Skip to main content

Rate analysis: M20 PCC, raft foundation

Short answer

For nominal mix 1:1.5:3, dry volume factor 1.54. Per m3: cement 8.06 bags, sand 0.42 m3, aggregate 0.84 m3, skilled 1 md, unskilled 7 md. Rate = Rs 21,900.60 per m3; raft cost = Rs 2,190,060.

Prepare the rate analysis for M20 PCC work in 10 m × 10 m × 1 m raft foundation.

Basis

Raft = 10 x 10 x 1 = 100 m³ of M20 concrete (nominal mix 1:1.5:3, IS 456 Table 9). Dry volume = 1.54 x wet volume. Rates are illustrative; mixing is manual (a concrete mixer would be preferred for this volume and would reduce the labour).

Quantities per m³

  • Cement = 1.54/5.5 = 0.2800 m³ = 8.06 bags
  • Sand = 1.54 x 1.5/5.5 = 0.4200 m³
  • Aggregate = 1.54 x 3/5.5 = 0.8400 m³

Rate analysis (per m³)

DescriptionQtyUnitRate (Rs)Amount (Rs)
Cement (0.2800 m³)8.06bag900.007,254.00
Sand (0.420 m³)0.42m³2,500.001,050.00
Aggregate 20 mm (0.840 m³)0.84m³3,500.002,940.00
Mason (skilled)1md1,200.001,200.00
Labour (unskilled)7md900.006,300.00
Water, curing, tools (L.S.)1L.S.300.00300.00
Sub-total19,044.00
Contractor's overhead and profit15%2,856.60
Rate per m³21,900.60

Quantities and cost for the raft (100 m³)

  • Cement = 806.4 bags; sand = 42.0 m³; aggregate = 84.0 m³
  • Skilled labour = 100 md; unskilled = 700 md
  • Cost = 100 x 21,900.60 = Rs 2,190,060.00

Answer: Rate of M20 PCC = Rs 21,900.60 per m³; cost of the 100 m³ raft concrete = Rs 2,190,060.00 (excluding formwork, reinforcement and VAT).

✓ Answer checked by Claude Opus 5.5 (high effort)