Based on 20% wastage and 1.30 dry factor, dry mortar is 0.0195 m3/m2. For 10 m2, cement 0.936 bags and sand 0.1625 m3. Rate = Rs 433.39 per m2, including 15% overhead.

Prepare analysis of rate for 12.5 mm thick plaster with (1:5) cement sand mortar per 1 m².

Basis

12.5 mm thick plaster in cement mortar 1:5 on brick wall, worked for 10 m² and divided by 10. Rates are illustrative.

Mortar quantity

  • Wet volume per m² = 0.0125 m³; add 20% for filling uneven wall surface and wastage: 0.0150 m³.
  • Dry mortar = 0.0150 x 1.30 = 0.01950 m³ per m².
  • For 10 m²: dry mortar = 0.1950 m³; cement = 0.1950/6 = 0.03250 m³ = 46.8 kg = 0.936 bags; sand = 0.1625 m³.

Analysis (per 10 m²)

DescriptionQtyUnitRate (Rs)Amount (Rs)
Cement (0.03250 m³)0.936bag900.00842.40
Sand (0.1625 m³)0.1625m³2,500.00406.25
Mason (skilled)1.2md1,200.001,440.00
Helper (unskilled, incl. water and scaffolding)1.2md900.001,080.00
Sub-total3,768.65
Contractor's overhead and profit15%565.30
Total per 10 m²4,333.95

Answer: Rate of 12.5 mm 1:5 plaster = 4,333.95 / 10 = Rs 433.39 per m² (excluding VAT).