Rate analysis: brickwork 1:6 per m³
Short answer
For 1 m³ 1:6 brickwork in upper floor, use 561 bricks, 1.37 bags cement, 0.286 m³ sand, 2 masons, 3 helpers and scaffolding allowance. Sub-total Rs 15,963 plus 15% overhead gives Rs 18,357.45 per m³.
Prepare an analysis of rate for 1st class brick work in (1:6) cement mortar (in upper floor) per m³.
Basis
Rate per m³ of 1st class brickwork in 1:6 cement-sand mortar in the upper floor, standard brick 230 x 110 x 55 mm with 10 mm joints (nominal size 240 x 120 x 65 mm). All rates are illustrative.
Materials per m³
- Bricks (net) = nos.; with 5% breakage = 561 nos.
- Volume of bricks without mortar = 534.19 x 0.23 x 0.11 x 0.055 = 0.7433 m³, so wet mortar = 1 - 0.7433 = 0.2567 m³.
- Dry mortar = 0.2567 x 1.30 = 0.3337 m³ (30% for filling voids and shrinkage).
- Cement = 0.3337/7 = 0.0477 m³ x 1,440 kg/m³ = 68.6 kg = 1.37 bags.
- Sand = 0.3337 x 6/7 = 0.286 m³.
Analysis (per m³)
| Description | Qty | Unit | Rate (Rs) | Amount (Rs) |
|---|---|---|---|---|
| 1st class bricks (230x110x55), 534.19 net + 5% breakage | 561 | nos. | 15.00 | 8,415.00 |
| Cement (dry mortar 0.3337 m³ x 1/7 = 0.0477 m³) | 1.37 | bag | 900.00 | 1,233.00 |
| Sand (0.3337 x 6/7 = 0.2860 m³) | 0.286 | m³ | 2,500.00 | 715.00 |
| Mason (skilled) | 2 | md | 1,200.00 | 2,400.00 |
| Helper incl. carrying mortar and bricks up | 3 | md | 900.00 | 2,700.00 |
| Scaffolding and lifting allowance (upper floor) | 1 | L.S. | 500.00 | 500.00 |
| Sub-total (materials + labour) | 15,963.00 | |||
| Contractor's overhead and profit | 15% | 2,394.45 | ||
| Total | 18,357.45 |
Answer: Rate of 1:6 brickwork in the upper floor = Rs 18,357.45 per m³ (excluding VAT). The extra labour and scaffolding for the upper floor is the difference from the ground-floor rate.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: brickwork 1:4, 10 m³ · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Rate analysis: brick masonry 1:5, superstructure · Estimating and Costing, chapter 4
- Rate analysis: 25 mm 1:2:4 concrete floor · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 40 mm PCC 1:2:4 floor · Estimating and Costing, chapter 4
- First class brickwork in 1:6 mortar numerical · Building Technology, chapter 3
- Detailed specification of brick work in 1:4 mortar · Construction Management, chapter 12 · asked 5×
- Detailed specification of brick work in 1:6 mortar · Construction Management, chapter 12 · asked 5×
- Mortar for 10 m³ brickwork (1:4) numerical · Building Technology, chapter 3