- 2082 Baisakh · 3×3 marks
Underground RCC tank: brick, PCC, steel (1% steel)
Short answer
On assumed dimensions, brickwork by centre-line method: 3.767 m³. PCC for floor and top slab (deducting manhole) is 2.255 m³. Steel at 1% of RCC volume weighs177.0 kg.
Prepare detailed estimate for the following items of works for an underground RCC water tank given in Figure 1. i) Brickwork ii) PCC for RCC works iii) Steel reinforcement in RCC works (assume 1% steel) [Figure 1 not included in the scanned paper]
Figure 1 is not available, so the working is shown on assumed dimensions; the method is the same for any drawing.
Assumed dimensions
- Clear internal size m, clear depth m.
- Brick walls m thick in 1:4 mortar, m high, resting on a m RCC floor.
- RCC floor m thick and top cover slab m thick, both of outer size m; a m manhole opening in the cover.
- Steel of the volume of RCC; density kg/m³.
i) Brickwork (centre-line method)
Centre-line length m
m³
ii) PCC (concrete) for the RCC works
| Member | Working | Volume (m³) |
|---|---|---|
| Floor slab | 1.277 | |
| Top slab | 1.021 | |
| Deduct manhole | −0.043 | |
| Total | 2.255 |
iii) Steel reinforcement
kg
Answer (for the assumed figure): brickwork = 3.767 m³; concrete in RCC = 2.255 m³; steel = 177.0 kg.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Underground RCC tank: brickwork 1:4, M20 PCC, steel · Estimating and Costing, chapter 6
- Underground RCC tank: brickwork, steel (fig a) · Estimating and Costing, chapter 6
- Building: PCC, brick, sal wood frame, RCC slab · Estimating and Costing, chapter 6
- Septic tank: excavation, brickwork, PCC · Estimating and Costing, chapter 6
- RCC slab culvert: brick, wearing coat, GI pipe, steel · Estimating and Costing, chapter 6
- RCC frame building: excavation, brick, plaster · Estimating and Costing, chapter 6