- 2067 Asar (old course) · 6 marks
Rate analysis: M20 (1:1½:3) RCC per 10 m³
Short answer
For 10 m³ M20 (1:1.5:3) concrete, dry volume 15.4 m³ requires 80.64 bags cement, 4.2 m³ sand, 8.4 m³ aggregate. After labour and plant, with 15% overhead and 10% profit, rate = NPR 294,800 per 10 m³ (29,480/m³).
Prepare an analysis of rate for M20 (1:1½:3) for RCC work per 10 m³.
Rates and labour norms below are illustrative (DUDBC-style); use the current District Rate for a real estimate. Cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled NPR 1,500/day, unskilled NPR 1,100/day, overhead 15%, profit 10%. The rate is for concrete only; formwork and reinforcement are paid separately.
Quantities for 10 m³ of M20 (1:1½:3)
- Dry volume m³; sum of ratio
- Cement m³ bags
- Sand m³; aggregate m³
- Labour: 12 skilled and 70 unskilled days per 10 m³ (mixing, lifting, placing, vibrating, curing; assumed norm).
Analysis
| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---|---|---|---|
| Cement | 80.64 | bag | 1,000.00 | 80,640.00 |
| Sand | 4.200 | m³ | 3,500.00 | 14,700.00 |
| Coarse aggregate (20 mm) | 8.400 | m³ | 4,500.00 | 37,800.00 |
| Skilled labour (mason) | 12.0 | day | 1,500.00 | 18,000.00 |
| Unskilled labour | 70.0 | day | 1,100.00 | 77,000.00 |
| Mixer, vibrator and fuel (lump) | 1 | LS | 6,500.00 | 6,500.00 |
| Water and curing (lump) | 1 | LS | 1,200.00 | 1,200.00 |
| Direct cost | 235,840.00 | |||
| Contractor's overhead @ 15% | 35,376.00 | |||
| Contractor's profit @ 10% | 23,584.00 | |||
| Total (rate per 10 m³) | 294,800.00 |
Rate of M20 RCC (concrete only) = NPR 294,800.00 per 10 m³ (NPR 29,480.00 per m³).
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: M20 PCC, raft foundation · Estimating and Costing, chapter 4
- Rate analysis: brickwork 1:6 per m³ · Estimating and Costing, chapter 4 · asked 2×
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Rate analysis: sal wood door/window frame per m³ · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 20 mm plaster 1:4 per 100 m² · Estimating and Costing, chapter 4 · asked 3×
- Symbol rate, entropy and information rate (6 symbols per 10 μs) · Communication Systems, chapter 6
- Detailed specification of RCC M20 column · Construction Management, chapter 12
- Ideal Brayton cycle: net work per kg and efficiency · Fundamental of Thermodynamics & Heat Transfer, chapter 6