- 2078 Bhadra · 3+5 marks
RCC column with footing: concrete and steel
Short answer
Column RCC 1:2:4: 0.337 m³ (0.3×0.3×3.75 m). Footing RCC: edge slab 0.45 m³ + frustum 0.232 m³ = 0.682 m³. Total 1.02 m³. Steel: main 12 mm (15 nos), distribution 10 mm (15), vertical 16 mm (4) and 12 mm (4), stirrups 6 mm (29 nos @15 cm), total mass 86.3 kg.
From the attached drawing (figure 2) of RCC column, estimate the following items. (i) RCC 1:2:4 in column (ii) Steel reinforcement work excluding formwork [Figure 2: Column footing 1.5 m × 1.5 m in plan, RCC 1:2:4, 20 cm thick at edge (sloping up to column) with 10 cm PCC 1:3:6 below; column 30 cm × 30 cm, 3.50 m above GL and 70 cm below GL; footing reinforcement 12 mm main bars @ 10 cm c/c and 10 mm distribution bars @ 10 cm c/c; column reinforcement 4–16 mm dia and 4–12 mm dia vertical bars; 6 mm dia stirrups @ 15 cm c/c; anchorage/development 45 times bar dia.]
The footing thickness at the column face is not given, so 0.45 m is assumed (0.20 m at the edge, sloping up 0.25 m to the column). The 1.5 m × 1.5 m footing has its bottom (of the RCC) 0.70 m below GL, and the 0.30 × 0.30 m column rises 3.50 m above GL.
i) RCC 1:2:4
Column (above footing top, height = 0.70 − 0.45 + 3.50 = 3.75 m):
0.30 × 0.30 × 3.75 = 0.337 m³
Footing (a slab plus a sloping pyramid frustum):
- Edge slab: 1.5 × 1.5 × 0.20 = 0.450 m³
- Frustum (prismoidal formula, m, , ): m³
- Footing total = 0.682 m³
Total RCC 1:2:4 (footing + column) = 0.337 + 0.682 = 1.020 m³. (PCC 1:3:6, 10 cm under footing = 1.5 × 1.5 × 0.10 = 0.225 m³.)
ii) Steel reinforcement (formwork excluded)
Cover 50 mm in footing, 25 mm in column; weight per metre = kg (d in mm).
| Bar | Working | Length (m) | Weight (kg) |
|---|---|---|---|
| 12 mm main, 15 bars | 15 × (1.5 − 0.10) | 21.00 | 18.67 |
| 10 mm distribution, 15 bars | 15 × 1.40 | 21.00 | 12.96 |
| 16 mm vertical, 4 bars | 4 × (4.20 − 0.05 + 45 × 0.016) | 19.48 | 30.78 |
| 12 mm vertical, 4 bars | 4 × (4.20 − 0.05 + 45 × 0.012) | 18.76 | 16.68 |
| 6 mm stirrups, 29 nos. | 29 × (4 × 0.25 + 2 × 10 × 0.006) | 32.48 | 7.22 |
| Total | 86.31 |
Number of stirrups = (4.20 − 0.10)/0.15 + 1, rounded up = 29. Bars per layer in the footing = 1.40/0.10 + 1 = 15. (Each column bar includes one 45d anchorage (development) allowance; hooks and bend allowances are ignored.)
Answer: RCC 1:2:4 = 1.02 m³ (column 0.337 m³, footing 0.682 m³); steel ≈ 86.3 kg.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Underground RCC tank: brickwork 1:4, M20 PCC, steel · Estimating and Costing, chapter 6
- RCC slab culvert 1.5 m span: four items · Estimating and Costing, chapter 6
- T-beam decking: PCC for RCC and steel · Estimating and Costing, chapter 6
- RCC slab culvert (u): four items · Estimating and Costing, chapter 6
- Underground RCC tank: brick, PCC, steel (1% steel) · Estimating and Costing, chapter 6
- Underground RCC tank: brickwork, steel (fig a) · Estimating and Costing, chapter 6
- Footing for 30x35 cm column, M25 · Design of RCC Structure, chapter 11
- Footing, 450x500 column, 6#20, uniaxial moment · Design of RCC Structure, chapter 11
- Footing 300x400 column, factored moment 120 kNm · Design of RCC Structure, chapter 11
- Footing, 1250 kN column load, depth 1.8 m · Design of RCC Structure, chapter 11