Brick 240x130x65 mm, 12 mm mortar yields 363 bricks/m³. Per m³: bricks 362.9, cement 1.609 bags, sand 0.2794 m³. Direct cost NPR 14,089.10; total with 15% overhead and 10% profit = NPR 17,611.38 per m³.
Prepare an analysis of rate of brick masonry in (1:5) cement mortar in super structure. Assume size of brick 240 × 130 × 65 mm and thickness of mortar joint is 12 mm.
Rates and labour norms below are illustrative (DUDBC-style norms; use the current District Rate and norms of the project area for a real estimate): cement NPR 1,000/bag, sand NPR 3,500/m³, 20 mm aggregate NPR 4,500/m³, skilled labour NPR 1,500/day, unskilled labour NPR 1,100/day, water lump sum, contractor's overhead 15% and profit 10% on direct cost (VAT excluded). Brick is taken at NPR 18 each.
Quantities per m³ of brickwork
- Brick with mortar m³; bricks per m³
- Brick volume m³; wet mortar m³
- Dry mortar m³; cement m³ bags; sand m³
- Labour (superstructure, assumed norm): mason 1.6 days, labourer 2.2 days per m³.
Analysis
| Item | Qty | Unit | Rate (NPR) | Amount (NPR) |
|---|---|---|---|---|
| Bricks 240 × 130 × 65 mm | 362.9 | no | 18.00 | 6,532.20 |
| Cement | 1.609 | bag | 1,000.00 | 1,609.00 |
| Sand | 0.2794 | m³ | 3,500.00 | 977.90 |
| Skilled labour (mason) | 1.6 | day | 1,500.00 | 2,400.00 |
| Unskilled labour | 2.2 | day | 1,100.00 | 2,420.00 |
| Water and scaffolding (lump) | 1 | LS | 150.00 | 150.00 |
| Direct cost | 14,089.10 | |||
| Contractor's overhead @ 15% | 2,113.37 | |||
| Contractor's profit @ 10% | 1,408.91 | |||
| Total (rate per m³) | 17,611.38 |
Rate of 1:5 brickwork in superstructure = NPR 17,611.38 per m³.
✓ Answer checked by Claude Opus 5.5 (high effort)
Related questions
- Rate analysis: 12.5 mm plaster 1:5, per m² · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: 12.5 mm plaster 1:3, per 100 m² · Estimating and Costing, chapter 4
- Rate analysis: 12 mm plaster 1:3 ceiling · Estimating and Costing, chapter 4 · asked 3×
- Rate analysis: brickwork 1:4, 10 m³ · Estimating and Costing, chapter 4
- Brick (1:6) materials; PCC (1:2:4) rate · Estimating and Costing, chapter 4
- Materials for 115 m³ brick masonry 1:3 · Estimating and Costing, chapter 4
- Brick and mortar for 230 mm wall (100 kN/m) · Concrete Technology and Masonry Structure, chapter 8 · asked 7×
- Brick and mortar for 250 mm wall (350 kN/m) · Concrete Technology and Masonry Structure, chapter 8 · asked 7×
- Brick and mortar for wall with timber flooring · Concrete Technology and Masonry Structure, chapter 8
- Single-storey external wall: stress, brick, mortar · Concrete Technology and Masonry Structure, chapter 8