Rate analysis: M20 (1:1½:3) RCC per 10 m³

Short answer

For 10 m³ M20 (1:1.5:3) concrete, dry volume 15.4 m³ requires 80.64 bags cement, 4.2 m³ sand, 8.4 m³ aggregate. After labour and plant, with 15% overhead and 10% profit, rate = NPR 294,800 per 10 m³ (29,480/m³).

Prepare an analysis of rate for M20 (1:1½:3) for RCC work per 10 m³.

Rates and labour norms below are illustrative (DUDBC-style); use the current District Rate for a real estimate. Cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled NPR 1,500/day, unskilled NPR 1,100/day, overhead 15%, profit 10%. The rate is for concrete only; formwork and reinforcement are paid separately.

Quantities for 10 m³ of M20 (1:1½:3)

  • Dry volume =1.54×10=15.40= 1.54 \times 10 = 15.40 m³; sum of ratio =5.5= 5.5
  • Cement =1/5.5×15.40=2.800= 1/5.5 \times 15.40 = 2.800 m³ =80.64= 80.64 bags
  • Sand =1.5/5.5×15.40=4.200= 1.5/5.5 \times 15.40 = 4.200 m³; aggregate =3/5.5×15.40=8.400= 3/5.5 \times 15.40 = 8.400 m³
  • Labour: 12 skilled and 70 unskilled days per 10 m³ (mixing, lifting, placing, vibrating, curing; assumed norm).

Analysis

ItemQtyUnitRate (NPR)Amount (NPR)
Cement80.64bag1,000.0080,640.00
Sand4.200m³3,500.0014,700.00
Coarse aggregate (20 mm)8.400m³4,500.0037,800.00
Skilled labour (mason)12.0day1,500.0018,000.00
Unskilled labour70.0day1,100.0077,000.00
Mixer, vibrator and fuel (lump)1LS6,500.006,500.00
Water and curing (lump)1LS1,200.001,200.00
Direct cost235,840.00
Contractor's overhead @ 15%35,376.00
Contractor's profit @ 10%23,584.00
Total (rate per 10 m³)294,800.00

Rate of M20 RCC (concrete only) = NPR 294,800.00 per 10 m³ (NPR 29,480.00 per m³).