m³. Steel at 1% of RCC volume weighs177.0 kg.

Prepare detailed estimate for the following items of works for an underground RCC water tank given in Figure 1. i) Brickwork ii) PCC for RCC works iii) Steel reinforcement in RCC works (assume 1% steel) [Figure 1 not included in the scanned paper]

Figure 1 is not available, so the working is shown on assumed dimensions; the method is the same for any drawing.

Assumed dimensions

  • Clear internal size 3.00×2.003.00 \times 2.00 m, clear depth 1.501.50 m.
  • Brick walls 0.230.23 m thick in 1:4 mortar, 1.501.50 m high, resting on a 0.150.15 m RCC floor.
  • RCC floor 0.150.15 m thick and top cover slab 0.120.12 m thick, both of outer size (3.00+0.46)×(2.00+0.46)=3.46×2.46(3.00 + 0.46) \times (2.00 + 0.46) = 3.46 \times 2.46 m; a 0.60×0.600.60 \times 0.60 m manhole opening in the cover.
  • Steel 1%1\% of the volume of RCC; density 78507850 kg/m³.

i) Brickwork (centre-line method)

Centre-line length =2 [(3.00+0.23)+(2.00+0.23)]=10.92= 2\,[(3.00 + 0.23) + (2.00 + 0.23)] = 10.92 m

V=10.92×0.23×1.50=3.767V = 10.92 \times 0.23 \times 1.50 = 3.767 m³

ii) PCC (concrete) for the RCC works

MemberWorkingVolume (m³)
Floor slab3.46×2.46×0.153.46 \times 2.46 \times 0.151.277
Top slab3.46×2.46×0.123.46 \times 2.46 \times 0.121.021
Deduct manhole0.60×0.60×0.120.60 \times 0.60 \times 0.12−0.043
Total2.255

iii) Steel reinforcement

W=1%×2.255×7850=177.0W = 1\% \times 2.255 \times 7850 = 177.0 kg

Answer (for the assumed figure): brickwork = 3.767 m³; concrete in RCC = 2.255 m³; steel = 177.0 kg.