Rate analysis: plain cement concrete (1:3:4)

Short answer

For 1 m³ PCC 1:3:4, dry volume 1.54 m³ gives cement 5.544 bags, sand 0.5775 m³, aggregate 0.77 m³. Labour: 1 skilled and 6 unskilled days. With 15% overhead and 10% profit, rate is NPR 23,975.32 per m³.

Prepare rate analysis of plain cement concrete (1:3:4). Assume suitable rates of material and labor.

Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded).

Quantities per m³ of PCC (1:3:4)

  • Dry volume =1.54= 1.54 m³; sum of ratio =8= 8
  • Cement =1/8×1.54=0.1925= 1/8 \times 1.54 = 0.1925 m³ =5.544= 5.544 bags
  • Sand =3/8×1.54=0.5775= 3/8 \times 1.54 = 0.5775 m³
  • Aggregate =4/8×1.54=0.7700= 4/8 \times 1.54 = 0.7700 m³
  • Labour: 1.0 skilled and 6.0 unskilled days per m³ for mixing, placing, compacting and curing (assumed norm).

Analysis

ItemQtyUnitRate (NPR)Amount (NPR)
Cement5.544bag1,000.005,544.00
Sand0.5775m³3,500.002,021.25
Coarse aggregate0.7700m³4,500.003,465.00
Skilled labour1.000day1,500.001,500.00
Unskilled labour6.000day1,100.006,600.00
Water and curing (lump)1LS50.0050.00
Direct cost19,180.25
Contractor's overhead @ 15%2,877.04
Contractor's profit @ 10%1,918.03
Total (rate per m³)23,975.32

Rate of PCC (1:3:4) = NPR 23,975.32 per m³.