- 2080 Bhadra · 4+3+1 marks
Underground RCC tank: brickwork 1:4, M20 PCC, steel
Short answer
Brickwork in two steps by centre-line method:3.199 m³. M20 concrete for floor and lining wall totals1.446 m³. Steel at1% gives113.5 kg.
Drawing of an Underground RCC water tank is given below (Fig. 1). Prepare detailed estimate for the following items of works: i) Brickwork (1:4) ii) PCC for M20 RCC work iii) Steel reinforcement for M20 RCC work (assuming 1% steel) [Figure 1: plan 3000 mm × 2300 mm outside; brick wall 230 mm thick at top stepping to 380 mm at base with 150 mm offset; clear inside 1990 mm × 1290 mm; M20 RCC walls/floor 125 mm; 125 mm thick M25 RCC slab at top; section: 800 mm and 475 mm wall heights, overall 1450 mm, clear height 1150 mm; brickwork (1:4); PCC (1:3:6) base with flat brick soling. All dimensions in mm.]
Reading of Fig. 1
- Outside size at base m; clear inside m. Wall at the base is m of brick plus m of M20 RCC, so m and m (check).
- Brick wall: m thick for the lower m, stepping in by m on the outer face to m for the upper m (total brick height m = clear height m + floor m).
- Inside the brick: 125 mm M20 RCC lining wall, m high, and 125 mm M20 RCC floor. Top slab 125 mm M25 RCC (not part of the M20 quantity).
i) Brickwork (1:4), centre-line method
| Part | Centre-line length (m) | Thickness (m) | Height (m) | Volume (m³) |
|---|---|---|---|---|
| Lower | 0.38 | 0.475 | 1.639 | |
| Upper | 0.23 | 0.800 | 1.560 | |
| Total | 3.199 |
The upper wall's outer face is set in by m on each side, so its centre-line rectangle is m.
ii) Concrete for M20 RCC work
| Member | Working | Volume (m³) |
|---|---|---|
| Floor | 0.431 | |
| Lining wall | 1.015 | |
| Total M20 | 1.446 |
(For information, the M25 top slab is m³.)
iii) Steel in M20 RCC (1%)
kg
Answer: brickwork (1:4) = 3.199 m³; M20 concrete = 1.446 m³; steel = 113.5 kg.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Underground RCC tank: brickwork, steel (fig a) · Estimating and Costing, chapter 6
- Underground RCC tank: brick, PCC, steel (1% steel) · Estimating and Costing, chapter 6
- Building: excavation, PCC, brick, wood work · Estimating and Costing, chapter 6
- RCC slab culvert: brick, wearing coat, GI pipe, steel · Estimating and Costing, chapter 6
- T-beam decking: PCC for RCC and steel · Estimating and Costing, chapter 6
- RCC column with footing: concrete and steel · Estimating and Costing, chapter 6
- Detailed specification of RCC M20 column · Construction Management, chapter 12