- 2075 Asoj · 6 marks
Rate analysis: plain cement concrete (1:3:4)
Short answer
For 1 m³ PCC 1:3:4, dry volume 1.54 m³ gives cement 5.544 bags, sand 0.5775 m³, aggregate 0.77 m³. Labour: 1 skilled and 6 unskilled days. With 15% overhead and 10% profit, rate is NPR 23,975.32 per m³.
Prepare rate analysis of plain cement concrete (1:3:4). Assume suitable rates of material and labor.
Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded).
Quantities per m³ of PCC (1:3:4)
- Dry volume m³; sum of ratio
- Cement m³ bags
- Sand m³
- Aggregate m³
- Labour: 1.0 skilled and 6.0 unskilled days per m³ for mixing, placing, compacting and curing (assumed norm).
Analysis
| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---|---|---|---|
| Cement | 5.544 | bag | 1,000.00 | 5,544.00 |
| Sand | 0.5775 | m³ | 3,500.00 | 2,021.25 |
| Coarse aggregate | 0.7700 | m³ | 4,500.00 | 3,465.00 |
| Skilled labour | 1.000 | day | 1,500.00 | 1,500.00 |
| Unskilled labour | 6.000 | day | 1,100.00 | 6,600.00 |
| Water and curing (lump) | 1 | LS | 50.00 | 50.00 |
| Direct cost | 19,180.25 | |||
| Contractor's overhead @ 15% | 2,877.04 | |||
| Contractor's profit @ 10% | 1,918.03 | |||
| Total (rate per m³) | 23,975.32 |
Rate of PCC (1:3:4) = NPR 23,975.32 per m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: 25 mm 1:2:4 concrete floor · Estimating and Costing, chapter 4
- Importance of rate analysis; how rates taken · Estimating and Costing, chapter 4
- Brick (1:6) materials; PCC (1:2:4) rate · Estimating and Costing, chapter 4
- Rate analysis: one metric ton reinforcement · Estimating and Costing, chapter 4
- Rate analysis: brick masonry 1:5, superstructure · Estimating and Costing, chapter 4
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Theoretical strength of moist cured concrete (1 kg cement) · Concrete Technology and Masonry Structure, chapter 4
- Types of stresses in cement concrete pavement · Transportation Engineering II, chapter 2 · asked 2×
- Construction steps of cement concrete pavement · Transportation Engineering II, chapter 3
- Plain CC pavement thickness by IRC, 7 m highway · Transportation Engineering II, chapter 2