- 2076 Asoj · 6 marks
Rate analysis: 40 mm PCC 1:2:4 floor
Short answer
Per m² of 40 mm PCC (1:2:4): cement 0.253 bag, sand 0.0176 m³, aggregate 0.0352 m³; mason 0.08 day, unskilled 0.20 day; total rate NPR 1,022.50 (direct cost NPR 818.00 plus overhead and profit).
Prepare an analysis of rate for 40 mm thick PCC (1:2:4) in floor per m².
Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded).
Quantities per m² of 40 mm PCC (1:2:4)
- Wet volume m³; dry volume m³
- Cement m³ bags
- Sand m³; aggregate m³
- Labour for mixing, laying, compacting, levelling and curing: mason 0.08 day, labourer 0.20 day per m² (assumed norm).
Analysis of rate per m²
| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---|---|---|---|
| Cement | 0.253 | bag | 1,000.00 | 253.00 |
| Sand | 0.0176 | m³ | 3,500.00 | 61.60 |
| Coarse aggregate (12–20 mm) | 0.0352 | m³ | 4,500.00 | 158.40 |
| Skilled labour (mason, levelling and finishing) | 0.08 | day | 1,500.00 | 120.00 |
| Unskilled labour | 0.20 | day | 1,100.00 | 220.00 |
| Water and curing (lump) | 1 | LS | 5.00 | 5.00 |
| Direct cost | 818.00 | |||
| Contractor's overhead @ 15% | 122.70 | |||
| Contractor's profit @ 10% | 81.80 | |||
| Total (rate per m²) | 1,022.50 |
Rate = NPR 1,022.50 per m².
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: 25 mm 1:2:4 concrete floor · Estimating and Costing, chapter 4
- Rate analysis: 40 mm asphalt wearing coat · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 20 mm plaster 1:4 per 100 m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: PCC 1:3:6 per m³ · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Drainage rate: 300 mm in 3 days, growth factor 1.5 · Irrigation and Drainage Engineering, chapter 9 · asked 2×