Rate analysis: 25 mm 1:2:4 concrete floor

Short answer

For 100 m² of 25 mm thick 1:2:4 floor, wet volume 2.5 m³, dry volume 3.85 m³. Requires cement 15.84 bags, sand 1.10 m³, aggregate 2.20 m³, mason 8 days, labourer 14 days. Adding 15% overhead and 10% profit gives rate NPR 72,687.50 per 100 m² (NPR 726.88/m²).

Prepare analysis of rate for 25 mm thick 1:2:4 cement concrete floor per 100 m². (Assume suitable rate)

Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded). Aggregate of 12 mm size is taken at NPR 4,800/m³.

Quantities per 100 m²

  • Wet volume =100×0.025=2.5= 100 \times 0.025 = 2.5 m³; dry volume =1.54×2.5=3.850= 1.54 \times 2.5 = 3.850 m³
  • Cement =1/7×3.850=0.550= 1/7 \times 3.850 = 0.550 m³ =15.84= 15.84 bags
  • Sand =1.100= 1.100 m³; aggregate =2.200= 2.200 m³
  • Labour (assumed): mason 8 days, labourer 14 days per 100 m² for laying, levelling, finishing and curing.

Analysis

ItemQtyUnitRate (NPR)Amount (NPR)
Cement15.84bag1,000.0015,840.00
Sand1.100m³3,500.003,850.00
Aggregate (12 mm)2.200m³4,800.0010,560.00
Skilled labour (mason)8.0day1,500.0012,000.00
Unskilled labour14.0day1,100.0015,400.00
Water and curing (lump)1LS500.00500.00
Direct cost58,150.00
Contractor's overhead @ 15%8,722.50
Contractor's profit @ 10%5,815.00
Total (rate per 100 m²)72,687.50

Rate = NPR 72,687.50 per 100 m² (NPR 726.88 per m²).