Detailed specification of RCC M20 column
Short answer
M20 concrete (1:1.5:3), w/c ≤0.50, slump 50–75 mm. Clear cover 40 mm, compacted by needle vibrator in layers ≤450 mm. Formwork removed after 24–48 h. Curing 7 days. Concrete measured in m³, steel in kg, formwork in m².
Write a detailed specification of RCC with M20 concrete in column.
Detailed specification: RCC M20 concrete in columns
Scope: Providing and casting reinforced cement concrete of grade M20 (nominal mix 1 : 1.5 : 3, characteristic strength 20 N/mm² at 28 days) in columns, including formwork, reinforcement, curing and finishing, as per IS 456:2000 and the drawings.
Materials
- Cement: OPC 43 grade/PPC, fresh and in good condition; minimum cement content 300 kg/m³ (IS 456 Table 5).
- Fine aggregate: clean river sand, zone II, free of silt and organic matter.
- Coarse aggregate: crushed stone, hard and angular, graded 20 mm down; flaky particles within limits.
- Water: potable; water-cement ratio not more than 0.50 (max 0.55 for mild exposure).
- Steel: Fe 415/Fe 500 deformed bars as per drawing, free from rust and oil.
Formwork: rigid, tight, plumb steel or timber/plywood shuttering with proper bracing, oiled with release agent. Cleaned and checked before concreting.
Reinforcement: cut, bent and placed as per bar bending schedule, tied with binding wire; clear cover 40 mm for columns (IS 456 clause 26.4.2.1) using cover blocks; lap lengths and stirrup spacing as per drawing.
Concreting
- Batching by weight preferably, or by volume using gauge boxes in a mechanical mixer; mixing for at least 2 minutes.
- Slump 50–75 mm for columns.
- Concrete is placed within 30 minutes of mixing, in layers of 300–450 mm, from a height less than 1.5 m to avoid segregation, and compacted by a needle vibrator to remove air voids.
- Place columns in a continuous pour; the construction joint at 25–50 mm below the beam soffit when needed.
Stripping of forms: vertical column forms may be removed after 24–48 hours (IS 456 clause 11.3).
Curing: wet curing (gunny bags or ponding) for at least 7 days.
Testing: cube samples (150 mm) at least one set per 5 m³ per day, tested at 7 and 28 days; slump tests; average strength not less than 20 N/mm² and no individual result below 16 N/mm² per IS 456 acceptance criteria.
Tolerance: column plumb within 5 mm per 3 m; size ±5 mm.
Measurement and payment: concrete in m³ (net, no deduction for steel), reinforcement in kg (as per bar bending schedule), formwork in m². Rates include all materials, labour, vibration, curing and scaffolding.
Related questions
- Types of specification: general and detailed · Construction Management, chapter 12 · asked 7×
- Detailed specification of brick work in 1:4 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of brick work in 1:6 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of cement sand mortar 1:4 · Construction Management, chapter 12 · asked 2×
- Detailed specification of cement sand mortar 1:6 · Construction Management, chapter 12 · asked 2×
- Detailed specification of cement plaster 1:4 · Construction Management, chapter 12
- Cost of M20 PCC for RCC column · Estimating and Costing, chapter 4
- RCC column with footing: concrete and steel · Estimating and Costing, chapter 6
- Underground RCC tank: brickwork 1:4, M20 PCC, steel · Estimating and Costing, chapter 6
- Rate analysis: M20 (1:1½:3) RCC per 10 m³ · Estimating and Costing, chapter 4